Hess v. Pennsylvania Public Utility Commission

107 A.3d 246, 2014 Pa. Commw. LEXIS 587
CourtCommonwealth Court of Pennsylvania
DecidedDecember 22, 2014
StatusPublished
Cited by8 cases

This text of 107 A.3d 246 (Hess v. Pennsylvania Public Utility Commission) is published on Counsel Stack Legal Research, covering Commonwealth Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hess v. Pennsylvania Public Utility Commission, 107 A.3d 246, 2014 Pa. Commw. LEXIS 587 (Pa. Ct. App. 2014).

Opinions

OPINION BY

Judge McGINLEY.

Marvin Roger Hess and Leona Hess, Ronald and Dianne Mace, Roy and Cindy Maurer, The Shoop Family Trust c/o Edwin and Denny Shoop, and Gary and Dor-ene Lahr (Protestants) Petition for Review of the Order of the Pennsylvania Public Utility Commission (Commission) which approved the Applications of PPL Electric Utilities Corporation (PPL)1, to exercise the power of eminent domain to acquire rights-of-way and easements over certain lands of Protestants for construction of a new eleven-mile transmission line and substation.

PPL is a public utility and an electric distribution company as defined in Sections 102 and 2803 of the Public Utility Code (Code), 66 Pa.C.S. §§ 102, 2803. PPL is also a “public utility corporation” as defined in Section 1103 of the Business Corporation Law of 1988 (BCL), 15 Pa. C.S. § 1103. PPL furnishes electric distribution, transmission, and supplier of last resort services in a service area covering all or part of twenty-nine counties in eastern and central Pennsylvania.

Relevant Statutory Law

PPL is statutorily obligated to provide “safe and reliable” service to its customers. Section 1501 of the Code provides, in relevant part, as follows:

Every public utility shall furnish and maintain adequate, efficient, safe and reasonable service and facilities and shall make all such repairs, changes, alterations, substitutions, extensions, and improvements in or to such service and facilities as shall be necessary or proper for the accommodation, convenience, and safety of its patrons, employees, and the public. Such service also shall be reasonably continuous and without unreasonable interruptions or delay.

66 Pa.C.S. § 1501.

To meet this obligation, the BCL authorizes public utility corporations, like PPL, to:

(a) ... take, occupy and condemn prop- . erty for one or more of the following principal purposes and ancillary purposes reasonably necessary or appropriate for the accomplishment of the principal purposes:
(3) The production, generation, manufacture, transmission, storage, distribution, or furnishing of ... electricity-

15 Pa.C.S. § 1511(a)(3). (Emphasis added.)

[250]*250Before PPL may exercise its power of eminent domain, it must first seek and obtain a certificate of public convenience for approval from the Commission. The BCL provides the Commission with the power to. authorize the condemnation of property as necessary for construction of the transmission line if the Commission determines that the service to be furnished by the utility is “necessary or proper for the service, accommodation, convenience, or safety of its patrons, employees and the public:”

(c) Public Utility Commission Approval. — The powers conferred by subsection (a) may be exercised to condemn property outside the limits of any street, highway, water or other public way or place for the purpose of erecting poles or running wires or other aerial electric, intrastate aerial telephone or intrastate aerial telegraph facilities only after the Pennsylvania Public Utility Commission, upon application of the' public utility corporation, has found and determined, after notice and opportunity for hearing, that the service to be furnished, by the corporation through the exercise of those powers is necessary or proper for the service, accommodation, convenience or safety of the public ....

15 Pa.C.S. § 1511(c). (Emphasis added.)

Here, PPL seeks to condemn certain portions of properties owned by Protestants to construct a new 11.54 mile .long 69 kilovolt (kV) transmission2 tie line known as the Richfield-Dalmatia 69 kV Tie Line (hereinafter “New Transmission Tie Line”) and a new Meiserville 69 12 kV Substation 3 (hereinafter “New Substation”).

PPL’s Applications Pursuant to 15 Pa.C.S. § 1511(c)

In October 2011, PPL filed ten Applications with the Commission pursuant to 15 Pa.C.S. § 1511(c) seeking approval to condemn portions of Protestants’ properties to accommodate the New Transmission Tie Line and New Substation.4

In its Application, PPL stated that the purpose of the New Transmission Tie Line and New Substation is “to resolve violations of reliability standards set forth in PPL Electric’s Reliability Principles & Practices Manual (RP & P Guidelines) applicable to 69 kV transmission lines and 12 kV distribution lines.” Application of PPL Electric Utilities Corporation (Application), October 11, 2011, ¶ 10 at 4; Reproduced Record (R.R.) at 18a. The New Transmission Tie Line will connect the existing Juniata-Richfield 69 kV .line with the existing Sunbury-Dauphin 69 kV line. According to PPL’s “Necessity Statement,” the project, which will cross Protestants’ properties, is required to “improve reliability in both PPL’s transmission and distribution systems to adhere to PPL’s RP & P [Guidelines].” Necessity Statement attached to Application as Exhibit No. 1, at 4; R.R. at 58a.

With regard to meeting transmission standards, PPL averred that in the event [251]*251of an outage on the existing Juniata-Rich-field 69 kV transmission line, approximately forty-four megawatts (MW) of load would remain interrupted until repairs were completed or additional reinforcements were provided. This would be a violation of the RP & P Guidelines.5 An outage on the Sunbury-Dauphin 69 kV transmission line would cause approximately ten MW of load to remain interrupted until repairs were made and field switching is completed. Although this particular situation on the Sunbury-Dauphin line is not a violation of PPL’s RP & P Guidelines, an outage encountered under 2012 peak conditions on the Sunbury-Dau-phin 69 kV line due to a line failure would result in approximately thirty-three MW of load to remain interrupted after all field switches are complete. This is a violation of the RP & P Guidelines. The proposed project will resolve these load restoration issues with the Sunbury-Dauphin line.

PPL stated that the proposed New Transmission Tie Line will provide for quick restoration of electric service by providing additional transmission capacity and load transfer capability for loss of either the Juniata-Richfield 69 kV line or the Sunbury-Dauphin 69 kV line. It will reduce the duration of any outage by improving PPL’s ability to transfer load from one transmission line to another in the event of an outage on either the Juniata-Richfield 69 kV line or the Sunbury-Dau-phin 69 kV line.

With regard to meeting standards at the distribution level, PPL indicated that the existing “Dalmatia 36-02” 12 kV distribution line which services a substantial area violated “several guidelines of PPL Elec-trie’s RP & P [Guidelines], and it has been among the worst performing lines on PPL Electric’s system.” Application ¶ 19, at 6; R.R. at 20a. PPL’s RP & P Guidelines provide that “no more than 1,300 customers should be served from a 12 kV circuit, and that a 12 kV circuit should not supply more than 50 circuit miles of distribution lines.” Application ¶ 20, at 6; R.R. at 20a. “The Dalmatia 36-02 12 kV distribution line currently exceeds PPL Electric’s RP & P guidelines.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Twp. of Marple v. PA PUC
Commonwealth Court of Pennsylvania, 2026
J. Kline v. PA PUC
Commonwealth Court of Pennsylvania, 2026
Center Twp., Butler County v. PA PUC
Commonwealth Court of Pennsylvania, 2024
P. & C. Hughes v. PA PUC
Commonwealth Court of Pennsylvania, 2024
The Tenant Union Representative Network v. PA PUC
Commonwealth Court of Pennsylvania, 2024
P.M. Cicero v. PA PUC
Commonwealth Court of Pennsylvania, 2023
Transource PA, LLC, & PPL Electric Utilities Corp. v. PA PUC
Commonwealth Court of Pennsylvania, 2022
E. Walden v. PUC
Commonwealth Court of Pennsylvania, 2022
New Garden Twp. v. PA PUC
Commonwealth Court of Pennsylvania, 2020
Red Lion Municipal Auth. v. PA PUC
Commonwealth Court of Pennsylvania, 2019

Cite This Page — Counsel Stack

Bluebook (online)
107 A.3d 246, 2014 Pa. Commw. LEXIS 587, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hess-v-pennsylvania-public-utility-commission-pacommwct-2014.