Boston Edison Co. v. Department of Public Utilities

631 N.E.2d 33, 417 Mass. 458, 1994 Mass. LEXIS 200
Massachusetts Supreme Judicial Court·Decided April 8, 1994·Published·Cited by 5 cases

Opinion

Wilkins, J.

The plaintiff (Edison) has appealed (G. L. c. 25, § 5 [1992 ed.]) from a decision of the Department of Public Utilities (department), issued on June 25, 1993, in D.P.U. 92-130, in which the department rejected Edison’s request to be relieved from a previously imposed requirement that it enter into a contract to purchase power from a non-utility generator. Edison argues that the department’s decision must be set aside, asserting that, if implemented, that decision would impose an unnecessary financial burden on Edison and its customers because Edison has no need for an additional power source in the immediate future. The department responds that in its 1991 decision in D.P.U. 90-270 it concluded that Edison should proceed to seek a nonutility source of power and that, in its attempt to be relieved from that obligation, Edison has made no showing sufficient to justify reconsideration of the 1991 decision. A single justice of this court reported the case to the full court without decision.

This case involves the operation of two State regulatory processes conducted by separate agencies that shared a common concern: Edison’s needs for electric power. The first of these regulatory processes concerns the department’s implementation of certain aspects of the Federal Public Utility Regulatory Policies Act of 1978 (PURPA) (16 U.S.C. §§ 796 and 824a-3 [1988]), enacted to encourage the development of alternative power sources that would reduce the demand for fossil fuels. To encourage the development of a competitive market for alternative power generation, the department adopted regulations that require electric utilities to request project proposals from qualifying facilities for the furnishing of electric power pursuant to long-term, fixed-price contracts. See 220 Code Mass. Regs. §§ 8.00-8.07 (1986). Under the department’s regulations, to be eligible for acceptance, any project proposal from a nonutility generator must be priced below the relevant utility’s calculated long-term avoided costs of power, that is, the costs that the utility would incur in obtaining that power if the long-term contract *460 were not entered into with the nonutility generator. See 220 Code Mass. Regs. § 8.05 (3). PURPA refers to this as “the incremental cost to the electric utility of alternative electric energy.” 16 U.S.C. § 824a-3. Obviously, a utility’s cost of additional power will vary depending on whether the utility can generate that power within .its existing capacity or whether it must incur the expense of constructing new generating capacity. Just as obvious is the fact that the anticipated demand by a utility’s customers for electric power will be a significant factor in determining the utility’s perceived need for new generating capacity and, hence, in determining its avoided costs.

The appeal in this case arises from the effects of the regulatory process that we have just described. The department’s 1991 decision, which we shall discuss in greater detail shortly, obliged Edison to proceed with a request for proposals which, in turn, led to Edison’s selection of the intervener Altresco Financial (Altresco) as the qualifying facility with which Edison would contract for specific megawatts of power.

Edison’s argument that there has been a significant change in circumstances relies on a decision made by the second regulatory agency concerned with Edison’s power needs, the Energy Facilities Siting Council (council or siting council). At the times significant for our purposes, under G. L. c. 164, § 691 (1992 ed.), Edison was obliged to “file with the council a long-range forecast with respect to the electric power needs and requirements of its market area.” 2 On May 1, 1990, Edison filed with the council its 1990 long-range demand forecast, supply plan, and a proposal to build a 306-mega-watt electric generating facility. The council held public hearings over many days, received updated information, and *461 on April 10, 1992, issued a final decision in which it found that “Edison can be anticipated to experience a capacity surplus totalling 149 MW [megawatts] in 1996, and 120 MW in 1997.” 3

We now discuss the department’s 1991 decision, the one that Edison argues the department should have agreed to reconsider and did not. The proceeding commenced on October 15, 1990, when Edison filed for approval of a proposed draft of its request for proposals from nonutility generators desiring to sell electric energy and capacity to Edison under a long-term contract pursuant to the procedures outlined in the department’s regulations. In May, 1991, Edison moved that the department defer action on its proposal until the siting council acted on Edison’s May 1, 1990, filing of its long-range plan with the council. Edison argued that the council might decide that whatever purchases of power the department might order would be unneeded and that the cost of the avoidable unit to be used in establishing the conditions of any request for proposals would depend on conclusions reached by the council.

In a decision issued on August 16, 1991, the department rejected Edison’s request for delay but modified its normal process by establishing a range for the electrical capacity to be sought through Edison’s requests for proposals. The department tentatively set the supply block at 306 megawatts, the capacity of Edison’s then proposed plant, subject to adjustment by the department following the siting council’s determination of Edison’s needs. The department also set a minimum supply block of 132 megawatts, which was equal to 5% of Edison’s current annual peak load. See 220 Code Mass. Regs. § 8.05 (2) (b). The department stated that this minimum supply block would be required even if the siting council should “find no need for [Edison] to bring any additional supply into service within the next 20 years.” The de *462 partment did not say, however, that, if Edison needed no additional supply, the cost of Edison’s proposed new plant would cease to be the appropriate unit for determining avoidable costs for the purposes of accepting bids from qualifying facilities. The department in effect said that, if the bid price was right, Edison would have to purchase power and capacity from a nonutility generator, even if Edison did not need additional generating capacity. Edison did not appeal to challenge the requirement that it use the cost of its proposed new plant in determining the avoidable costs to be used as a price ceiling on bids to be submitted in response to its request for proposals. Nor did Edison appeal to challenge the requirement that, whatever its needs, if the bid price was right, Edison must enter into a contract with a nonutility generator for the purchase of at least 132 megawatts of power.

On January 27, 1992, the department decided that it should wait no longer for the siting council’s decision on Edison’s capacity needs and, in order to move the bidding process forward, fixed the supply block for Edison’s request for proposals at the 132-megawatt minimum.

Free access — add to your briefcase to read the full text and ask questions with AI

Boston Edison Co. v. Department of Public Utilities, 631 N.E.2d 33, 417 Mass. 458, 1994 Mass. LEXIS 200 (Mass. 1994).

631 N.E.2d 33 (Boston Edison Co. v. Department of Public Utilities) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Murphy's Case
829 N.E.2d 1156 (Massachusetts Appeals Court, 2005)
Plymouth Rock Energy Associates v. Department of Public Utilities
648 N.E.2d 752 (Massachusetts Supreme Judicial Court, 1995)
Boston Edison Co. v. Department of Public Utilities
647 N.E.2d 46 (Massachusetts Supreme Judicial Court, 1995)
Point of Pines Beach Ass'n v. Energy Facilities Siting Board
419 Mass. 281 (Massachusetts Supreme Judicial Court, 1995)
Massachusetts Electric Co. v. Department of Public Utilities
643 N.E.2d 1029 (Massachusetts Supreme Judicial Court, 1994)