Allegheny Ludlum Corp. v. Pennsylvania Public Utility Commission

612 A.2d 604, 149 Pa. Commw. 106, 133 P.U.R.4th 607, 1992 Pa. Commw. LEXIS 455
CourtCommonwealth Court of Pennsylvania
DecidedJune 25, 1992
Docket100 and 118 C.D. 1991
StatusPublished
Cited by6 cases

This text of 612 A.2d 604 (Allegheny Ludlum Corp. v. Pennsylvania Public Utility Commission) is published on Counsel Stack Legal Research, covering Commonwealth Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Allegheny Ludlum Corp. v. Pennsylvania Public Utility Commission, 612 A.2d 604, 149 Pa. Commw. 106, 133 P.U.R.4th 607, 1992 Pa. Commw. LEXIS 455 (Pa. Ct. App. 1992).

Opinion

McGINLEY, Judge.

These are consolidated petitions for review by industrial ratepayers from an order of the Pennsylvania Public Utility Commission (PUC or Commission) in a general base rate case in which West Penn Power Company (West Penn or the utility) applied for an increase in rates. 1 On March 15, 1990, West Penn filed supplements to existing tariffs, which were calculated to produce approximately $56,880,000 in additional annual revenues, an increase of approximately 7.9%. Complaints against the proposed supplements were filed by the Office of Consumer Advocate (OCA), the Office of Small *110 Business Advocate, Armco Advanced Materials Corporation and Air Products and Chemicals, Inc. (together, Armco), Allegheny Ludlum Corporation (Allegheny Ludlum), West Penn Power Industrial Users Group and others. Milesburg Energy, Inc. (Milesburg) and another party were granted intervenor status. The Commission suspended the operation of the supplements and ordered a formal investigation into their justness and reasonableness, with participation of .the Office of Trial Staff of the PUC (OTS). Administrative Law Judge Larry Gesoff (ALJ) conducted multiple evidentiary hearings and a public input hearing.

The ALJ issued a Recommended Decision on October 15, 1990, which included a recommendation that West Penn had established a need for additional annual revenues of $28,429,000. The principal parties filed exceptions and replies to exceptions. The Commission entered its opinion and order on December 14, 1990, authorizing an increase in operating revenues of $36,170,000. Pennsylvania Public Utility Commission v. West Penn Power Co., 119 PUR 4th 110 (1990) (Commission Decision). The scope of our review of a decision of the PUC is to determine whether constitutional rights have been violated or an error of law committed and whether the PUC’s findings are supported by substantial evidence in the record. 2 Pa.C.S. § 704; Barasch v. Pennsylvania Public Utility Commission, 507 Pa. 561, 493 A.2d 653 (1985).

Some background is necessary for an understanding of the issues raised by Armco and Allegheny Ludlum and their conceptual and procedural relation to orders of the Commission in other proceedings. Electric utilities must offer to purchase power from cogenerators and small power producers that are “qualifying facilities” (QFs), under Sections 201 and 210 of the Public Utility Regulatory Policies Act of 1978 (PURPA), 16 U.S.C. §§ 796(17)-(22) and 824a-3. The Federal Energy Regulatory Commission (FERC) regulations implementing Section 210 of PURPA require a rate for mandated purchases equal to (but not greater than) the full “avoided costs” (FAC). 18 C.F.R. § 292.304(b)(2). Those are defined as “the incremental costs to the electric utility of energy or *111 capacity or both which, but for the purchase from the qualifying facility ... such utility would generate itself or purchase from another source.” 18 C.F.R. § 292.106(b)(6) (emphasis added). 2

In Pennsylvania charges are recovered from customers through base rates and through the mechanism of the Energy Cost Rate (ECR). 3 In base rates, charges typically are allocated among various classes of customers in a rate structure. The primary consideration in establishing a rate structure is the cost of service, although this court has recognized that other concerns are properly considered as well. 4 Cost of *112 service is determined by consideration of cost-of-serviee studies, in which costs are first “functionalized” among categories of generation, transmission and distribution, and then classified within each function as demand/capacity costs, commodity/energy costs or customer costs (expenses, such as meters and billing, affected by the number of customers served). See Peoples Natural Gas Co. v. Pennsylvania Public Utility Commission, 122 Pa.Commonwealth Ct. 445, 552 A.2d 1135 (1989); J. Cawley and N. Kennard, Rate Case Handbook, A Guide to Utility Ratemaking before the Pennsylvania Public Utility Commission (Pennsylvania Public Utility Commission 1983) (Cawley and Kennard) at 257-61.

As a general rule, the capacity or “demand” component of the cost of service is lower for customers that have a high load factor, that is, the demand that they place on the system on a regular basis is close to their peak demand. The utility need not plan for or construct or purchase capacity to meet a peak demand far above the average consumption of such customers, which typically include large industrials. Customers with a low load factor consume electricity in a manner that varies widely, and their maximum peak demand is far above their average demand. Because the utility must comply with its statutory duty to secure sufficient capacity to meet its overall peak demand, the capacity component of the cost to serve such customers is higher, resulting in a higher overall rate for such a class. Cawley and Kennard at 258-59, 267.

Charges that are recovered through the ECR are assessed on strictly an energy basis: each customer is charged the same rate for every kilowatt hour (kwh) of electricity that it consumes, regardless of its load factor or any other considerations relating to cost of service. Since 1985, the Commission has approved recovery of costs from utility purchases of power from QFs on a dollar-for-dollar basis through the ECR. AES Beaver Valley, Inc. v. West Penn Power Co., Docket No. C-844022 (entered March 13, 1985). In addition to normal fuel and energy costs, some demand-related items not involv *113 ing QF purchases are recovered or credited through the ECR as well, i.e., purchases from non-QF sources and revenues from off-system sales of power.

In 1987 West Penn petitioned the PUC to approve the terms of a contract that it had negotiated with Milesburg for the delivery of power for thirty years from a QF that Miles-burg was to construct. Armco and Allegheny Ludlum jointly challenged the procedure under which the PUC gave its approval. This court held that the Commission’s approval of a utility-QF contract that provides for significant payments for capacity in a petition proceeding is an adjudication involving substantial property interests of ratepayers and so is subject to due process requirements of notice and an opportunity to be heard. Barasch v. Pennsylvania Public Utility Commission, 119 Pa.Commonwealth Ct. 81, 546 A.2d 1296, reargument denied,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Philadelphia Suburban Water Co. v. Pennsylvania Public Utility Commission
808 A.2d 1044 (Commonwealth Court of Pennsylvania, 2002)
South River Power Partners L.P. v. Pennsylvania Public Utility Commission
696 A.2d 926 (Commonwealth Court of Pennsylvania, 1997)
Pennsylvania Electric Co. v. Pennsylvania Public Utility Commission
648 A.2d 63 (Commonwealth Court of Pennsylvania, 1994)
Duquesne Light Co. v. Pennsylvania Public Utility Commission
643 A.2d 130 (Commonwealth Court of Pennsylvania, 1994)
GPU Industrial Intervenors v. Pennsylvania Public Utility Commission
628 A.2d 1187 (Commonwealth Court of Pennsylvania, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
612 A.2d 604, 149 Pa. Commw. 106, 133 P.U.R.4th 607, 1992 Pa. Commw. LEXIS 455, Counsel Stack Legal Research, https://law.counselstack.com/opinion/allegheny-ludlum-corp-v-pennsylvania-public-utility-commission-pacommwct-1992.