Town of Andover v. Energy Facilities Siting Board

435 Mass. 377
CourtMassachusetts Supreme Judicial Court
DecidedNovember 19, 2001
StatusPublished
Cited by10 cases

This text of 435 Mass. 377 (Town of Andover v. Energy Facilities Siting Board) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Town of Andover v. Energy Facilities Siting Board, 435 Mass. 377 (Mass. 2001).

Opinion

Spina, J.

The Energy Facilities Siting Board (board) approved the petition of Nickel Hill Energy, LLC, to construct and operate a 750-megawatt natural gas-fired, combined cycle electrical generating facility on a twenty-five acre site in the town of Dracut. The town of Andover and Merrimack Valley Residents for the Environment, Inc., interveners in the administrative proceedings below,3 appealed from the decision of the board to a single justice of this court, pursuant to G. L. c. 25, § 5, and G. L. c. 164, § 69R The single justice reserved and reported the case to the full court.

On appeal the interveners argue that (1) the board’s decision improperly relies on future actions by other agencies and thus is not a final agency decision; (2) the board’s decision and subsidiary findings are not supported by substantial evidence; (3) the board improperly limited its review of the site selection process to whether Nickel Hill’s description of the process was accurate; (4) the board violated the interveners’ procedural rights; and (5) Nickel Hill lacked standing to pursue its petition because it did not have a property interest in the selected site. We affirm the decision of the board.

1. Scope of review. Our review of the board’s decision is governed by the provisions of G. L. c. 25, § 5, and G. L. c. 164, § 69P. Section 69P states that “[t]he scope of such judicial review shall be limited to whether the decision of the board is [379]*379in conformity with the constitution of the commonwealth and the constitution of the United States, was made in accordance with the procedures established under [G. L. c. 164, § 69H- § 690,] and with the rules and regulations of the board with respect to such provisions, was supported by substantial evidence of record in the board’s proceedings; and was arbitrary, capricious or an abuse of the board’s discretion under the provisions of [§ 69H] to [§ 690].” The party appealing from a decision of the board bears the burden of showing that the decision is invalid. See G. L. c. 25, § 5.

2. The finality of the board’s decision. The interveners argue that the board’s decision should be vacated because it is not sufficiently final. They contend that the board failed to make findings regarding certain environmental impacts, and that the board improperly relied on future actions by the Department of Environmental Protection (department) and other contingencies in lieu of making these findings. The interveners rely on Point of Pines Beach Ass’n v. Energy Facilities Siting Bd., 419 Mass. 281 (1995), for the proposition that only a final decision may be upheld. There we vacated a decision where the board had concluded that it was “unable to determine that the proposed project is needed to provide a necessary energy supply for the Commonwealth,” an ultimate finding required by G. L. c. 164, § 69J, for nongenerating facilities. Id. at 285-286. The board, unlike in the Point of Pines Beach Ass’n case, did not fail to make ultimate findings. Its decision was final.

General Laws c. 164, § 69JV4, which governs petitions for construction of generating facilities,4 requires the board to conduct an evidentiary hearing on a petition to construct a generating facility within 180 days of filing, and to approve a petition within one year of filing if it “determines that the petition meets the following requirements: (i) the description of the proposed generating facility and its environmental impacts are substantially accurate and complete; (ii) the description of the site selection process used is accurate; (iii) the plans for the construction of the proposed generating facility are consistent with current health and environmental protection policies of the [380]*380commonwealth and with such energy policies as are adopted by the commonwealth for the specific purpose of guiding the decision of the board; (iv) such plans minimize the environmental impacts consistent with the minimization of costs associated with the mitigation, control, and reduction of the environmental impacts of the proposed generating facility; and (v) if the petitioner was required to provide information on other fossil fuel generating technologies, the construction of the proposed generating facility on balance contributes to a reliable, low-cost, diverse, regional energy supply with minimal environmental impacts.” We turn to the points that the interveners contend were wanting, addressing first their general, and primary, issue.

(a) Delegation of responsibility. The interveners claim that the board improperly delegated its responsibility under § 69JV4 to the department when it said that “[fjinal, binding, emissions limits for the proposed facility will not be established until [the department] issues its final air plan approval.” Far from constituting a delegation, the statement is an accurate observation of the different roles of the board and the department in the over-all permit process. The board concluded that the department “may not [issue its final air plan approval] until after the [board] issues its final approval” (emphasis added). A permit issued by the board is only the first of many permits and licenses that will be required of a developer of a generating facility, and no other State agency may issue a construction permit for a generating facility until it first has been approved by the board. See G. L. c. 164, § 69F/4, first par.

As to the specific contention of the interveners, the role of the board in this case with respect to air emissions is limited to a review of Nickel Hill’s description of the environmental impacts of the proposed generating facility for substantial accuracy and completeness, and a determination whether Nickel Hill’s construction plans minimize the environmental impacts consistent with the. minimization of costs associated with the mitigation, control, and reduction of the environmental impacts of the proposed facility. See G. L. c. 164, § 69JV4, fifth par. Nickel Hill’s descriptive accuracy of the environmental impacts of its proposed generating facility and its plans to minimize those impacts consistent with the cost of mitigation may satisfy [381]*381the board, but it will not necessarily satisfy the emission standards established by the department pursuant to G. L. c. 111, § 142D. See 310 Code Mass. Regs. §§ 7.00, 7.02 & Appendix A (2001). After the board issues its permit, the department must determine how the proposed generating facility may operate, and under what conditions.

The board neither delegated nor abdicated its responsibility to establish “final, binding emissions limits for the proposed facility” because it never had that authority. Regulation of the actual emissions of the proposed facility is a matter within the jurisdiction of the department, not the board, and it will be determined on Nickel Hill’s petition for a major comprehensive air plan, without which the facility may not operate. See 310 Code Mass. Regs. § 4.10 Appendix at (2) (c) (BWPAQ03) (2001); 310 Code Mass. Regs. § 7.02 (2) (a). The board also correctly stated, referring to “SCONOx technology” (see discussion, infra at 383), that because the department’s “primacy of jurisdiction and ... its greater expertise in emissions control technologies, [it] is the agency best suited to determine whether and when to introduce new emissions control technologies into the Commonwealth.” In point of fact, it is the State agency to make that determination. See G. L. c. Ill, § 142D; 310 Code Mass. Regs. §§ 7.00, 7.02 & Appendix A.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Adoption of Osei.
Massachusetts Appeals Court, 2026
JACQUELINE JOHNSON v. ENERGY FACILITIES SITING BOARD & Another
Massachusetts Supreme Judicial Court, 2025
City of Brockton v. Energy Facilities Siting Board (No. 1)
14 N.E.3d 167 (Massachusetts Supreme Judicial Court, 2014)
Brockton Power Co. LLC v. EFSB/City of Brockton v. EFSB (No. 2)
469 Mass. 215 (Massachusetts Supreme Judicial Court, 2014)
Board of Health of Sturbridge v. Board of Health of Southbridge
461 Mass. 548 (Massachusetts Supreme Judicial Court, 2012)
Town of Sturbridge Board of Health v. O'Leary
26 Mass. L. Rptr. 359 (Massachusetts Superior Court, 2009)
Sturbridge Board of Health v. O'Leary
25 Mass. L. Rptr. 171 (Massachusetts Superior Court, 2009)
Providence & Worcester Railroad v. Energy Facilities Siting Board
899 N.E.2d 829 (Massachusetts Supreme Judicial Court, 2009)
Alliance to Protect Nantucket Sound, Inc. v. Energy Facilities Siting Board
858 N.E.2d 294 (Massachusetts Supreme Judicial Court, 2006)
City Council of Agawam v. Energy Facilities Siting Board
776 N.E.2d 1002 (Massachusetts Supreme Judicial Court, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
435 Mass. 377, Counsel Stack Legal Research, https://law.counselstack.com/opinion/town-of-andover-v-energy-facilities-siting-board-mass-2001.