MEMORANDUM AND ORDER ON STATE DEFENDANTS’ MOTION TO DISMISS
STEARNS, District Judge.
This Complaint is the latest chapter in a long-running saga involving the siting of a wind farm in Nantucket Sound. The dispute pits the Commonwealth of Massachusetts and the diversified energy policy espoused by Governor Deval Patrick against an obdurate band of aggrieved residents of Cape Cod and the Islands. Both sides in the dispute claim the mantle of environmentalism, although for present purposes, plaintiffs1 have doffed their green garb and draped themselves in the banner of free-market economics. Plaintiffs filed the Complaint on January 21, 2014, seeking declaratory and injunctive relief against various State Defendants,2 while naming Cape Wind Associates, LLC (Cape Wind) and NSTAR Electric Company (NSTAR) as required parties, pursuant to Fed. R.Civ.P. 19(a). Plaintiffs allege violations of the “dormant” Commerce Clause and the Supremacy Clause of the United States Constitution and pray that the court abrogate an order of the DPU approving an energy-supply contract entered into between NSTAR and Cape Wind. All defendants have moved to dismiss (the State Defendants collectively, and Cape Wind and NSTAR separately).3
[116]*116BACKGROUND
Cape Wind is a for-profit company with plans to develop a wind-powered renewable energy generation facility in federal waters in Nantucket Sound, a triangular-shaped 750 square-mile tract of the Atlantic Ocean bounded by Cape Cod and the Islands of Martha’s Vineyard and Nantucket. The proposed wind facility is to consist of 130 horizontal-axis wind turbines dispersed over 24 square miles of open ocean, and is designed to generate 454 megawatts of electricity at peak operation.
In 2001, Cape Wind applied for a permit to build the wind facility on Horseshoe Shoals in the Sound, some five miles from the Cape Cod coastline and roughly 16 miles from the Town of Nantucket. In August of 2002, the U.S. Army Corps of Engineers granted Cape Wind a permit to build a meteorological tower to gather data in preparation for the project. As Judge Tauro presciently predicted in rejecting a suit against the Corps of Engineers’ action, this was just “the first skirmish in an eventual battle.” Ten Taxpayers Citizen Grp. v. Cape Wind Assocs., LLC, 278 F.Supp.2d 98, 99 (D.Mass.2003). The Alliance, the leading plaintiff in this action, filed a parallel (and equally unsuccessful) lawsuit also challenging the permitting authority of the Corps of Engineers. See Alliance to Protect Nantucket Sound, Inc. v. U.S. Dep’t of the Army, 288 F.Supp.2d 64 (D.Mass.2003), aff'd, 398 F.3d 105 (1st Cir.2005).4
In 2005, the Massachusetts Energy Facilities Siting Board approved the construction of two undersea electric transmission cables to connect the proposed wind facility with the regional power grid. The Alliance promptly filed suit protesting the approval.5 In 2007, the Secretary of the Executive Office of Energy and Environmental Affairs issued a certificate approving Cape Wind’s Final Environmental Impact Report. The Ten Taxpayers Group filed a suit in response.6 The Supreme Judicial Court (SJC) and the Superior Court ultimately dismissed the two lawsuits, separately holding that the Board and the Secretary had each exercised their approval authority appropriately by deferring where necessary to federal jurisdiction.7 The Town of Barnstable, also a plaintiff in this case, meanwhile filed a lawsuit of its own against the Siting Board. See Town of Barnstable v. Mass. Energy Facilities Siting Bd., 25 Mass. L. Rptr. 375, 2009 WL 1449032 (2009). The Alliance, the Ten Taxpayer Group, and the Town of Barnstable then joined all of then-grievances in another Superior Court lawsuit, Town of Barnstable v. Cape Wind Assocs., LLC, 27 Mass. L. Rptr. 1111 [117]*117(2010), followed by another onslaught against the Facilities Siting Board. See Alliance to Protect Nantucket Sound, Inc. v. Energy Facilities Siting Bd., 457 Mass. 663, 932 N.E.2d 787 (2010) (affirming the Siting Board’s authority to issue the environmental certificate).8
In April of 2010, Kenneth Salazar, the United States Secretary of the Interior, issued a Record of Decision giving federal approval to the Cape Wind project.9 The Secretary also issued a lease to Cape Wind to operate a wind energy facility on Horseshoe Shoals, effective November 1, 2010. Notwithstanding, as one academic observer has accurately stated, “[djespite full federal and state approval of the project, CWA has continued to face vehement opposition from local groups.”10
The Green Communities Act
In 2008, the Massachusetts Legislature passed the Green Communities Act (GCA), Mass. St.2008, ch. 169.11 Section 83 of the GCA requires Massachusetts electric utilities to solicit long term supply proposals from renewable energy generators. Among the favored suppliers are generators of wind energy like Cape Wind. The GCA requires DPU-regulated utilities to obtain at least three percent of their total energy supply from “green” sources.
As originally enacted, the GCA contained a provision requiring that all eligible alternative energy suppliers be located within Massachusetts or its adjacent state and federal waters. On June 9, 2010, the DPU suspended the territorial restriction12 after TransCanada Power Market[118]*118ing Ltd. challenged the limitation in federal court under the dormant Commerce Clause.13 In 2012, the Legislature amended the GCA to eliminate the geographical restriction.
The National Grid — Cape Wind Contract
In December of 2009, National Grid, a competitor of defendant NSTAR, sought approval from the DPU to enter into negotiations with Cape Wind over a long-term energy-supply contract.14 The parties signed a Power Purchase Agreement (PPA) on May 7, 2010. Plaintiffs allege that the contract prices that National Grid agreed to pay were significantly above the market price for electricity in general and well above the price being charged by other generators of renewable energy in 2010. Compl. ¶ 48. In May of 2010, National Grid submitted two Cape Wind contracts to DPU for approval. DPU approved the first contract (for 50% of Cape Wind’s anticipated power supply to be distributed by National Grid), but rejected the second (for the remaining 50%, to be assigned to another purchaser for distribution).15
Two separate avenues of appeal were taken from DPU’s approval of the National Grid contract. The Alliance (along with TransCanada) appealed directly to the SJC, asserting, among other claims, that DPU’s approval of the contract violated the dormant Commerce Clause. The SJC rebuffed the objections and affirmed DPU’s decision, specifically rejecting the dormant Commerce Clause claim. See Alliance, 461 Mass, at 174, 959 N.E.2d 413 (noting that “[t]he constitutional challenge advanced by the Alliance and TransCanada fails”).16
Free access — add to your briefcase to read the full text and ask questions with AI
MEMORANDUM AND ORDER ON STATE DEFENDANTS’ MOTION TO DISMISS
STEARNS, District Judge.
This Complaint is the latest chapter in a long-running saga involving the siting of a wind farm in Nantucket Sound. The dispute pits the Commonwealth of Massachusetts and the diversified energy policy espoused by Governor Deval Patrick against an obdurate band of aggrieved residents of Cape Cod and the Islands. Both sides in the dispute claim the mantle of environmentalism, although for present purposes, plaintiffs1 have doffed their green garb and draped themselves in the banner of free-market economics. Plaintiffs filed the Complaint on January 21, 2014, seeking declaratory and injunctive relief against various State Defendants,2 while naming Cape Wind Associates, LLC (Cape Wind) and NSTAR Electric Company (NSTAR) as required parties, pursuant to Fed. R.Civ.P. 19(a). Plaintiffs allege violations of the “dormant” Commerce Clause and the Supremacy Clause of the United States Constitution and pray that the court abrogate an order of the DPU approving an energy-supply contract entered into between NSTAR and Cape Wind. All defendants have moved to dismiss (the State Defendants collectively, and Cape Wind and NSTAR separately).3
[116]*116BACKGROUND
Cape Wind is a for-profit company with plans to develop a wind-powered renewable energy generation facility in federal waters in Nantucket Sound, a triangular-shaped 750 square-mile tract of the Atlantic Ocean bounded by Cape Cod and the Islands of Martha’s Vineyard and Nantucket. The proposed wind facility is to consist of 130 horizontal-axis wind turbines dispersed over 24 square miles of open ocean, and is designed to generate 454 megawatts of electricity at peak operation.
In 2001, Cape Wind applied for a permit to build the wind facility on Horseshoe Shoals in the Sound, some five miles from the Cape Cod coastline and roughly 16 miles from the Town of Nantucket. In August of 2002, the U.S. Army Corps of Engineers granted Cape Wind a permit to build a meteorological tower to gather data in preparation for the project. As Judge Tauro presciently predicted in rejecting a suit against the Corps of Engineers’ action, this was just “the first skirmish in an eventual battle.” Ten Taxpayers Citizen Grp. v. Cape Wind Assocs., LLC, 278 F.Supp.2d 98, 99 (D.Mass.2003). The Alliance, the leading plaintiff in this action, filed a parallel (and equally unsuccessful) lawsuit also challenging the permitting authority of the Corps of Engineers. See Alliance to Protect Nantucket Sound, Inc. v. U.S. Dep’t of the Army, 288 F.Supp.2d 64 (D.Mass.2003), aff'd, 398 F.3d 105 (1st Cir.2005).4
In 2005, the Massachusetts Energy Facilities Siting Board approved the construction of two undersea electric transmission cables to connect the proposed wind facility with the regional power grid. The Alliance promptly filed suit protesting the approval.5 In 2007, the Secretary of the Executive Office of Energy and Environmental Affairs issued a certificate approving Cape Wind’s Final Environmental Impact Report. The Ten Taxpayers Group filed a suit in response.6 The Supreme Judicial Court (SJC) and the Superior Court ultimately dismissed the two lawsuits, separately holding that the Board and the Secretary had each exercised their approval authority appropriately by deferring where necessary to federal jurisdiction.7 The Town of Barnstable, also a plaintiff in this case, meanwhile filed a lawsuit of its own against the Siting Board. See Town of Barnstable v. Mass. Energy Facilities Siting Bd., 25 Mass. L. Rptr. 375, 2009 WL 1449032 (2009). The Alliance, the Ten Taxpayer Group, and the Town of Barnstable then joined all of then-grievances in another Superior Court lawsuit, Town of Barnstable v. Cape Wind Assocs., LLC, 27 Mass. L. Rptr. 1111 [117]*117(2010), followed by another onslaught against the Facilities Siting Board. See Alliance to Protect Nantucket Sound, Inc. v. Energy Facilities Siting Bd., 457 Mass. 663, 932 N.E.2d 787 (2010) (affirming the Siting Board’s authority to issue the environmental certificate).8
In April of 2010, Kenneth Salazar, the United States Secretary of the Interior, issued a Record of Decision giving federal approval to the Cape Wind project.9 The Secretary also issued a lease to Cape Wind to operate a wind energy facility on Horseshoe Shoals, effective November 1, 2010. Notwithstanding, as one academic observer has accurately stated, “[djespite full federal and state approval of the project, CWA has continued to face vehement opposition from local groups.”10
The Green Communities Act
In 2008, the Massachusetts Legislature passed the Green Communities Act (GCA), Mass. St.2008, ch. 169.11 Section 83 of the GCA requires Massachusetts electric utilities to solicit long term supply proposals from renewable energy generators. Among the favored suppliers are generators of wind energy like Cape Wind. The GCA requires DPU-regulated utilities to obtain at least three percent of their total energy supply from “green” sources.
As originally enacted, the GCA contained a provision requiring that all eligible alternative energy suppliers be located within Massachusetts or its adjacent state and federal waters. On June 9, 2010, the DPU suspended the territorial restriction12 after TransCanada Power Market[118]*118ing Ltd. challenged the limitation in federal court under the dormant Commerce Clause.13 In 2012, the Legislature amended the GCA to eliminate the geographical restriction.
The National Grid — Cape Wind Contract
In December of 2009, National Grid, a competitor of defendant NSTAR, sought approval from the DPU to enter into negotiations with Cape Wind over a long-term energy-supply contract.14 The parties signed a Power Purchase Agreement (PPA) on May 7, 2010. Plaintiffs allege that the contract prices that National Grid agreed to pay were significantly above the market price for electricity in general and well above the price being charged by other generators of renewable energy in 2010. Compl. ¶ 48. In May of 2010, National Grid submitted two Cape Wind contracts to DPU for approval. DPU approved the first contract (for 50% of Cape Wind’s anticipated power supply to be distributed by National Grid), but rejected the second (for the remaining 50%, to be assigned to another purchaser for distribution).15
Two separate avenues of appeal were taken from DPU’s approval of the National Grid contract. The Alliance (along with TransCanada) appealed directly to the SJC, asserting, among other claims, that DPU’s approval of the contract violated the dormant Commerce Clause. The SJC rebuffed the objections and affirmed DPU’s decision, specifically rejecting the dormant Commerce Clause claim. See Alliance, 461 Mass, at 174, 959 N.E.2d 413 (noting that “[t]he constitutional challenge advanced by the Alliance and TransCanada fails”).16 A second group of plaintiffs filed a challenge with the Federal Energy Regulatory Commission (FERC), alleging that the DPU had violated the Supremacy Clause by encroaching on FERC’s exclusive prerogative under the Federal Power Act (FPA) to set national wholesale electricity prices. FERC rejected the argument for, among other reasons, the fact that the contract as approved by DPU explicitly required the parties to obtain wholesale rate clearances from FERC. See Californians for Renewable Energy, Inc. (CARE) & Barbara Durkin v. Nat’l Grid, Cape Wind, & DPU, Order Dismissing Complaint, 137 FERC ¶ 61jl3 (2011).17
[119]*119The NSTAR — Cape Wind Contract
After the suspension of the geographical limitation, DPU had directed NSTAR and other utilities to reopen their Requests for Proposals (RFPs) to take bids from out-of-state generators. Compl. ¶ 58. NSTAR did so and ultimately contracted with three land-based wind generators, Groton Wind, LLC, New England Wind, LLC, and Blue Sky East, LLC. Id. ¶ 54. Plaintiffs allege that the price of wind energy from NSTAR’s contracts with the three land-based generators was approximately one-half the initial price agreed to by National Grid in its contract with Cape Wind. Id. ¶¶ 55-57. NSTAR chose not to enter a contract with Cape Wind. Id. ¶ 56. Plaintiffs allege that NSTAR’s “refusal” to contract with Cape Wind threatened the very existence of the project because National Grid had secured DPU approval to distribute only half of the wind farm’s output (the second National Grid contract, for the remaining 50% had been rejected by the DPU). Id. ¶ 58.
On November 24, 2010, NSTAR filed an application with DPU for approval of a merger between it and Northeast Utilities.18 The Department of Energy Resources (DOER), the agency responsible for implementing the state’s renewable energy priorities (see Mass. Gen. Laws ch. 25A, § 6), intervened in the merger proceedings. DOER had no power to veto the merger,19 but requested that DPU modify its standard of review from “no net harm” to one that would “determine whether the proposed merger will provide a substantial net benefit to the public interest....” Compl. ¶66. In response, DPU entered an Interlocutory Order acknowledging that the GCA (and the related Global Warming Solutions Act (GWSA)) required it to reconsider its standard of review, and adopted the “net benefits” standard.
In July of 2011, DOER asked the DPU to stay the merger pending an assessment of its potential impact on consumers. NSTAR and Northeast argued that a stay would derail the merger. Compl. ¶ 68. On September 28, 2011, DOER submitted a filing urging DPU to require NSTAR to purchase off-shore wind energy as a condition for approving the merger. Id. ¶ 70. NSTAR and Northeast opposed the request, arguing a potential violation of the dormant Commerce Clause as Cape Wind appeared to be the only viable off-shore wind developer. Plaintiffs allege that NSTAR representatives subsequently entered into “secret negotiations with the Patrick Administration.” Id. ¶ 75. On February 15, 2012, NSTAR and DOER entered into a settlement agreement, which included a condition that NSTAR pursue a PPA with Cape Wind on terms that were “substantially the same” as those of the National Grid-Cape Wind contract. The settlement agreement was subject to DPU approval.
[120]*120On February 24, 2012, NSTAR submitted to DPU a Memorandum of Understanding (MOU) between NSTAR, DOER, and Cape Wind setting out a timetable and method of solicitation of GCA bid proposals. The DPU invited comment on the MOU, and the Alliance, among others, submitted statements in opposition (including allegations that DOER had violated the dormant Commerce Clause). On March 22, 2012, DPU approved the MOU. The Alliance appealed the DPU’s order to the SJC, but subsequently withdrew the appeal. See Alliance to Protect Nantucket Sound v. Dep’t of Pub. Utils., No. SJC-2012-0171 (filed Apr. 23, 2012; dismissed Jan. 8, 2013). On April 4, 2012, DPU approved the merger between NSTAR and Northeast.
On March 23, 2012, NSTAR and Cape Wind executed a PPA under which NSTAR agreed to purchase energy, capacity, and renewable power certificates from Cape Wind over a 15-year period. Compl. ¶¶ 84 and 86. On March 30, 2012, NSTAR submitted the PPA to DPU for approval. Id. ¶¶ 84 and 90. The contract required Cape Wind to comply with the rules of FERC and other government entities, and required Cape Wind to obtain and maintain the requisite permits and approvals from FERC, including wholesale rates clearances. Alliance intervened in the proceedings, which included three public hearings and two evidentiary hearings. On November 26, 2012, DPU approved the PPA. Neither the Alliance nor any other party to the proceedings appealed DPU’s final decision to the SJC. On January 14, 2014, over fourteen months after the DPU’s decision, plaintiffs filed this case.
DISCUSSION
Plaintiffs seek a declaration that Massachusetts violated both the dormant Commerce Clause and the Supremacy Clause “when it used its influence over NSTAR’s merger request to bring about NSTAR’s entry into an above-market wholesale electricity contract with Cape Wind, a politically favored renewable energy project in Massachusetts, to buy electricity at a particular price.” Compl. ¶ 4. Plaintiffs also seek injunctive relief to “remedy the constitutional violation” by invalidating the Cape Wind contract that “Massachusetts compelled NSTAR to enter.” Id. Plaintiffs allege that this is necessary to “alleviate the increased electricity costs that NSTAR customers such as Plaintiffs will be forced to pay as a result of the illegal, above-market contract.” Id.
Plaintiffs’ Complaint sets out two causes of action. In Count I, plaintiffs allege that DOER “intruded on FERC’s exclusive jurisdiction to regulate wholesale electric energy prices” in violation of the Supremacy Clause and the Federal Civil Rights Act, 42 U.S.C. § 1983.20 Compl. ¶ 107. In Count II, plaintiffs allege that “by conditioning its approval of the merger on the execution of a PPA between NSTAR and Cape Wind, DOER prevented out-of-state generation facilities from competing with Cape Wind,” in violation of the dormant Commerce Clause and 42 U.S.C. [121]*121§ 1983. Id. ¶ 115. Defendants seek dismissal of the Complaint on numerous grounds, including sovereign immunity, Burford abstention, comity, claim preclusion, standing, and failure to state a claim. As the debate begins and ends with the Eleventh Amendment, I will devote the bulk of the discussion to the doctrine of sovereign immunity, and then briefly explain why neither the Supremacy Clause nor the dormant Commerce Clause give rise to a substantive right of action bene-fitting plaintiffs.
The Eleventh Amendment states that “[t]he judicial power of the United States shall not be construed to extend to any suit in law or equity, commenced or prosecuted against one of the United States by citizens of another State, or by citizens or subjects of any foreign state.” U.S. Const, amend. XI. “The Supreme Court ... has expanded the doctrine of sovereign immunity beyond the literal words of the Eleventh Amendment, holding that state governments, absent then-consent, are not only immune from suit by citizens of another state, but by their own citizens as well.” Guillemard-Ginorio v. Contreras-Gomez, 585 F.3d 508, 529 n. 23 (1st Cir.2009) (citing Alden v. Maine, 527 U.S. 706, 728-729, 119 S.Ct. 2240, 144 L.Ed.2d 636 (1999)).21 “The Eleventh Amendment largely shields States from suit in federal court without their consent, leaving parties with claims against a State to present them, if the State permits, in the State’s own tribunals.” Pastrana-Torres v. Corporacion de Puerto Rico para la Difusion Publica, 460 F.3d 124, 126 (1st Cir.2006) (quoting Hess v. Port Auth. Trans-Hudson Corp., 513 U.S. 30, 39, 115 S.Ct. 394, 130 L.Ed.2d 245 (1994)). A state entity is similarly immune from suit if it functions as an “arm of the state.” Coggeshall v. Mass. Bd. of Registration of Psychologists, 604 F.3d 658, 662 (1st Cir.2010).
A suit against a government official in his or her official capacity is the same as a suit “against [the] entity of which [the] officer is an agent.” Monell v. New York City Dep’t of Soc. Servs., 436 U.S. 658, 690 n. 55, 98 S.Ct. 2018, 56 L.Ed.2d 611 (1978). Thus, a plaintiff may not resort to the expedient of naming a state official as a defendant as a means of circumventing the Eleventh Amendment. Muirhead v. Mecham, 427 F.3d 14, 18 (1st Cir.2005) (quoting Dugan v. Rank, 372 U.S. 609, 620, 83 S.Ct. 999, 10 L.Ed.2d 15 (1963)). A narrow exception to the rule has been carved out by Ex parte Young, 209 U.S. 123, 159-160, 28 S.Ct. 441, 52 L.Ed. 714 (1908), and Home Tel. & Tel. Co. v. City of Los Angeles, 227 U.S. 278, 293-294, 33 S.Ct. 312, 57 L.Ed. 510 (1913). The Eleventh Amendment does not bar a suit against a State officer in his or her official capacity where the complaining party seeks prospective equitable relief from a continuing violation of federal law. Green v. Mansour, 474 U.S. 64, 68, 106 S.Ct. 423, 88 L.Ed.2d 371 (1985). A classic example is Georgia R.R. & Banking Co. v. Redwine, 342 U.S. 299, 72 S.Ct. 321, 96 L.Ed. 335 (1952), in which the plaintiff railroad sought to enjoin the Georgia State Revenue Commissioner from assessing or collecting ad volarem taxes in violation of the Article I prohibition against the enactment by any State of a law impairing the obligation of contracts. U.S. Const., Art. I, § 10, cl. 1. The Supreme Court affirmed the jurisdiction of the district court to grant the relief requested. “This Court has long held that a suit to restrain uncon[122]*122stitutional action threatened by an individual who is a state officer is not a suit against the State.” Id. at 304, 72 S.Ct. 321. See also Edelman v. Jordan, 415 U.S. 651, 664, 94 S.Ct. 1347, 39 L.Ed.2d 662 (1974) (“[T]he relief awarded in Ex parte Young was prospective only; the Attorney General of Minnesota was enjoined to conform his future conduct of that office to the requirement of the Fourteenth Amendment.”) (emphasis added); Rosie D. v. Swift, 310 F.3d 230, 234 (1st Cir.2002) (observing that the Ex parte Young exception allows a federal court to “enjoin state officials to conform future conduct to the requirements of federal law.”) (emphasis added).
The rule is different where the relief sought is retroactive in nature. “[A] suit, although nominally aimed at an official, will be considered one against the sovereign ‘if the judgment sought would expend itself on the public treasury or domain, or interfere with the public administration, or if the effect of the judgment would be to restrain the Government from acting, or to compel it to act.’ ” Muirhead, 427 F.3d at 18 (quoting Dugan, 372 U.S. at 620, 83 S.Ct. 999). As summarized by Professor Tribe, “[ajctions for retroactive relief, even when styled as requests for an injunction and even if nominally directed against state officers and not the state itself, will ordinarily be barred by the Eleventh Amendment if the effect of the judgment is to burden the state treasury.” Laurence H. Tribe, American Constitutional Law § 3-25 at 535 n. 99 (3d ed.2000).
That the relief being sought here is retroactive and thus barred by the Eleventh Amendment is easily ascertained by turning to the specific demands set out in plaintiffs’ Complaint for Declaratory and Injunctive Relief. Prayers (a), (b), and (c) seek a declaration that (1) the DPU acted illegally in “forcing” NSTAR to enter a contract with Cape Wind at a specified price,22 (2) that the DPU’s order approving the contract is therefore null and void, and (3) that the contract is thus “null and void and without legal force or effect.” Prayer (d) is a variant on (a) through (c) that seeks an injunction preventing DPU from taking any steps to enforce its order approving the contract and to do whatever is necessary to remedy the constitutional harms caused by its allowing the contract to take effect. An award of prospective declaratory relief that has “much the same effect as a full-fledged award of damages or restitution by the federal court” is a form of relief distinctly barred by the Eleventh Amendment. Mills v. State of Maine, 118 F.3d 37, 54-55 (1st Cir.1997). Here the effect of a declaration that Massachusetts had illegally compelled NSAR and Cape Wind to enter an above-market price contract for wind energy would inevitably lead to restitutionary claims against the Commonwealth by NSTAR and Cape Wind, while an injunction ordering DPU to cease enforcement of the PPA and to take remedial measures for the alleged constitutional harms23 would restrain the State [123]*123from acting by frustrating its efforts to implement the policies enunciated in the GCA and the GWSA, while further bleeding the treasury.
Plaintiffs attempt unsuccessfully to distinguish the cases in which sovereign immunity was found to compel dismissal of an action against state officials, including a recent decision by this court, Tyler v. Massachusetts, 981 F.Supp.2d 92, 2013 WL 5948092 (D.Mass. Nov. 7, 2013). Plaintiffs state that, “DPU Order 12-30 constitutes an ongoing legal entitlement for NSTAR to pay certain rates to Cape Wind and pass them down to consumers, whereas the [probation condition in Tyler requiring that the rapist acknowledge paternity of the child and abide by any child support orders issued by the Probate and Family Court] did not constitute an ongoing legal entitlement in any way.” Pl.’s Opp’n Mem., Dkt. # 48 at 20. However, what plaintiffs seek here is precisely analogous to Tyler (although much less sympathetic), in that they seek relief from the ongoing “effects” of past state action “in the form of elevated electricity rates over fifteen years,” just as Tyler unsuccessfully sought relief from the enduring effects of a state court order.24 In rejecting the “ongoing effects” doctrine as a means of circumventing the Eleventh Amendment, the law is not cruel, but pragmatic in its understanding that the doctrine if applied would have the effect of vitiating the right guaranteed to the States in the Eleventh Amendment to be free from tmconsented suits in the federal courts. See, e.g., Green, 474 U.S. at 68, 106 S.Ct. 423 (“Both prospective and retrospective relief implicate Eleventh Amendment concerns, but the availability of prospective relief of the sort awarded in Ex parte Young gives life to the Supremacy Clause. Remedies designed to end a continuing violation of federal law are necessary to vindicate the federal interest in assuring the supremacy of that law. But compensatory or deterrence interests are insufficient to overcome the dictates of the Eleventh Amendment.”) (emphasis added) (internal citations omitted); Edelman v. Jordan, 415 U.S. at 668, 94 S.Ct. 1347 (noting the remedy must be a “consequence of [state] compliance in the future with a substantive federal-question determination” otherwise it “is in practical effect indistinguishable in many aspects [124]*124from an award of damages against the State ... resulting from a past breach of a legal duty on the part of the defendant state officials”).
Because the Eleventh Amendment requires that this case be dismissed, there is no reason to consider the additional grounds for dismissal advocated by defendants, other than to note that the result would be no different were the court to rule on the substance of the claims, whether brought independently under section 1983,25 or directly under the Supremacy Clause,26 or under the dormant Commerce Clause.27
ORDER
For the foregoing reasons, the defendants’ motions to dismiss are ALLOWED with prejudice. The Clerk will enter judgment for defendants and close the case.28
SO ORDERED.