CONSERVATION LAW FOUNDATION & Another v. ENERGY FACILITIES SITING BOARD & Another (And a Consolidated Case)

CourtMassachusetts Supreme Judicial Court
DecidedSeptember 11, 2024
DocketSJC-13521
StatusPublished

This text of CONSERVATION LAW FOUNDATION & Another v. ENERGY FACILITIES SITING BOARD & Another (And a Consolidated Case) (CONSERVATION LAW FOUNDATION & Another v. ENERGY FACILITIES SITING BOARD & Another (And a Consolidated Case)) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
CONSERVATION LAW FOUNDATION & Another v. ENERGY FACILITIES SITING BOARD & Another (And a Consolidated Case), (Mass. 2024).

Opinion

SUPREME JUDICIAL COURT

CONSERVATION LAW FOUNDATION & another[1] vs. ENERGY FACILITIES SITING BOARD & another[2] (and a consolidated case[3])

Docket: SJC-13521
Dates: May 6, 2024 - September 11, 2024
Present: Budd, C.J., Gaziano, Kafker, Wendlandt, Georges, & Wolohojian, JJ.
County: Suffolk
Keywords: Energy Facilities Siting Board. Public Utilities, Energy company, Electric company, Findings, Judicial review. Electric Company. Environment. Administrative Law, Substantial evidence, Findings, Agency's interpretation of statute, Judicial review. Permit. Department of Environmental Protection.

            Civil actions commenced in the Supreme Judicial Court for the county of Suffolk on December 19 and 29, 2022.

            The cases were reported by Cypher, J.

            Phelps Turner (Anxhela Mile also present) for Conservation Law Foundation & another.

            Adam M. Ramos, Special Assistant Attorney General (Christine E. Dieter also present) for the respondent.

            David S. Rosenzweig (Catherine J. Keuthen & Cheryl A. Blaine also present) for the intervener.

            Francis E. O'Brien, pro se, was present but did not argue.

            Rosa Hayes & Sommer H. Engels, for Union of Concerned Scientists, amicus curiae, submitted a brief.

            WOLOHOJIAN, J.  The petitioners in these two consolidated actions seek judicial review, pursuant to G. L. c. 164, § 69P, of a decision of the Energy Facilities Siting Board (board) granting a certificate of environmental impact and public interest (certificate) to NSTAR Electric Company, doing business as Eversource Energy (Eversource), in connection with a proposed electric substation in the East Boston section of Boston (substation).  The petitioners raise several arguments on appeal.  First, they argue that the board should not have considered the merits of the petition for a certificate because Eversource failed to make a threshold showing of "undue delay" on the part of two city of Boston (city) agencies.  Second, as to the board's decision regarding the merits of Eversource's petition, they argue that (1) the board failed to consider or properly weigh the environmental justice principles contained in "An Act Creating a Next-Generation Roadmap for Massachusetts Climate Policy" (Next-Generation Roadmap Act), St. 2021, c. 8, §§ 55-60; (2) the board failed to consider (a) the increased cost of the project, (b) the Massachusetts Environmental Policy Act, G. L. c. 30, §§ 61-62H, (c) substantial evidence of risks to public health and safety, (d) substantial evidence that the substation was not in the public interest, and (e) technological and siting alternatives; and (3) the board unlawfully approved a G. L. c. 91 tidelands license for the project. 

            We conclude that the board's decision is lawful, was supported by substantial evidence, and was not arbitrary, capricious, or otherwise an abuse of the board's discretion under the provisions of G. L. c. 164, §§ 69H-69O.  We accordingly affirm.[4]

            1.  Background.  a.  Statutory and regulatory framework.  An electric, gas, or oil company seeking to build a new nongenerating energy facility (applicant) -- such as the proposed substation at issue here -- must receive board approval in order to commence construction.[5]  G. L. c. 164, § 69J.  In addition to receiving construction approval from the board, the applicant must ordinarily obtain the myriad of State and local permits, licenses, and approvals required to build an energy facility.  See Alliance to Protect Nantucket Sound, Inc. v. Energy Facilities Siting Bd., 457 Mass. 663, 689 & nn.38, 39 (2010) (Alliance II) (discussing nine required local and State permits).  When an applicant does not obtain all the necessary State and local approvals and can demonstrate that the failure is a result of certain specified types of hindrance, the applicant may seek relief from the board by filing a petition for a "certificate of environmental impact and public interest" pursuant to G. L. c. 164, §§ 69K-69O.  In such cases, the applicant must show at least one of the following as a threshold requirement before the board will consider the merits of the petition:  (1) constructing the facility according to the standards imposed by a State or local agency is impossible "with commercially available equipment"; (2) construction is prevented by a State or local agency's undue delay for any reason; (3) "there are inconsistencies among resource use permits issued by such [S]tate or local agencies"; (4) a State or local agency has attempted to impose a nonregulatory issue or condition; (5) construction is impossible "due to any disapprovals, conditions or denials by a [S]tate or local agency"; or (6) a "[S]tate or local agency has imposed a burdensome condition or limitation on any license or permit which has a substantial impact on the board's responsibilities."  G. L. c. 164, § 69K.  See 980 Code Mass. Regs. § 6.02 (1993).  Only if the board concludes that the applicant has established one of these threshold circumstances will it consider the merits of the applicant's petition for a certificate.[6]  G. L. c. 164, § 69K.

            If the board concludes that the applicant has satisfied the threshold showing, it must consider and make written findings concerning the following in order to grant a certificate:

"(1) the need for the facility to meet the energy requirements of the applicant's market area taking into account wholesale bulk power or gas sales or purchases or other co-operative arrangements with other utilities and energy policies as adopted by the [C]ommonwealth;

"(2) the compatibility of the facility with considerations of environmental protection, public health and public safety;

"(3) [t]he extent to which construction and operation of the facility will fail to conform with existing [S]tate and local laws, ordinances, by-laws, rules and regulations and reasonableness of exemption thereunder, if any, consistent with the implementation of the energy policies contained in this chapter to provide a necessary energy supply for the [C]ommonwealth with a minimum impact on the environment at the lowest possible cost; and

"(4) the public interest, convenience and necessity requiring construction and operation of the facility."

G. L. c. 164, § 69O.  See 980 Code Mass. Regs. § 6.05 (1993).  In addition, the board is to examine "the good faith effort made by the applicant to obtain from [S]tate agencies and local governments the licenses, permits and other regulatory approvals required by law."  G. L. c. 164, § 69L. 

            The board is obligated to render its decision "[a]s expeditiously as possible but in no event later than six months from the date of filing of the petition."  G. L. c. 164, § 69O.  The board may grant the petition, deny the petition, or grant the petition subject to conditions.  See id.  If granted, the certificate operates as "a composite of all individual permits, approvals or authorizations which would otherwise be necessary for the construction and operation of the facility."  G. L. c. 164, § 69K.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

MCI Telecommunications Corp. v. Department of Telecommunications & Energy
755 N.E.2d 730 (Massachusetts Supreme Judicial Court, 2001)
City Council of Agawam v. Energy Facilities Siting Board
776 N.E.2d 1002 (Massachusetts Supreme Judicial Court, 2002)
Alliance to Protect Nantucket Sound, Inc. v. Energy Facilities Siting Board
858 N.E.2d 294 (Massachusetts Supreme Judicial Court, 2006)
Moot v. Department of Environmental Protection
448 Mass. 340 (Massachusetts Supreme Judicial Court, 2007)
eVineyard Retail Sales-Massachusetts, Inc. v. Alcoholic Beverages Control Commission
882 N.E.2d 334 (Massachusetts Supreme Judicial Court, 2008)
Providence & Worcester Railroad v. Energy Facilities Siting Board
899 N.E.2d 829 (Massachusetts Supreme Judicial Court, 2009)
Town of Canton v. Commissioner of Massachusetts Highway Department
919 N.E.2d 1278 (Massachusetts Supreme Judicial Court, 2010)
Moot v. Department of Environmental Protection
456 Mass. 309 (Massachusetts Supreme Judicial Court, 2010)
Alliance to Protect Nantucket Sound, Inc. v. Energy Facilities Siting Board
457 Mass. 663 (Massachusetts Supreme Judicial Court, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
CONSERVATION LAW FOUNDATION & Another v. ENERGY FACILITIES SITING BOARD & Another (And a Consolidated Case), Counsel Stack Legal Research, https://law.counselstack.com/opinion/conservation-law-foundation-another-v-energy-facilities-siting-board-mass-2024.