Plymouth Rock Energy Associates v. Department of Public Utilities

648 N.E.2d 752, 420 Mass. 168, 1995 Mass. LEXIS 150
CourtMassachusetts Supreme Judicial Court
DecidedApril 26, 1995
StatusPublished
Cited by1 cases

This text of 648 N.E.2d 752 (Plymouth Rock Energy Associates v. Department of Public Utilities) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Plymouth Rock Energy Associates v. Department of Public Utilities, 648 N.E.2d 752, 420 Mass. 168, 1995 Mass. LEXIS 150 (Mass. 1995).

Opinion

Greaney, J.

The plaintiff, Plymouth Rock Energy Associates (PREA), has appealed (G. L. c. 25, § 5 [1992 ed.]) [169]*169from a decision of the Department of Public Utilities (department), issued on February 18, 1994, in D.P.U. 92-122, which set the price at which the intervener, Commonwealth Electric Company (Commonwealth) is required to purchase power from PREA, a small power producer, pursuant to the department’s integrated resource management regulations (IRM), 220 Code Mass. Regs. § 10.00 (1990). PREA argues that the decision violates the department’s regulations and administrative decisions and also violates requirements of the Federal Public Utility Regulatory Policies Act of 1978 (PURPA) (16 U.S.C. §§ 796 and 824a-3 [1988]). The department and Commonwealth respond that the department properly construed its own IRM regulations in setting the price for PREA’s contract with Commonwealth, and that PREA’s arguments asserting a conflict between the department’s decision and PURPA should be rejected. A single justice of this court reported the case to the full court without decision.

The regulatory and factual background of this case is summarized as follows.2 PURPA was enacted to encourage the development of alternative power and cogeneration resources by nonutility power generators thereby reducing the demand for fossil fuels. Under PURPA, if a power generation project meets certain specified requirements, it is characterized as a Qualifying Facility (QF). 16 U.S.C. § 796 (18) (B). PURPA requires that the Federal Energy Regulatory Commission (FERC) establish regulations that obligate public utilities to sell electric energy to and purchase power from QFs. 16 U.S.C. § 824a-3 (a). PURPA also specifies that the rates established by FERC for these purchases may not exceed the “incremental cost” to the utility of purchasing alternative electric energy. 16 U.S.C. § 824a-3 (b). This “incremental cost” is defined as “the cost to the electric utility of the elec[170]*170trie energy which, but for the purchase from such [QF], such utility would generate or purchase from another source.” 16 U.S.C. § 824a-3 (d).

PURPA’s implementing regulations, 18 C.F.R. Part 292 (1994), require that utilities purchase power from QF’s at the utility’s full “avoided cost” rate. 18 C.F.R. § 292.304 (d). “Avoided costs” are defined as a utility’s incremental costs of purchasing alternative electric energy.3 18 C.F.R. § 292.101 (b) (6). See American Paper Inst. v. American Elec. Power Serv. Corp., 461 U.S. 402, 412-418 (1983) (upholding requirement that QFs receive full avoided costs rate). Thus, in essence, the statutory ceiling price has become the floor price; Although FERC’s regulations provide guidelines for the calculation of avoided costs, 18 C.F.R. § 292.304 (e), FERC has granted the States flexibility in implementing rates for purchase and, specifically, determining avoided costs. See Southern Cal. Edison Co., 70 F.E.R.C. par. 61,666, at 61,675 (1995) (Federal commission gives States wide latitude in implementing PURPA in recognition of role Congress intended to give to States). See also Small Power Production and Cogeneration Facilities; Regulations Implementing Section 210 of the Public Utility Regulatory Policies Act of 1978, 45 Fed. Reg. 12,214, 12,226 (1980) (codified at 18 C.F.R. Part 292).

The department’s IRM regulations (220 Code Mass. Regs. § 10.00) were promulgated in 1990 to govern the planning, solicitation, and procurement of new and additional resources by investor-owned electric utilities such as Commonwealth from small power producers and cogenerators which qualify as QFs. The IRM regulations replaced the department’s QF [171]*171regulations. 220 Code Mass. Regs. § 8.00 (1986). Under the QF regulations, utilities had to conduct periodic competitive solicitations under which QFs could respond to a request for proposals (RFP) by submitting bids to sell specified amounts of energy or capacity to the utility under long-term contracts. 220 Code Mass. Regs. § 8.05. Acceptable bids under this process led to the establishment of an “Award Group” from which the utility was obliged to select, and contract with, a supplier. 220 Code Mass. Regs. § 8.05 (6). Under the new IRM regulations, cogenerators and small power producers submit bids for the fulfilment of a utility’s resource needs, the utility eventually designates a “proposed award group” from among the bids submitted, and the department, after a hearing, approves and designates a “final award group.” 220 Code Mass. Regs. § 10.04 (3) (f). 220 Code Mass. Regs. § 10.05 (4) (a). There is an exception to the procedure for a small power producer with a proposed project not exceeding five megawatts (MW) whereby the producer may enter into a long-run standard contract B (not to exceed twenty years) without participating in the solicitation process. The exceptian is set out in 220 Code Mass. Regs. § 10.07 (1), which specifies that the contract price for such a project shall be “equivalent in value, on a present worth basis, to the weighted average stream of contractually-set prices paid to all of the project developers from the most recent final award group.”

PREA, a limited partnership, is the developer of a five MW cogeneration power production facility adjacent to a regional shopping mall in Kingston. PREA’s project will produce steam for heating and cooling the mall and electricity for sale to the utility grid. PREA made contact with Commonwealth in early 1992 to sell electricity to Commonwealth under a long-run standard contract B. When Commonwealth disputed any obligation to enter such a contract with PREA, these proceedings were commenced at the department. The department found that PREA’s project fell within the exceptian for projects of five MW or less and would be governed by the provisions of § 10.07 (1). Because the IRM regula[172]*172tians had recently become effective, and because Commonwealth had not by then had a “final award group” under the IRM regulations, the question arose as to how to establish a contract price.4 (The IRM regulations did not address this point.) PREA maintained that the department should employ the price for Commonwealth’s last “award group” under the predecessor QF regulations (RFP 2 price). Commonwealth resisted this approach.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Turners Falls Ltd. Partnership v. Board of Assessors
767 N.E.2d 629 (Massachusetts Appeals Court, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
648 N.E.2d 752, 420 Mass. 168, 1995 Mass. LEXIS 150, Counsel Stack Legal Research, https://law.counselstack.com/opinion/plymouth-rock-energy-associates-v-department-of-public-utilities-mass-1995.