Alliance to Protect Nantucket Sound, Inc. v. Energy Facilities Siting Board

457 Mass. 663
CourtMassachusetts Supreme Judicial Court
DecidedAugust 31, 2010
StatusPublished
Cited by26 cases

This text of 457 Mass. 663 (Alliance to Protect Nantucket Sound, Inc. v. Energy Facilities Siting Board) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Alliance to Protect Nantucket Sound, Inc. v. Energy Facilities Siting Board, 457 Mass. 663 (Mass. 2010).

Opinions

Botsford, J.

In 2005, the Energy Facilities Siting Board (siting board), acting pursuant to G. L. c. 164, § 69J (§ 69J), approved the petition of Cape Wind Associates, LLC (Cape Wind), to build and operate two 115 kilovolt underground and undersea electric transmission cables or lines (transmission project, or transmission Unes) that would connect Cape Wind’s proposed offshore wind-powered energy generating facility (wind farm) to the regional electric power grid. This court affirmed the siting board’s decision. Alliance to Protect Nantucket Sound, Inc. v. Energy Facilities [666]*666Siting Bd., 448 Mass. 45, 56 (2006) (Alliance I). Actual construction of the transmission lines, however, requires additional permits, licenses, and approvals from a number of different State and local authorities.

In 2007, the Cape Cod Commission (commission) denied Cape Wind’s proposed development of regional impact (DRI); approval of the DRI by the commission was one of the required “approvals” for the transmission project. Soon thereafter, Cape Wind applied to the siting board pursuant to G. L. c. 164, § 69K (§ 69K), for a “certificate of environmental impact and public interest” (certificate, or § 69K certificate) that would constitute a “composite” of the “individual permits, approvals or authorizations which would otherwise be necessary for the construction and operation” of the transmission project. Id. After conducting an adjudicatory proceeding, the siting board granted the requested certificate in May, 2009. Three of the interveners in the certificate proceeding appeal from the siting board’s decision pursuant to G. L. c. 164, § 69P, and G. L. c. 25, § 5: the Alliance to Protect Nantucket Sound (Alliance), the commission, and the town of Barnstable (Barnstable) (collectively, petitioners). They seek reversal of the decision, and also request that we declare invalid a regulation of the Department of Environmental Protection (DEP). We affirm the decision of the siting board and conclude that the challenged regulation is valid.

Background.5 Cape Wind plans to construct a wind farm consisting of 130 wind turbine generators, each 440 feet tall, on Horseshoe Shoal in Nantucket Sound, a location that is more than three miles from any Commonwealth coast and entirely in Federal waters. As a result, the wind farm itself requires only Federal permits. However, the transmission lines at issue in this case, which Cape Wind proposes to build to connect the wind farm to the regional power grid, will pass under Massachusetts territorial waters in Lewis Bay and Nantucket Sound for approximately six miles and therefore require State and local permits, licenses, and approvals for their construction and operation. The [667]*667transmission lines — two cables, each comprised of three copper conductors and one fiber optic cable bundled together — will carry electricity across an approximately 18.4 mile route, running under the seabed through Nantucket Sound and Lewis Bay for 12.5 miles, coming ashore in the town of Yarmouth (Yarmouth), and continuing underground for 5.9 miles through Yarmouth and Barnstable to an existing switching station in Barnstable.

Cape Wind’s efforts to secure the necessary Federal and, of greater significance here, State and local regulatory approvals for its wind farm and transmission project have a lengthy history. In November, 2001, Cape Wind began to seek the permits required for the transmission project by fifing an expanded environmental notification form (ENF) with the Executive Office of Energy and Environmental Affairs (EOEEA). The filing set in motion a joint review by the EOEEA under the Massachusetts Environmental Protection Act (MEPA),6 and by the commission under § 12 (i) of St. 1989, c. 716, “An Act establishing the Cape Cod commission” (Cape Cod Act). Cape Wind stated in the ENF that it sought a DRI approval from the commission. After holding a public hearing, the Secretary of the EOEEA determined that the transmission project would require Cape Wind to file an environmental impact report (EIR) in order to comply with MEPA, and outlined [668]*668the scope of the joint DRI-EER review. Pursuant to a memorandum of understanding with the EOEEA, the commission held public hearings and submitted comment letters to provide input for the MEPA review.

[667]*667“Because MEPA (like the Cape Cod Commission Act) is the product of state law, not federal law, MEPA review (and by extension Cape Cod Commission review) applies only to those portions of the project that are located within Massachusetts, including its territorial waters (generally within three nautical miles of the low water mark of the shore). The proposed [wind farm] is located outside of Massachusetts and, therefore, is not subject to state regulatory requirements. There is one notable exception . . . federal law (pursuant to the Coastal Zone Management Act) specifically delegates review authority over projects in federal waters to the Coastal Zone Management Office of the adjacent coastal state . . . .”

[668]*668In 2002, Cape Wind sought permission from the siting board pursuant to § 69J, to construct the transmission lines.78 “The approval of the [siting] board is required prior to the commencement of construction of any ‘facility’[9] ... in the Commonwealth, and no State agency may issue a construction permit for any such facility unless the petition to construct the facility has already received approval from the [siting] board.” Alliance I, 448 Mass, at 46-47, citing § 69J. Following a three-year review, the siting board approved construction of the transmission line facility under § 69J in 2005,10 a decision this court affirmed in 2006. See id. at 56.

[669]*669In March, 2007, the Secretary of the EOEEA issued a final environmental impact report, finding the transmission project in compliance with MEPA. Cape Wind then renewed its efforts to obtain DRI approval from the commission. In deciding whether to grant such approval under the Cape Cod Act, St. 1989, c. 716, the commission assesses whether a project complies with minimum performance standards (MPS) set forth in its regional policy plan (RPP), a county ordinance enacted under the Barn-stable County Home Rule Charter. St. 1988, c. 163.

In its review of Cape Wind’s DRI application, the commission first deemed it incomplete for failure to include certain engineering plans and proof of control of the property along the transmission line route. Nevertheless, the commission held three days of public hearings in May, 2007, and after receiving additional information from Cape Wind, found the application complete as of August 3, 2007. The commission closed public hearings on August 8, 2007, triggering, under § 13 (a) of the Cape Cod Act, a sixty-day period for the commission to make a decision, in the absence of which Cape Wind’s DRI application would receive constructive approval. The commission held additional public hearings in September, 2007, and sought still more information. At the commission’s request, on September 11, 2007, Cape Wind agreed to extend the decision deadline to October 21, 2007, and provided responses to the specific information requests.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

JACQUELINE JOHNSON v. ENERGY FACILITIES SITING BOARD & Another
Massachusetts Supreme Judicial Court, 2025
Ryan v. Mary Ann Morse Healthcare Corp.
Massachusetts Supreme Judicial Court, 2019
Cheryl Albaugh v. The Reserve
930 N.W.2d 676 (Supreme Court of Iowa, 2019)
Cuticchia v. Town of Andover
121 N.E.3d 703 (Massachusetts Appeals Court, 2019)
Craft Beer Guild, LLC v. Alcoholic Beverages Control Comm'n
117 N.E.3d 676 (Massachusetts Supreme Judicial Court, 2019)
Commercial Wharf East Condominium Assoc. v. Boston Boat Basin, LLC
106 N.E.3d 1114 (Massachusetts Appeals Court, 2018)
Commonwealth v. Escobar
93 N.E.3d 1156 (Massachusetts Supreme Judicial Court, 2018)
DeFelice Corp. v. Department of Public Utilities
38 N.E.3d 1040 (Massachusetts Appeals Court, 2015)
Navy Yard Four Associates, LLC v. Department of Environmental Protection
37 N.E.3d 46 (Massachusetts Appeals Court, 2015)
Commonwealth v. DiNardo
33 Mass. L. Rptr. 58 (Massachusetts Superior Court, 2015)
Chiulli v. Liberty Mutual Insurance, Inc.
87 Mass. App. Ct. 229 (Massachusetts Appeals Court, 2015)
In the Matter of a Grand Jury Investigation
22 N.E.3d 927 (Massachusetts Supreme Judicial Court, 2015)
City of Brockton v. Energy Facilities Siting Board (No. 1)
14 N.E.3d 167 (Massachusetts Supreme Judicial Court, 2014)
Brockton Power Co. LLC v. EFSB/City of Brockton v. EFSB (No. 2)
469 Mass. 215 (Massachusetts Supreme Judicial Court, 2014)
Town of Barnstable v. Berwick
17 F. Supp. 3d 113 (D. Massachusetts, 2014)
Fitchburg Gas & Electric Light Co. v. Department of Public Utilities
467 Mass. 768 (Massachusetts Supreme Judicial Court, 2014)
Alford v. Boston Zoning Commission
996 N.E.2d 883 (Massachusetts Appeals Court, 2013)
Kelley v. Cambridge Historical Commission
993 N.E.2d 1228 (Massachusetts Appeals Court, 2013)
Papleacos v. Town of Tewksbury
975 N.E.2d 456 (Massachusetts Appeals Court, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
457 Mass. 663, Counsel Stack Legal Research, https://law.counselstack.com/opinion/alliance-to-protect-nantucket-sound-inc-v-energy-facilities-siting-board-mass-2010.