JACQUELINE JOHNSON v. ENERGY FACILITIES SITING BOARD & Another

CourtMassachusetts Supreme Judicial Court
DecidedJanuary 9, 2025
DocketSJC-13622
StatusPublished

This text of JACQUELINE JOHNSON v. ENERGY FACILITIES SITING BOARD & Another (JACQUELINE JOHNSON v. ENERGY FACILITIES SITING BOARD & Another) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
JACQUELINE JOHNSON v. ENERGY FACILITIES SITING BOARD & Another, (Mass. 2025).

Opinion

SUPREME JUDICIAL COURT

JACQUELINE JOHNSON vs. ENERGY FACILITIES SITING BOARD & another[1]

Docket: SJC-13622
Dates: November 6, 2024 - January 9, 2025
Present: Budd, C.J., Gaziano, Kafker, Wendlandt, Georges, & Wolohojian, JJ.
County: Suffolk
Keywords: Energy Facilities Siting Board. Environment, Noise. Public Utilities, Energy company, Electric company. Electric Company. Administrative Law, Substantial evidence, Decision, Judicial review.

      Civil action commenced in the Supreme Judicial Court for the county of Suffolk on December 20, 2023.

      The case was reported by Gaziano, J.

      Christopher G. Senie for the petitioner.

      Thaddeus Heuer (Aaron Lang also present) for the intervener.

      John R. Hitt, Assistant Attorney General (Katherine M. Fahey, Assistant Attorney General, also present) for the respondent.

      David S. Rosenzweig, Erika J. Hafner, & Michael J. Koehler, for NSTAR Electric Company, amicus curiae, submitted a brief.

      WENDLANDT, J.  "And no one dared / Disturb the sound of silence."[2]  Comprised of multiple cacophonous industrial components, including two particularly loud step-up transformers, the substation[3] at the center of the present dispute, which will connect an offshore wind farm to the New England electric grid, indubitably will not be silent.  But the substation's potential clangor will be dampened by implementing design features, according to acoustical experts' reports and testimony presented by the project's proponent, Park City Wind LLC (PCW), to the Energy Facilities Siting Board (board).  These features, the experts opined, will lessen the substation's contribution to the ambient sound level at the abutting home of the petitioner, Jacqueline Johnson;[4] more specifically, the experts told the board, the substation, designed with these proposed softening features, will affect the sound levels at Johnson's home by, at the most, eight A-weighted decibels (dBA),[5] a benchmark that is well within the allowable noise impact of ten dBA set by the Department of Environmental Protection (DEP).[6]

      To arrive at the noise estimate, the experts relied on industry-standard sound-modeling software to optimize the variables that will contribute to the expected noise levels.  Among the variables the experts tweaked were certain sound level design specifications for the yet-to-be-manufactured substation equipment, which will require PCW to procure equipment with features to meet the needed "quieted" levels of sound emissions.  Acknowledging that the specifications were "aggressive," the experts nonetheless anticipated them to be within the equipment manufacturers' ken.

      Following a three-year administrative process, during which Johnson was allowed to participate fully, to demand discovery from PCW, to submit briefing materials setting forth her position, and to cross-examine PCW's experts, the board approved PCW's petition to construct the substation, subject to several conditions.[7]  See G. L. c. 164, § 69J.  Because the experts' modeling relied, in part, on sound level specifications of yet-to-be-manufactured equipment, and because Johnson had raised concerns regarding manufacturers' abilities to meet these design specifications, the board required PCW to confirm, prior to construction, that the predicted eight dBA ambient sound level increase at Johnson's home would not be exceeded once the actual sound level specifications of the substation equipment are known;[8] this preconstruction compliance filing must set forth any additional noise mitigation measures that PCW intends to take.  The board further required that, after the construction, PCW confirm that the as-built operational substation does not exceed the eight dBA sound level increase at Johnson's home.  At each of these stages, the board directed PCW to cooperate with Johnson and to attempt to reach consensus on any proposed noise mitigation efforts.  If these preconstruction or postconstruction reviews show that PCW will be unable to ensure that the substation's contribution to ambient noise levels at Johnson's home will be capped at eight dBA, PCW will need to submit a project change petition in order to proceed with the proposed construction and operation of the substation, reopening proceedings and providing Johnson a renewed opportunity to participate in the approval process.

      On appeal, Johnson contends that the board's decision, insofar as it rests on the substation's anticipated noise impact, is not supported by substantial evidence because the predicted rise in ambient sound levels rests, in part, on aggressive sound level design specifications for yet-to-be-manufactured substation equipment.  Concluding that Johnson failed to surmount the heavy burden required to overturn the board's decision, to which we owe great deference, and further concluding that the preconstruction and postconstruction reviews are not improper, we affirm.[9]

      1.  Discussion.[10]  In conducting our review of the board's decision,[11] "we give great deference to the board's expertise and experience."  Alliance to Protect Nantucket Sound, Inc. v. Energy Facilities Siting Bd., 448 Mass. 45, 51 (2006) (Alliance I).  We do not "substitute our judgment or the petitioners' judgment for that of the board."  Sudbury v. Energy Facilities Siting Bd., 487 Mass. 737, 738 (2021).  A party challenging the board's decision "bears the burden of proving that the decision is invalid, and that burden is a heavy one."  Alliance I, supra, citing G. L. c. 25, § 5.

      a.  Substantial evidence.  Johnson first contends that the part of the board's decision concerning the noise impact of the substation[12] is not supported by substantial evidence.  See G. L. c. 164, § 69P.  "'Substantial evidence' means such evidence as a reasonable mind might accept as adequate to support a conclusion."  G. L. c. 30A, § 1 (6).  See Andover v. Energy Facilities Siting Bd., 435 Mass. 377, 386 (2001).  When reviewing the board's decisions, we do not determine "whether, faced with the same set of facts, we would have drawn the same conclusion as [the board], but only 'whether a contrary conclusion is not merely a possible but a necessary inference.'"  Alliance to Protect Nantucket Sound, Inc. v. Energy Facilities Siting Bd., 457 Mass. 663, 690 (2010) (Alliance II), quoting Goldberg v. Board of Health of Granby, 444 Mass. 627, 638 (2005). 

      Here, the board was presented with reports and testimony of PCW's experts,[13] who performed an acoustical analysis of the proposed substation's sound level impacts at thirteen locations -- including at Johnson's home.  The experts explained to the board that their analysis was conservative, assuming a worst-case scenario vis-à-vis noise impact from the substation. 

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Tebo v. Board of Appeals of Shrewsbury
495 N.E.2d 892 (Massachusetts Appeals Court, 1986)
City of Brockton v. Energy Facilities Siting Board (No. 1)
14 N.E.3d 167 (Massachusetts Supreme Judicial Court, 2014)
Brockton Power Co. LLC v. EFSB/City of Brockton v. EFSB (No. 2)
469 Mass. 215 (Massachusetts Supreme Judicial Court, 2014)
Town of Andover v. Energy Facilities Siting Board
435 Mass. 377 (Massachusetts Supreme Judicial Court, 2001)
Box Pond Ass'n v. Energy Facilities Siting Board
435 Mass. 408 (Massachusetts Supreme Judicial Court, 2001)
Goldberg v. Board of Health
444 Mass. 627 (Massachusetts Supreme Judicial Court, 2005)
Alliance to Protect Nantucket Sound, Inc. v. Energy Facilities Siting Board
858 N.E.2d 294 (Massachusetts Supreme Judicial Court, 2006)
Duggan v. Board of Registration in Nursing
925 N.E.2d 812 (Massachusetts Supreme Judicial Court, 2010)
Alliance to Protect Nantucket Sound, Inc. v. Energy Facilities Siting Board
457 Mass. 663 (Massachusetts Supreme Judicial Court, 2010)
Police Department of Boston v. Kavaleski
978 N.E.2d 55 (Massachusetts Supreme Judicial Court, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
JACQUELINE JOHNSON v. ENERGY FACILITIES SITING BOARD & Another, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jacqueline-johnson-v-energy-facilities-siting-board-another-mass-2025.