Duquesne Light Co. v. Pennsylvania Public Utility Commission

643 A.2d 130, 163 Pa. Commw. 367, 1994 Pa. Commw. LEXIS 181
CourtCommonwealth Court of Pennsylvania
DecidedApril 13, 1994
StatusPublished
Cited by4 cases

This text of 643 A.2d 130 (Duquesne Light Co. v. Pennsylvania Public Utility Commission) is published on Counsel Stack Legal Research, covering Commonwealth Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Duquesne Light Co. v. Pennsylvania Public Utility Commission, 643 A.2d 130, 163 Pa. Commw. 367, 1994 Pa. Commw. LEXIS 181 (Pa. Ct. App. 1994).

Opinion

LORD, Senior Judge.

On June 14, 1991, a group known as the Duquesne Interruptible Complainants1 (DIC) filed a formal complaint before the Pennsylvania Public Utility Commission (Commission) asking the Commission to find the then current $2.00/kw interruptible credit contained in the Duquesne Light Company’s (Duquesne) Rate HVPS (High Voltage Power Service) and Rider No. 7 (Rate L Large Power Service) unjust and unreasonable, in violation of Section 1301 of the Public Utility Code,2 66 Pa.C.S. § 1301. The complaint also requested that the Commission find a just and reasonable interruptible service credit based upon a calculation producing a credit level approximately equal to fifty per cent of the applicable production demand cost per kilowatt (kW) for Rider No. 7 and Rate HVPS customers.3

The complaint averred that DIC members purchase substantial quantities of electricity from Duquesne pursuant to the rates, terms and conditions of Rider No. 7 and Rate HVPS, and that DIC members desire to continue to purchase substantial quantities of electricity from Duquesne if Rider No. 7 and Rate HVPS interruptible service credit levels are made just and reasonable.

The complaint cited the history of Du-quesne’s interruptible credit level where the $2.00/kW credit level for interruptible service contained in Rider No. 7 was originally established in January 1983 when the Rate GL (General Service Large) demand charge was $8.763/kW for the first 5,000 kW and $6.62/kW for all kW in excess of 5,000 kW. When Rate HVPS was added to Duquesne’s tariff in 1988, the $2.00/kW interruptible service credit level was continued.

The DIC complaint urged the Commission to consider a higher interruptible service credit in light of the marked increase in the frequency of notices of likely interruptions and actual interruptions.

The complaint also outlined a framework where increased interruptible service credit levels would bolster DIC member efforts in becoming more operationally competitive in the steelmaking marketplace, which was averred to be constantly threatened by out-of-state and foreign competition. The DIC complaint maintained that despite Du-quesne’s and the Commission’s purported focus on new customer economic development, little, if any, effort has been made to examine existing customer needs in the context of the just and reasonable interruptible credit levels.

After a pre-hearing conference, submission of direct and rebuttal written statements by the parties and three days of hearings, Administrative Law Judge John H. Corbett, Jr. (ALJ) found DIC’s proposed methodology for the calculation of the interruptible credit to be the “most logical and the best supported approach in the proceeding.” (ALJ decision, October 14, 1992, p. 92). The ALJ agreed [132]*132with DIC’s use of a production demand factor in determining an appropriate interrupti-ble credit and recommended the DIC methodology with its $5.89/kW interruptible service credit level be adopted by the Commission. (ALJ decision, October 14, 1992, pp. 91-92).

The Commission did not accept the ALJ’s recommended decision. The Commission did, however, find that DIC was entitled to an increase in the interruptible service credit to $3.04/kW.4

Understandably, none of the parties was satisfied by the Commission’s order and they have all petitioned for a review to this Court. Their respective positions5 may be stated suecintly. Duquesne Light contends there should be no increase from the present $2.00/kW figure. DIC argues that this court should adopt the figure recommended by the ALJ — viz., $5.89/kW. The Commission urges that we affirm its order which sets the credit for interruptible service at $3.04/kW.

In this opinion, we shall discuss our standard of review and the relationship between the ALJ’s recommendation and the Commission’s findings and conclusion. We shall then review the reasoning stated in the Commission’s decision and review the respective positions of the parties. Finally, we shall state our disposition of the petitions for review which are before the Court and the reasons for our disposition.

Standard of Review and Relationship Between the ALJ’s Recommendations and the Commission’s Findings

This Court is required to affirm the order of the Commission if it is based upon substantial evidence and does not contain an error of law or offend a constitutional requirement. Allegheny Ludlum Corp. v. Pennsylvania Public Utility Commission, 149 Pa.Commonwealth Ct. 106, 612 A.2d 604 (1992). While the opinion of the ALJ is instructive, and often persuasive, the ALJ’s weighing of the evidence is not binding on the Commission for the purpose of appellate review. It is for the Commission to gauge the sufficiency of evidence, and the Commission is not bound by the ALJ’s weighing of the evidence or characterization of the argument. Pennsylvania Retailers’ Associations v. Pennsylvania Public Utility Commission, 64 Pa.Commonwealth Ct. 491, 440 A.2d 1267 (1982).

The Opinion and Order of the Commission

Some background is necessary for an understanding of our holding in this appeal that the Commission’s conclusion cannot be affirmed.

The ALJ filed an extremely comprehensive recommended decision. In his ninety-two page decision, he reviewed in detail the history of the case, the testimony, the contentions of the parties and his conclusions. His recommended decision in essence accepted [133]*133DIC’s arguments and the statements of its witnesses and rejected Duquesne’s position.

When the Commission rendered its decision, the parties were advised for the first time in the proceeding that a “comprehensive cost of service study” was necessary before the Commission would impose a permanent rate for Duquesne’s interruptible service credit. The Commission made no attempt to order such a study under the power granted to it, Section 504 of the Public Utility Code, 66 Pa.C.S. § 504,6 either before making its decision or in the decision itself. Rather, as it appears to this Court, the Commission arbitrarily selected and imposed a rate of $3.04 pending the completion of a cost of service study.

The Commission’s opinion may be summarized as follows. The Commission found that there was adequate evidence to substantiate the recommendation of the ALJ that the $2.00 interruptible service credit was unjust and unreasonable and must be increased. However, it refused to accept the recommendation that the interruptible service credit be increased to $5.89/kW. It then made its own conclusion that it would increase the rate to $3.04/kW. We quote the paragraph which provides this Court with the sole reasoning for the Commission’s selection of $3.04 as the credit rate:

Nonetheless, the existence of the CEEP Report and the recommendations concerning the Respondent contained therein, as well as any effect on rates that an isolated adjustment of the magnitude of that proposed by the Complainants may have, without the benefit of a comprehensive cost of service study, causes us great concern.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Energy Conservation Council of Pennsylvania v. Public Utility Commission
25 A.3d 440 (Commonwealth Court of Pennsylvania, 2011)
City of Philadelphia v. Pennsylvania Public Utility Commission
702 A.2d 1139 (Commonwealth Court of Pennsylvania, 1997)
Popowsky v. Pennsylvania Public Utility Commission
669 A.2d 1029 (Commonwealth Court of Pennsylvania, 1995)
Pennsylvania Industrial Energy Coalition v. Pennsylvania Public Utility Commission
653 A.2d 1336 (Commonwealth Court of Pennsylvania, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
643 A.2d 130, 163 Pa. Commw. 367, 1994 Pa. Commw. LEXIS 181, Counsel Stack Legal Research, https://law.counselstack.com/opinion/duquesne-light-co-v-pennsylvania-public-utility-commission-pacommwct-1994.