Tofias v. Energy Facilities Siting Board

435 Mass. 340
CourtMassachusetts Supreme Judicial Court
DecidedNovember 14, 2001
StatusPublished
Cited by7 cases

This text of 435 Mass. 340 (Tofias v. Energy Facilities Siting Board) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tofias v. Energy Facilities Siting Board, 435 Mass. 340 (Mass. 2001).

Opinion

Sosman, J.

Arnold B. Tofias, trustee of the Julius Tofias Realty Trust (trust), has appealed from the decision of the Energy Facilities Siting Board (board) approving the proposal of Brock-ton Power, EEC (Brockton Power), to construct a power plant [341]*341in an industrial park in Brockton. G. L. c. 164, § 69P. The trust does not challenge any aspect of the proposal for the actual power generating facility, but objects to the proposed overhead transmission lines that would connect the plant to an existing electric company transmission line. The route for those transmission lines abuts the trust’s property, and the trust claims that the lines would adversely affect the property by the emission of electromagnetic fields (EMF). On appeal, the trust complains that the board erred in denying its motion to intervene as a party in the proceedings and limiting the trust’s status to that of an “interested person.” G. L. c. 30A, § 10 (4).3 The matter was reserved and reported to us by a single justice of this court. For the reasons set forth below, we conclude that the trust is not a “party in interest aggrieved by a decision of the board” and thus lacks standing to pursue an appeal of the board’s decision. G. L. c. 164, § 69P.

1. Background. Pursuant to G. L. c. 164, § 69J lk, Brockton Power petitioned the board for approval of a proposed 270 megawatt natural gas-fired generating facility to be located on a thirteen-acre parcel in an industrial park in Brockton. Electric output from the proposed facility would be carried by a new overhead 115 kilovolt transmission line running along a railroad right of way a distance of 3,500 feet, where it would then connect with an existing transmission line. The new transmission line would consist of three high-voltage power cables hung on seventy-four-foot transmission towers, spaced every 400 feet along the route.

The trust owns a vacant twenty-one acre parcel of land in Brockton. An existing 115 kilovolt power line runs across a comer near the southern boundary of the trust parcel. On its eastern boundary is an active railroad line. The area is zoned for industry, and various industrial uses are in the immediate vicinity of the trust’s vacant parcel. The trust parcel does not abut the site on which Brockton Power proposes to build its generating facility. However, in its original application, Brock-ton Power proposed to run a portion of the connecting transmis[342]*342sion line (approximately 1,360 feet) immediately adjacent to the eastern boundary of the trust property.

On March 10, 1999, the deadline for filing any petition to intervene or to participate as an interested person in the proceedings on Brockton Power’s application, the trust sought leave to intervene as a party. After identifying the trust’s ownership of its parcel and explaining its location in relation to the proposed transmission line, the trust’s petition to intervene identified its interest in the proceedings as follows: “ [Electromagnetic fields associated with transmission lines vary, in part, according to the distance from the source of the field .... The [Brockton Power] Petition does not disclose the precise alignment of the [Brockton Power] Line, but it is likely that the [trust] Parcel will be the property closest to the longest portion of the [Brock-ton Power] Line. Accordingly, the [trust] has a substantial and specific interest in seeing that the construction and operation of the [Brockton Power] Line does not lead to a substantial loss in the value of the [trust] Parcel.” No other basis for intervention was identified in the trust’s petition.4

On April 8, 1999, a board hearing officer denied the trust’s petition to intervene. The hearing officer noted that the petition to intervene contained nothing beyond the trust’s conclusory assertion that it would be substantially and specifically affected by the project, and that the trust “does not identify existing or likely future uses of its property that would be affected by environmental impacts from the transmission interconnection line.” The mere reference to the line’s generation of EMF “does not provide a nexus sufficient to establish substantial and specific effect” on the trust parcel, and alleged adverse effect on the value of the trust parcel did not come within the ambit of the statute. See G. L. c. 164, § 69J V4. Finally, the hearing of[343]*343ficer noted that the board had, in the past, allowed intervention by abutters to proposed power plants because “[p]ower plants are typically large structures with many potential attendant environmental impacts.” While the statutory definition of “generating facility” includes “transmission . . . interconnections,” transmission lines alone “do not automatically pose the same environmental impacts on abutters as might inure to abut-ters to the power plant itself.”5

Although denying the trust’s petition to intervene as a party, the hearing officer allowed the trust (and several other entities) to participate in the proceedings as “interested persons.” As an “interested person,” the trust was allowed to (and did) present argument, file briefs, and submit comment on the hearing officer’s tentative decision. Lacking status as a party, the trust was not allowed to conduct discovery, present evidence at the hearing, or cross-examine witnesses.

Prior to the hearing, the board had asked Brockton Power to consider whether modifications to the route for the transmission line might minimize the impacts (both visual and EMF) on nearby residential areas. In response, Brockton Power submitted an alternative route that would keep the line further from (and far less visible to) existing residences. At the hearing, Brockton Power expressed a willingness to make such a modification to the route if the board preferred that alternative.

Based on the fact that the alternative, if adopted, would run an additional segment of the line (another 518 feet in length) set back fifty feet from the northern boundary of the trust property, [344]*344the trust filed a renewed petition to intervene. In that renewed petition, the trust alleged that, in other properties it had developed, it had had to set buildings back from transmission lines, and that the placement of the proposed transmission line adjacent to two boundaries of the trust property (in combination with the existing transmission line on its southern boundary) would “substantially shrink the environmentally safe building ‘envelope’ on the [trust] Parcel.” The trust claimed that “[e]mployers will be reluctant to place employees underneath or near high-voltage lines, and companies will be unwilling to place sensitive electronic equipment on the site.”

The hearing officer treated the trust’s renewed petition as a motion for reconsideration, granted reconsideration in light of the potential change in the transmission line route, and again denied the petition to intervene. The hearing officer reasoned that the alleged claim of being substantially and specifically affected was speculative:

“[The] [t]rust’s arguments regarding potential future commercial uses in which people or electronic equipment might be affected by EMF or visual impacts are conjectural. In essence, [the trust] asks the [board] to postulate future commercial tenants who would be dissuaded from locating on the [trust] Parcel by transmission lines on three, but not on two or one, of its property boundaries.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Brockton Power Co. LLC v. EFSB/City of Brockton v. EFSB (No. 2)
469 Mass. 215 (Massachusetts Supreme Judicial Court, 2014)
Alliance to Protect Nantucket Sound, Inc. v. Department of Public Utilities
461 Mass. 166 (Massachusetts Supreme Judicial Court, 2011)
Providence & Worcester Railroad v. Energy Facilities Siting Board
899 N.E.2d 829 (Massachusetts Supreme Judicial Court, 2009)
Taylor v. Board of Appeals
863 N.E.2d 79 (Massachusetts Appeals Court, 2007)
Alliance to Protect Nantucket Sound, Inc. v. Energy Facilities Siting Board
858 N.E.2d 294 (Massachusetts Supreme Judicial Court, 2006)
Wood v. Metropolitan Nashville & Davidson County Government
196 S.W.3d 152 (Court of Appeals of Tennessee, 2005)
Liberty Mutual Insurance v. Commissioner of Insurance
16 Mass. L. Rptr. 95 (Massachusetts Superior Court, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
435 Mass. 340, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tofias-v-energy-facilities-siting-board-mass-2001.