Point of Pines Beach Ass'n v. Energy Facilities Siting Board

419 Mass. 281
CourtMassachusetts Supreme Judicial Court
DecidedJanuary 11, 1995
StatusPublished
Cited by3 cases

This text of 419 Mass. 281 (Point of Pines Beach Ass'n v. Energy Facilities Siting Board) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Point of Pines Beach Ass'n v. Energy Facilities Siting Board, 419 Mass. 281 (Mass. 1995).

Opinion

O’Connor, J.

The plaintiffs appeal pursuant to G. L. c. 164, § 69P (1992 ed.), and G. L. c. 25, § 5 (1992 ed.), from a decision of the Energy Facilities Siting Board issued December 15, 1993. In that matter, Altresco Lynn, Inc. (Altresco), petitioned the board to approve Altresco’s planned construction of a gas-fired cogeneration 170 megawatt power facility at the General Electric River Works in Lynn. The proposal contemplated a facility that would begin operation in 1996. The board concluded as follows:

“Here, in light of the need for the proposed project beginning in the year 2000 on reliability grounds, the Siting Board[4] finds that submission of (1) a signed and approved contract with [Boston Edison Company] for 132 [megawatts], or (2) signed and approved [power purchase agreements] [5] which include capacity payments for at least 75 percent of the proposed project’s electric output, will be sufficient to establish that the proposed project will provide a necessary energy supply for the Commonwealth. Altresco must satisfy this condition within four years from the date of this condi[283]*283tional approval. Altresco will not receive final approval of its project until it complies with this condition. The Siting board finds that, at such time that Altresco complies with this condition, Altresco will have demonstrated that the proposed project will provide a necessary energy supply for the Commonwealth.”

A single justice of this court allowed Altresco’s motion to intervene in this appeal, and reserved and reported the matter to the full court.

General Laws c. 164, § 69J, provides in relevant part:

“No applicant shall commence construction of a facility at a site unless a petition for approval of construction of that facility has been approved by the board .... The board shall within twelve months from the date of filing approve a petition to construct a facility .. . if it determines that it meets the following requirements: . . . plans for expansion and construction of the applicant’s new facilities are consistent with . . . policies stated in section sixty-nine H to provide a necessary energy supply for the commonwealth with a minimum impact on the environment at the lowest possible cost . . .” (emphasis added).

The statute “requires that the energy the facility will supply is necessary for the Commonwealth.” New Bedford v. Energy Facilities Siting Council, 413 Mass. 482, 486 (1992). In the absence of need, a facility cannot properly be approved.

Since Altresco’s proposal contemplated a facility that would begin operation in 1996, the board considered whether, beginning in that year, the Commonwealth would have need for the energy the facility is designed to generate. In order to make the required showing, Altresco submitted to the board voluminous material regarding capacity and demand forecasts for the Commonwealth and for New England. The board found the record to be “unclear regarding the ability of Massachusetts utilities to acquire surplus sup[284]*284plies from out-of-state providers” before the year 2000, and thus concluded that, “based on the record, the Siting Board is unable to determine that the proposed project is needed to provide a necessary energy supply for the Commonwealth prior to the year 2000.”

The board then turned to a procedure that it had used in an earlier decision on remand in Eastern Energy Corporation (Remand). See Attorney General v. Energy Facilities Siting Board, post 1003 (1995). In that case, the board concluded that, for the years in which the Commonwealth’s energy requirements might be met by surplus energy produced elsewhere in New England, the board would nevertheless find the Commonwealth to have need of energy if the board were to receive signed power purchase agreements, previously approved by the Department of Public Utilities (department), which provide buyers for a specified percentage of the proposed facility’s output. In the present case, the board applied the same principle and concluded that “at such time as Altresco [submits approved power purchase agreements], Altresco will have demonstrated that the proposed project will provide a necessary energy supply for the Commonwealth.” The plaintiffs challenge the board’s logic, arguing that an approved power purchase agreement, standing alone, cannot demonstrate need.

In Eastern Energy Corporation (Remand), the board did not explain how the existence of approved power purchase agreements would demonstrate the existence of Commonwealth need. The board merely cited its own earlier (1987) decision, Northeast Energy Associates, for the proposition that signed and approved power purchase agreements constitute prima facie evidence that the energy contracted for is needed by the Commonwealth. The Northeast Energy Associates decision, however, does not support the proposition for which it is cited. In that case, the board concluded that a power purchase agreement may be evidence that a particular utility needs energy, but the board did not conclude that the existence of such an agreement by itself demonstrates the Commonwealth’s need for energy, and no explanation of the [285]*285inferability of Commonwealth need from utility need has been furnished to us either in reasoned argument or by reference to board decisions.

In Northeast Energy Associates, the board did find Commonwealth need based in part on evidence of a utility’s need. The board’s “[conclusion on [n]ced” was as follows:

“NBA [Northeast Energy Associates] has established (1) that New England needs at least 300 MW of additional power resources for reliability purposes by 1990, and (2) that the Commonwealth is likely to receive reliability and economic benefits from the proposed additional power within the same time period. Accordingly, the Siting Council finds that the proposed 300 MW of additional power resources are needed by 1990.”

The board relied on an almost identical rationale in the original Eastern Energy Corporation case and, on appeal in that case, this court rejected that rationale. New Bedford v. Energy Facilities Siting Council, supra at 489-490.

The board argues that it properly may rely on approved power purchase agreements to establish Commonwealth need because the department must be satisfied of the existence of such need as a prerequisite to its approval. By according deference to the department’s findings in this regard, the board argues, the public interest is served by ensuring a harmonious and consistent energy policy. Such reasoning fails to take into account G. L. c. 164, § 69J’s provision that the “board shall . . . approve a petition to construct a facility . . . if it determines that it meets the following requirements: . . . plans for expansion and construction of the applicant’s new facilities are consistent with . . . policies stated in section sixty-nine H to provide a necessary energy supply for the commonwealth . . . .” The board must ensure that every project it approves is necessary, and it may not abdicate its responsibility by relying on conclusions of the department. We note that, in this case, the board concluded that “based on the record, the Siting board is unable to determine that [286]*286the proposed project is needed to provide a necessary energy supply for the Commonwealth prior to the year 2000.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Alliance to Protect Nantucket Sound, Inc. v. Energy Facilities Siting Board
858 N.E.2d 294 (Massachusetts Supreme Judicial Court, 2006)
Town of Andover v. Energy Facilities Siting Board
435 Mass. 377 (Massachusetts Supreme Judicial Court, 2001)
Plymouth Rock Energy Associates v. Department of Public Utilities
648 N.E.2d 752 (Massachusetts Supreme Judicial Court, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
419 Mass. 281, Counsel Stack Legal Research, https://law.counselstack.com/opinion/point-of-pines-beach-assn-v-energy-facilities-siting-board-mass-1995.