City of New Bedford v. Energy Facilities Siting Council

597 N.E.2d 1032, 413 Mass. 482, 1992 Mass. LEXIS 459
CourtMassachusetts Supreme Judicial Court
DecidedAugust 20, 1992
StatusPublished
Cited by8 cases

This text of 597 N.E.2d 1032 (City of New Bedford v. Energy Facilities Siting Council) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of New Bedford v. Energy Facilities Siting Council, 597 N.E.2d 1032, 413 Mass. 482, 1992 Mass. LEXIS 459 (Mass. 1992).

Opinion

Lynch, J:

The city of New Bedford (New Bedford) and the Attorney General (collectively petitioners) appeal from a final decision of the Energy Facilities Siting Council (council) approving the petition of Eastern Energy Corporation (Eastern) to construct a coal-fired cogeneration power facility (facility) in New Bedford.2 Eastern petitioned the council for approval to construct such a facility on January 29, 1990. The council granted the Attorney General’s petition to inter[484]*484vene in the proceedings.3 After extensive discovery and fourteen days of evidentiary hearings, the council issued a tentative decision conditionally approving the construction of the facility. Written comments were filed by the Attorney General and others. The council then voted to approve the construction of the facility subject to certain conditions and requirements and issued a final decision. The Attorney General and New Bedford timely petitioned for appeal from the final decision. G. L. c. 25, § 5 (1990 ed.). A single justice of this court consolidated the appeals, allowed Eastern’s motion to intervene, and reserved and reported the matter to this court.

At issue is the interpretation and application of the statutory mandate found in G. L. c. 164, § 69H (1990 ed.). We conclude that the council exceeded its authority under G. L. c. 164, § 69H, and therefore we remand this matter to the council to compare alternative energy resources in its review of Eastern’s application.

The petitioners argue that (1) the council failed to analyze the environmental impact of the proposed power plant by failing to compare it with energy alternatives; (2) the council erred in finding that there was a “need” for the energy proposed by Eastern; (3) the council failed to make a finding that the new power would be at the lowest possible cost to the rate payers; and (4) the council failed to perform a balancing to determine whether the environmental harm from the facility was outweighed by other statutory objectives because it placed improper weight on the benefits of economic development of New Bedford and southeastern Massachusetts in reaching its decision. In addition, the petitioners contend that the council’s decision failed explicitly and clearly to state the reasons for its final decision and failed to make adequate subsidiary findings to support its conclusions.

[485]*485“The starting point of our analysis is the language of the statute, ‘the principal source of insight into Legislative purpose.’ Commonwealth, v. Lightfoot, 391 Mass. 718, 720 (1984).” Simon v. State Examiners of Electricians, 395 Mass. 238, 242 (1985).

General Laws c. 164, § 69H, states in part: “There is hereby established the Energy Facilities Siting Council which shall be responsible for implementing the energy policies contained in sections sixty-nine H to sixty-nine R, inclusive, to provide a necessary energy supply for the commonwealth with a minimum impact on the environment at the lowest possible cost” (emphasis added). Thus the statute mandates that the council balance environmental harm that would be caused by a new power plant against the other statutory objectives — providing a necessary energy supply at the lowest possible cost. In performing that balancing the council must evaluate whether the minimum impact standard has been met.

As its decision indicates, prior to this application the council had required a nonutility applicant to establish that its proposed project was superior to alternative approaches in terms of cost, environmental impact, reliability, and ability to address the previously identified need for energy. This past practice comports with the council’s statutory mandate. Here, the council declined to engage in a full comparative review of the environmental consequences, relative benefits, and feasibility of using alternative fuels and plants. The council stated,

“for non-utility generating facility proposals, the Siting Council traditionally has focussed on whether a particular project is the least-cost, least-environmental impact project when compared to a number of different generating technologies .... [Hjowever, the Siting Council no longer views this comparative technology approach as effective in ensuring that resource additions proposed for the Commonwealth are necessary, least-cost, and minimize environmental impact. . . .
[486]*486“In sum, it is our view that it is most appropriate to review a non-utility developer’s project in light of a broad range of resource use and development policies.”

The council set forth its new methodology of reviewing proposed facilities:

“In accordance with G. L. c. 164, sec. 69H, before approving an application to construct facilities, the Siting Council requires non-utility applicants to justify generating facility proposals in three phases. First, the Siting Council requires the applicant to show that additional energy resources are needed .... Second, the Siting Council requires the applicant to establish that its project is (1) consistent with the resource use and development policies of the Commonwealth . . . and (2) is viable as a source of energy over time .... Finally, the Siting Council requires the applicant to show that its site selection process has not overlooked or eliminated clearly superior sites and that the proposed site is acceptable in terms of cost, environmental impacts and reliability of supply .... In cases where a noticed alternative is required, the Siting Council also requires the applicant to show that the proposed site for the facility is superior to the alternative site in terms of cost, environmental impacts, and reliability of supply.”

The statutory mandate, however, requires that the energy the facility will supply is necessary for the Commonwealth; that the supply of the energy involves a minimum impact on the environment; and that such energy is supplied at the lowest possible cost. Thus, the statutory balance involves weighing minimum environmental impact and cost. Nowhere in the new standard is this balance explicitly stated. Instead, the council attempts to balance the resource use and development policies of the Commonwealth. Only with respect to the site selection process does the council require the applicant to show that its site selection process has not overlooked or eliminated clearly superior sites and that the proposed site is [487]*487acceptable in terms of cost, environmental impact, and reliability of supply. The new standard of review does not comport with the statutory mandate.

The council stated in its final decision that Eastern’s petition was filed in accordance with G. L. c. 164, § 69H, and pursuant to G. L. c. 164, § 691 (1990 ed.). Section 691 requires every electric company4 to file forecasts which include

“(3) A description of actions planned to be taken by the company which will affect capacity to meet such needs or requirements, including, but not limited to: expansion, reduction or removal of existing facilities; construction or acquisition of additional facilities; a description of alternatives

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Desmond v. Town of West Bridgewater
33 Mass. L. Rptr. 364 (Massachusetts Superior Court, 2016)
Haskins v. Deutsche Bank National Trust Co.
19 N.E.3d 455 (Massachusetts Appeals Court, 2014)
Rockett v. State Board of Retirement
932 N.E.2d 280 (Massachusetts Appeals Court, 2010)
Water Department of Fairhaven v. Department of Environmental Protection
920 N.E.2d 33 (Massachusetts Supreme Judicial Court, 2010)
Providence & Worcester Railroad v. Energy Facilities Siting Board
899 N.E.2d 829 (Massachusetts Supreme Judicial Court, 2009)
Alliance to Protect Nantucket Sound, Inc. v. Energy Facilities Siting Board
858 N.E.2d 294 (Massachusetts Supreme Judicial Court, 2006)
Attorney General v. Energy Facilities Siting Board
644 N.E.2d 963 (Massachusetts Supreme Judicial Court, 1995)
Point of Pines Beach Ass'n v. Energy Facilities Siting Board
419 Mass. 281 (Massachusetts Supreme Judicial Court, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
597 N.E.2d 1032, 413 Mass. 482, 1992 Mass. LEXIS 459, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-new-bedford-v-energy-facilities-siting-council-mass-1992.