Energy Conservation Council of Pennsylvania v. Public Utility Commission

25 A.3d 440, 2011 WL 2672541
CourtCommonwealth Court of Pennsylvania
DecidedJuly 11, 2011
Docket899 C.D. 2010, 951 C.D. 2010
StatusPublished
Cited by9 cases

This text of 25 A.3d 440 (Energy Conservation Council of Pennsylvania v. Public Utility Commission) is published on Counsel Stack Legal Research, covering Commonwealth Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Energy Conservation Council of Pennsylvania v. Public Utility Commission, 25 A.3d 440, 2011 WL 2672541 (Pa. Ct. App. 2011).

Opinion

OPINION BY

Judge BUTLER.

Energy Conservation Council of Pennsylvania (ECC) and the Office of Consumer Advocate (OCA) petition for review of the February 12, 2010 and April 23, 2010 orders of the Public Utility Commission (PUC) granting the Applications of PPL Electric Utilities Corporation (PPL) at Docket Nos. A-2009-2082652, A-2009-2082832, A-2009-2088297, A-2009-2088337, A-2009-2088327, A-2009-2088340, A-2009-2088312, A-2009-2088360 to construct a new 500 kV transmission line and substation in Pennsylvania. 1 The *442 issues before this Court are whether the PUC committed errors of law, acted arbitrarily and capriciously, violated Article I, Section 27, of the Pennsylvania Constitution, and/or abused its discretion by approving the proposed line and accompanying facilities, and by allowing construction to begin on the proposed line before a permit is received from the National Park Service for the Wallenpaupack to Bushkill segment. Based upon the following, we affirm the orders of the PUC.

ECC is a Pennsylvania non-profit organization consisting of over 1,600 members dedicated to energy conservation, and to the preservation of the natural beauty, historical sites, and the rural and agricultural character of the Commonwealth. PPL is a public utility and electric distribution company that supplies electricity in eastern and central Pennsylvania under the PUC’s jurisdiction. PPL is a member of PJM Interconnection, L.L.C. (PJM), which is a regional transmission organization approved by the Federal Energy Regulatory Commission (FERC) charged with ensuring the reliability of the electric utilities transmission system, and coordinating the movement of wholesale electricity in all or parts of 13 states and the District of Columbia, including most of Pennsylvania and New Jersey. FERC adopted the North American Electric Reliability Corporation (NERC) as the electric reliability organization for the United States, many of whose standards are mandatory for regional transmission organizations, such as PJM, and their members, like PPL.

PJM annually prepares a regional transmission expansion plan (RTEP) using complex computer modeling or load flow studies to analyze the electric supply needs of customers in its region. PJM uses load deliverability tests (which examine defined load zones in PJM’s region and considers the ability of the transmission system to deliver adequate power to the load zone during a generation capacity emergency) and generator deliverability tests (which evaluate the capability of the transmission system to assure resources can be delivered to the remainder of the PJM system during peak load). PJM is required to apply certain NERC reliability standards to its planning process over the short (years 1 to 5) and long-term (15 years). If PJM identifies NERC criteria violations, it must develop and implement solutions to mitigate them, or suffer penalties. Each year, PJM also reviews previously-approved transmission plans in order to determine whether they are still required, and whether they are required in the year originally identified. This is referred to as retooling.

PPL performs independent analyses of its bulk electric system transmission facilities under PJM’s control, in addition to its non-bulk electric system transmission facilities. It provides the results of its studies to PJM for consideration for its RTEP process. PPL’s planning guidelines are consistent with PJM’s criteria and, in some cases, are more stringent. As a result, PPL may recommend reinforcements and additional projects.

PJM’s 2007 and 2008 RTEPs identified the need for a new line between Pennsylvania and New Jersey, because forecasts reflected that transmission facilities in Pennsylvania would be overloaded by early 2013 (i.e., loading on the transmission facilities was projected to exceed applicable ratings, which may cause permanent dam *443 age to transmission infrastructure and widespread power outages). The 2008 RTEP specifically identified twenty-three NERC Category A and B (single contingency) violations projected to occur beginning in 2012, 2 and twenty-seven NERC Category C5 (double circuit; lower probably event) violations. 3 Accordingly, PJM directed PPL and Public Service Electric & Gas Company (PSE & G) to construct a new line by June 1, 2012. PPL submitted three transmission line alternatives to PJM (no non-transmission alternatives were proposed). A retool study completed by PJM in March of 2009 reduced the number of potential Category A and B reliability issues from twenty-three to thirteen, and the Category C5 violations from twenty-seven to ten. Because it had the greatest positive impact over a 15-year planning horizon, PJM chose the 500 kV Susquehanna-Roseland transmission line, the Pennsylvania portion of which would consist of approximately 101 miles that will run through portions of Lackawanna, Lu-zerne, Monroe, Pike and Wayne counties (proposed line). 4

On January 6, 2009, PPL filed an application with the PUC for authorization to construct the proposed line, part of which would result in the necessary modernization of the approximately 28-miles of the 80-year-old Wallenpaupack to Bushkill 230 kV transmission line, which must take place either as part of this project or as a separate project. Consolidated with that application was PPL’s request for authorization to construct a new substation in Blakely Borough, Lackawanna County, to connect the 500 kV line to the regional transmission system in that area. PPL also filed applications for determination that the proposed exercise of eminent domain over five tracts of land is necessary for the service, accommodation and convenience or safety of the public. The applications were, likewise, consolidated. Notice of the applications was published.

Public hearings were scheduled based upon a request of the OCA and letters from two Pennsylvania state legislators. Notices of appearance were entered by OCA, the Office of Trial Staff (OTS). Petitions to intervene were granted for Wino-na Lake Property Owners Association, 5 UGI Utilities, Inc. (UGI), Pennsylvania American Water Company (PAWC), 6 Exe-lon Generation (Exelon), PPL Industrial Customer Alliance (PPLICA), and Donna *444 Davis, Esquire. 7 Protests were filed by ECC 8 and the Saw Creek Estates Community Association, Inc. (SCECA) and various individuals. Two hearings were held on March 20, 2009.

On April 2, 2009, pursuant to a pre-hearing order issued by the PUC, PPL amended its application to reflect rerouting. Due to public interest, public hearings were held on May 21, 2009 (18 individuals offered testimony) and July 2, 2009 (21 individuals offered testimony). The PUC issued protective orders on June 8 and July 8, 2009, in response to PPL’s unopposed motions.

Evidentiary hearings were held before an administrative law judge (ALJ) on September 1, 2, 4, 8, 9 and 10, 2009.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Com. v. Phillips, N.
Superior Court of Pennsylvania, 2026
Com. v. Smith, N.
2026 Pa. Super. 10 (Superior Court of Pennsylvania, 2026)
Baker, A. v. PPL Elect. Util. Corp.
Superior Court of Pennsylvania, 2024
R.N. Myers v. PA PUC
Commonwealth Court of Pennsylvania, 2023
Twp. of Marple v. PA PUC
Commonwealth Court of Pennsylvania, 2023
City of Lancaster v. PA PUC
Commonwealth Court of Pennsylvania, 2020
Hess v. Pennsylvania Public Utility Commission
107 A.3d 246 (Commonwealth Court of Pennsylvania, 2014)
Robinson Township v. Commonwealth
83 A.3d 901 (Supreme Court of Pennsylvania, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
25 A.3d 440, 2011 WL 2672541, Counsel Stack Legal Research, https://law.counselstack.com/opinion/energy-conservation-council-of-pennsylvania-v-public-utility-commission-pacommwct-2011.