Boston Edison Co. v. Department of Public Utilities

647 N.E.2d 46, 419 Mass. 738, 1995 Mass. LEXIS 68
CourtMassachusetts Supreme Judicial Court
DecidedMarch 16, 1995
StatusPublished
Cited by2 cases

This text of 647 N.E.2d 46 (Boston Edison Co. v. Department of Public Utilities) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Boston Edison Co. v. Department of Public Utilities, 647 N.E.2d 46, 419 Mass. 738, 1995 Mass. LEXIS 68 (Mass. 1995).

Opinion

Greaney, J.

After our decision in Boston Edison Co. v. Department of Pub. Utils., 417 Mass. 458 (1994) (Boston Edison I), in which we set aside the decision of the Depart[739]*739ment of Public Utilities (department) in D.P.U. 92-130, and remanded the proceeding for further consideration, the plaintiff, Boston Edison Company (Edison), moved to reopen the evidentiary record before the department. Edison appealed (G. L. c. 25, § 5 [1992 ed.]) from the department’s decision after remand in D.P.U. 92-130-B to deny the motion to reopen and to reaffirm its determination that Edison’s deferral of its proposed 306-megawatt electric generating plant was not a “truly extraordinary circumstance” warranting an exception from its regulations. A single justice of this court reported the case to the full court without decision.

Edison argues that the department’s remand decision should be set aside, contending that, because the department failed to receive evidence as to whether deferral of the proposed generating plant would unnecessarily cost ratepayers $290,000,000, the department’s order requiring Edison to fulfil a previously imposed obligation to enter into a twenty-year contract to purchase 132 megawatts of power from the intervener, JMC Altresco, Inc. (Altresco), was unsupported by the record.2 The department responds that its conclusion that Edison’s deferral of the proposed generating plant was not a truly extraordinary circumstance was supported by evidence in the existing record which demonstrated that the [740]*740deferral of the proposed generating plant was an anticipated consequence for which provision had been made, and that, because Edison, in any event, has been found to need at least a minimum of additional power capacity, ratepayers would not be burdened with unnecessary charges. Altresco also argues that the department did not deviate from the order of remand in Boston Edison I, that the department was not required to reopen the record, and that the department had adequate reasons for concluding that Edison’s deferral of the proposed generating facility did not amount to a truly extraordinary circumstance.

We conclude that the department’s decision in D.P.U. 92-130-B is not adequately supported by the existing record, and, therefore, we set aside that decision and remand the case to the department with instructions to reopen the record to consider new evidence as to whether, in view of Edison’s deferral of its proposed generating plant, requiring it to purchase power from Altresco would result in excessive charges to ratepayers.

As we explained in Boston Edison I, the department, pursuant to the Federal Public Utility Regulatory Policies Act of 1978 (PURPA) (16 U.S.C. §§ 796 and 824a-3 [1988]), which was enacted to encourage the development of alternative energy sources that would reduce the demand for fossil fuels, adopted regulations requiring electric utilities to request project proposals from qualifying facilities for the furnishing of electric power through long-term, fixed-price contracts. See 220 Code Mass. Regs. §§ 8.00-8.07 (1986). Under these regulations, to be eligible for acceptance, any project proposal from a nonutility generator must be priced below the relevant utility’s “avoided costs,” which are the costs that the utility would incur in obtaining that power if the long-term contract were not entered into with the non-utility generator. See 220 Code Mass. Regs. § 8.05 (3). A utility’s costs depends on whether it needs new generating capacity to meet those power requirements.

The following is a synopsis of the pertinent facts concerning Edison’s involvement in this regulatory scheme from [741]*741which the present appeal arises.3 On October 15, 1990, Edison submitted for approval a draft request for proposals (RFP 3) from nonutility generators desiring to sell it electric power under long-term contracts pursuant to the procedures in the department’s regulations. In D.P.U. 90-270, issued on August 16, 1991, the department denied Edison’s request to defer the RFP 3 proceedings until the Energy Facilities Siting Council (siting council) addressed whether Edison had a long-range need for power.4 In addition, the department set a minimum supply block of 132 megawatts, which was equal to 5% of Edison’s current annual peak load, stating that this minimum supply block would be required even if the siting council should “find no need for [Edison] to bring any additional supply into service within the next 20 years.”

The department subsequently ruled that the “ceiling price,” which was the price against which the RFP 3 contract was to be measured, would continue to be based on the costs associated with Edison’s proposed generating plant. On April 10, 1992, the siting council concluded that Edison would have excess capacity totalling 147 megawatts in 1996 and 118 megawatts in 1997. Edison responded to this decision by announcing, on April 30, 1992, that it was deferring its proposed generating plant and by moving, on May 20, 1992, for a delay in the deadline for selecting the successful nonutility generator. In its petition to defer RFP 3, Edison objected to the use of a ceiling price based on the costs associated with the now deferred plant. Edison asserted that the contract with the nonutility generator, in light of the siting council’s finding of no immediate need, would unnecessarily increase the cost of electricity to its customers by [742]*742$273,000,000.5 These circumstances, Edison maintained, justified an exception from the department’s regulations governing power purchases. See 220 Code Mass. Regs. § 8.07 (3) (“The Department may, where appropriate, grant an exception from any provision of these regulations”).

The department’s decision in D.P.U. 92-130 denying deferral, issued on June 25, 1993, recognized that it had previously required a party seeking an exception from its regulations to demonstrate the existence of “truly extraordinary circumstances.” (We indicated in Boston Edison I, supra at 464, that “[t]he department was warranted in construing its own regulation as providing that an exception to its regulations would be ‘appropriate,’ only when there were truly extraordinary circumstances.”) Furthermore, in its decision which was the subject of the appeal in Boston Edison I, the department refused to consider more recent information that Edison had submitted and ordered Edison to proceed with RFP 3. The department explained that, because it had provided for the possibility of a finding by the siting council that Edison had no need for additional resources by fixing a minimum supply block, it was “hard pressed now to accept a finding of no need by the Siting Council as constituting truly extraordinary circumstances that would justify terminating” the request for proposals process. The department, however, did not discuss whether Edison’s deferral of its proposed new plant might have such a significant impact on the figures used to calculate avoided costs that this would constitute a truly extraordinary circumstance warranting an exception from the department’s regulations.

In Boston Edison

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Box Pond Ass'n v. Energy Facilities Siting Board
435 Mass. 408 (Massachusetts Supreme Judicial Court, 2001)
Plymouth Rock Energy Associates v. Department of Public Utilities
648 N.E.2d 752 (Massachusetts Supreme Judicial Court, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
647 N.E.2d 46, 419 Mass. 738, 1995 Mass. LEXIS 68, Counsel Stack Legal Research, https://law.counselstack.com/opinion/boston-edison-co-v-department-of-public-utilities-mass-1995.