Brockton Power Co. LLC v. EFSB/City of Brockton v. EFSB (No. 2)

469 Mass. 215
CourtMassachusetts Supreme Judicial Court
DecidedJuly 31, 2014
DocketSJC 11405, 11407
StatusPublished
Cited by6 cases

This text of 469 Mass. 215 (Brockton Power Co. LLC v. EFSB/City of Brockton v. EFSB (No. 2)) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Brockton Power Co. LLC v. EFSB/City of Brockton v. EFSB (No. 2), 469 Mass. 215 (Mass. 2014).

Opinion

Botsford, J.

On August 7, 2009, the Energy Facilities Siting Board (board), acting pursuant to G. L. c. 164, § 69PA (§ 69F4), approved the petition of Brockton Power Company LLC (Brockton Power or company), to build and operate a 350-megawatt combined-cycle energy generating facility (facility or project) powered by natural gas and ultra-low sulfur distillate (ULSD) in the city of Brockton (city). As approved by the board, the facility would use wastewater from the city’s advanced wastewater reclamation facility (AWRF) for its cooling tower. In a consolidated appeal by three of the interveners, we affirmed the board’s decision. See Brockton v. Energy Facilities Siting Bd. (No. 1), ante 196 (2014) (Brockton [No. 1 ]), decided today.

On April 9, 2010, while the consolidated appeal was pending, Brockton Power submitted a project change filing (PCF) to the board, seeking approval of three changes to its project. In the PCF, Brockton Power sought to (1) change the source of the facility’s cooling tower water from the AWRF to the Brockton municipal water supply (BMWS); (2) eliminate the use of ULSD as an alternative fuel and rely solely on natural gas as the *217 facility’s fuel; and (3) make certain changes in the design of the facility. After additional public comment, extensive discovery, testimony, and six days of evidentiary hearings that the board considered as a “continuation of the [original [proceeding,” the board issued its PCF decision, denying Brockton Power’s proposal to use BMWS but approving the two other project changes. 4 Brockton Power appealed from the board’s denial of the PCF with respect to the facility’s water source, 5 and the city appealed from the board’s approval of the design and fuel changes. A single justice of this court reserved and reported the appeals to the full court. We affirm the board’s final decision with respect to both appeals.

The scope of our review of the board’s PCF decision is the same as in Brockton (No. 1), supra, and is set forth in G. L. c. 164, § 69P. 6 The board’s evidentiary rulings are entitled to deference, and the appellants bear the burden of showing that the board’s decision is invalid. Alliance to Protect Nantucket Sound, Inc. v. Energy Facilities Siting Bd., 448 Mass. 45, 51 (2006) (Alliance I).

1. Board’s authority to consider PCF as part of original proceeding. In its August 7, 2009, final decision, the board required Brockton Power to notify it of “any changes other than minor variations to the proposal so that the [board] may decide whether to inquire further into a particular issue.” In addition to this general requirement, noting “the uncertainty . . . around the availability of the Brockton AWRF water supply,” the board directed Brockton Power to “work with the [city] regarding use of [the city’s] AWRF water, and to provide a report to the [board] with respect to the outcome of such efforts.” In the event that *218 Brockton Power determined not to use the AWRF water and instead “to use potable [municipal] water for the majority of the water requirements of its proposed facility,” the board directed the company to “provide a project change filing to the [board], together with a detailed analysis focused on those issues that are germane to the use of potable water, including opportunities for water conservation.”

Consistent with this directive, on April 9, 2010, Brockton Power submitted its PCF to the board seeking approval of a change in the source of the facility’s water supply for the cooling tower, approval of the nonuse of ULSD as an alternate fuel, and approval of building design changes. Over the objection of interveners, who argued that the PCF should be treated as a new petition, the board, as previously described, held evidentiary hearings on the PCF and issued a decision rejecting the proposed change in source of water supply for the cooling tower, but approving the two other changes.

Under § 69PÁ, fifth and sixth pars., the board may approve, reject in whole or in part, or conditionally approve a petition for an electrical generating facility. 7 The statute provides that “[i]n the event of rejection or conditional approval, the applicant may, within 180 days, submit an amended petition. Public and evidentiary hearings on the amended petition shall be held on the same terms and conditions applicable to the original petition.” G. L. c. 164, § 69PÁ, sixth par. See note 7, supra. The city contends that Brockton Power’s PCF was an “amended petition” within the meaning of § 69PÁ, sixth par., and because it was submitted on April 9, 2010, 245 days after the board issued its original decision, the board did not have the authority to consider *219 it as part of the original proceeding — the window for filing an amended petition had already closed. According to the city, the board should have reviewed the PCF as a new petition, which would have required readjudication of the full range of issues the board considered in its original decision issued on August 7, 2009. The city’s argument fails.

“We accord substantial discretion to an agency to interpret the statute it is charged with enforcing . . . .” Alliance to Protect Nantucket Sound, Inc. v. Energy Facilities Siting Bd., 457 Mass. 663, 681 (2010). Moreover, “administrative agencies have broad discretion over procedural matters before them.” Zachs v. Department of Pub. Utils., 406 Mass. 217, 227 (1989) (Zachs). We defer to an agency’s procedural rulings and review them for “error of law or abuse of discretion.” Id. This is so in particular when the ruling concerns whether to reopen a proceeding or an administrative record. See Alliance to Protect Nantucket Sound, Inc. v. Department of Pub. Utils. (No. 2), 461 Mass. 190, 193-194 & n.7 (2011); Box Pond Ass’n v. Energy Facilities Siting Bd., 435 Mass. 408, 420 (2001) (Box Pond).

The board determined that Brockton Power’s PCF was not an “amended petition” within the meaning of § 69F4, sixth par. As interpreted by the board, the “amended petition” provision is limited to an amended filing submitted by a project proponent within six months after the board has issued a final decision rejecting the original petition or imposing conditions from which the proponent seeks relief. The board contends that its power under § 69B4, fifth and sixth pars., to approve a petition with conditions, combined with its ability to “issue orders with respect to any matter over which it has jurisdiction,” see G. L. c. 164, § 69H, provides it with more than sufficient authority to include in a final decision an order requiring the project proponent to bring back to the board for potential review any proposed changes to the project that may affect the basis on which it was originally approved.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Alan Sliski v. Board of Assessors of Lincoln.
Massachusetts Appeals Court, 2025
JACQUELINE JOHNSON v. ENERGY FACILITIES SITING BOARD & Another
Massachusetts Supreme Judicial Court, 2025
Padmanabhan, MD PhD v. Hulka
D. Massachusetts, 2018
Padmanabhan v. Hulka
308 F. Supp. 3d 484 (District of Columbia, 2018)
Padmanabhan v. Paikos
280 F. Supp. 3d 248 (D. Massachusetts, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
469 Mass. 215, Counsel Stack Legal Research, https://law.counselstack.com/opinion/brockton-power-co-llc-v-efsbcity-of-brockton-v-efsb-no-2-mass-2014.