DeFelice Corp. v. Department of Public Utilities

38 N.E.3d 1040, 88 Mass. App. Ct. 544
CourtMassachusetts Appeals Court
DecidedOctober 19, 2015
DocketAC 14-P-1056
StatusPublished
Cited by1 cases

This text of 38 N.E.3d 1040 (DeFelice Corp. v. Department of Public Utilities) is published on Counsel Stack Legal Research, covering Massachusetts Appeals Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
DeFelice Corp. v. Department of Public Utilities, 38 N.E.3d 1040, 88 Mass. App. Ct. 544 (Mass. Ct. App. 2015).

Opinion

Cohen, J.

On November 3, 2010, DeFelice Corporation (DeFelice), a contractor engaged in removing and reinstalling water mains, struck an underground natural gas service line while excavating on Danny Road in the Hyde Park neighborhood of Boston. The ensuing explosion and fire destroyed a single family home at 17 Danny Road, and badly damaged other nearby residences. 1

The pipeline and engineering safety division (division) of the Department of Public Utilities (department) investigated DeFel-ice’s operations on Danny Road, as well as its operations at a nearby site on Como Road. As a result of the division’s investigation, it issued notices of probable violations (NOPVs) of the “dig safe” law, G. L. c. 82, §§ 40-40E, 2 and associated regulations, for each of the two sites. DeFelice contested the NOPVs and, after receiving adverse informal review decisions as to both matters, requested a formal adjudicatory hearing. The cases were consolidated, and a hearing was held before a three-member panel of department commissioners. In a thirty-nine page decision and order, the department found DeFelice responsible for four violations of the dig safe law and imposed the maximum statutory penalty allowed for each violation, resulting in a total fine of $31,000.

As to both the Como Road and Danny Road excavations, the department determined that DeFelice had violated G. L. c. 82, § 40A, which requires an excavator to provide proper advance notice of its planned work to the telephone call center of Dig Safe System, Inc. (call center), an information clearinghouse and communications system statutorily required to be maintained by various utility companies. See G. L. c. 164, § 76D. Specifically, the department found that DeFelice’s notification to the call center failed to provide information needed to “accurately define the location” of the excavations as required by G. L. c. 82, § 40. See *546 G. L. c. 82, § 40A. In addition, the department found that, at both sites, DeFelice had failed to use “reasonable precautions” while performing work in “close proximity” to existing underground utility facilities, as required by G. L. c. 82, § 40C.

Before us is DeFelice’s appeal, pursuant to G. L. c. 25, § 5. 3 DeFelice challenges the department’s findings of dig safe law violations, but only with respect to the excavation on Danny Road. 4 DeFelice also challenges the four separate penalties as cumulative. For the following reasons, we affirm.

Background. 1. Regulatory scheme. The dig safe law, G. L. c. 82, §§ 40-40E, and the regulations promulgated thereunder, 220 Code Mass. Regs. §§ 99.00-99.12 (2008), are designed to protect life and property by requiring excavators to comply with notification and safety procedures. See generally Yukna v. Boston Gas Co., 1 Mass. App. Ct. 62, 66-67 (1973). An excavator must “premark[ ]” the location of the intended work using white paint, stakes, or other suitable white markings. G. L. c. 82, § 40A. See 220 Code Mass. Regs. § 99.02 (2008). The excavator then must notify the call center, “accurately” describing the excavation location, and indicating the date that excavation is expected to begin. G. L. c. 82, § 40A. 220 Code Mass. Regs. § 99.04 (2008). Except in the case of emergency, the excavator cannot proceed with the work until at least seventy-two hours after giving notice. See G. L. c. 82, § 40A; 220 Code Mass. Regs. § 99.04 (2008). During this seventy-two hour period, the call center notifies the utility companies that have underground facilities where the excavation is to occur. Using standard, color-coded markings, each such company must mark the location of any of its facilities within the excavator’s premarking zone and an additional fifteen-foot safety zone. See G. L. c. 82, § 40B; 220 Code Mass. Regs. § 99.05 (2008).

At the conclusion of the seventy-two hour period, the excavator may begin work, but must use “reasonable precautions” when in close proximity to an underground facility in order to avoid damaging it. G. L. c. 82, § 40C. 220 Code Mass. Regs. § 99.06(1) (2008). “[Reasonable precautions” include using “non-mechani *547 cal means” when excavating near an underground facility. G. L. c. 82, § 40C. See 220 Code Mass. Regs. § 99.06(1) (2008). Violation of any provision of the dig safe statute or regulations is subject to a penalty of $1,000 for a first offense, and between $5,000 and $10,000 for any subsequent offense within twelve consecutive months. See G. L. c. 82, § 40E; 220 Code Mass. Regs. § 99.12(1) (2008).

2. Facts. We summarize the essential facts established in the administrative record. In 2010, DeFelice began work on a public works contract awarded to it by the Boston water and sewer commission to replace and repair underground municipal water mains and sewer pipes in the Hyde Park, Roslindale, and West Roxbury neighborhoods of Boston. Among other things, the project involved the “re-lay” of water mains on Reynold Road in Hyde Park, including the junctions where Reynold Road intersects with Danny Road and Como Road.

On October 1, 2010, DeFelice notified the call center of its planned excavation work, reporting that it had done its premarking and giving the following description of the excavation location: “Starting at and including the intersection with Como Road, continuing approximately 500 feet north on Reynold Road to and including the intersection with Chesterfield Street.” DeFelice also stated that the work would be from “street to property lines.” Based upon this notification, the call center issued a dig safe ticket to DeFelice and relayed the information to NSTAR Gas Company (NSTAR), which, at the time, was the owner of the underground natural gas facilities in that area.

DeFelice began working at the junction of Reynold Road and Como Road on or about October 22, 2010. The department found that DeFelice excavated parts of Como Road that were sixty-five feet away from the intersection with Reynold Road and that, therefore, DeFelice had failed to provide the call center with an accurate description of the excavation location, in violation of G. L. c. 82, § 40A. The department also found that DeFelice had used a jackhammer on Como Road in close proximity to unidentified underground gas facilities and, therefore, DeFelice had failed to use reasonable precautions in performing the excavation, in violation of G. L. c. 82, § 40C.

DeFelice began working at the junction of Reynold Road and Danny Road on November 3, 2010. This excavation was for a connection to a water main drain pipe starting at the corner of Reynold Road and Danny Road, and continuing down Danny *548 Road. While excavating on Danny Road seventeen feet beyond the property line running along the east side of Reynold Road, the work crew’s backhoe machine struck and punctured a one-inch steel gas pipeline that serviced the home at 17 Danny Road. Gas entered the home and ignited, causing the explosion. At the time of the excavation, there were a few NSTAR markings on Danny Road beyond the immediate intersection with Reynold Road; however, the service pipeline to 17 Danny Road was not marked.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Burns v. Defelice Corp.
103 N.E.3d 770 (Massachusetts Appeals Court, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
38 N.E.3d 1040, 88 Mass. App. Ct. 544, Counsel Stack Legal Research, https://law.counselstack.com/opinion/defelice-corp-v-department-of-public-utilities-massappct-2015.