Transource PA, LLC, & PPL Electric Utilities Corp. v. PA PUC

CourtCommonwealth Court of Pennsylvania
DecidedMay 5, 2022
Docket689 C.D. 2021
StatusUnpublished

This text of Transource PA, LLC, & PPL Electric Utilities Corp. v. PA PUC (Transource PA, LLC, & PPL Electric Utilities Corp. v. PA PUC) is published on Counsel Stack Legal Research, covering Commonwealth Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Transource PA, LLC, & PPL Electric Utilities Corp. v. PA PUC, (Pa. Ct. App. 2022).

Opinion

IN THE COMMONWEALTH COURT OF PENNSYLVANIA

Transource Pennsylvania, LLC, and : PPL Electric Utilities Corporation, : Petitioners : : v. : No. 689 C.D. 2021 : Argued: March 7, 2022 Pennsylvania Public Utility : Commission, : Respondent :

BEFORE: HONORABLE RENÉE COHN JUBELIRER, President Judge HONORABLE ELLEN CEISLER, Judge HONORABLE LORI A. DUMAS, Judge

OPINION NOT REPORTED

MEMORANDUM OPINION BY PRESIDENT JUDGE COHN JUBELIRER FILED: May 5, 2022

Transource Pennsylvania, LLC (Transource) and PPL Electric Utilities Corporation (PPL) (together, Petitioners) petition for review of the May 24, 2021 Opinion and Order of the Pennsylvania Public Utility Commission (Commission) that, in relevant part, denied an application and an amended application for the siting and construction of two high-voltage (HV) transmission lines related to the Independence Energy Connection (IEC) Project in Franklin and York Counties, Pennsylvania (Siting Applications), and rescinded the provisional certificate of public convenience (CPC) that the Commission had previously granted Transource for the IEC Project. The Commission concluded that there was no error or abuse of discretion in the Administrative Law Judge’s (ALJ) determination that Transource failed to establish the requisite need for the IEC Project under Section 57.76(a)(1) of the Commission’s Regulations (Regulations), 52 Pa. Code § 57.76(a)(1), or met the requirements of Section 1501 of the Public Utility Code (Code), 66 Pa.C.S. § 1501. The Commission held that the ALJ’s findings of fact were supported by substantial evidence, in the form of the credited evidence submitted by opposing or objecting parties. The Commission further concluded that the ALJ’s determinations, including that the Commission could evaluate the need for the IEC Project for purposes of Pennsylvania law independently of the evaluation of need for the IEC Project that had been performed by PJM Interconnection LLC (PJM), were consistent with the Code, the Regulations, and Pennsylvania law.1 On appeal, Petitioners argue that the Commission erred in interpreting Section 1501 of the Code and Section 57.76(a)(1) of the Regulations and used an incorrect standard in denying the Siting Applications. Petitioners assert that the findings of fact necessary to support the conclusion of a lack of need or necessity for the IEC Project were not supported by substantial evidence. As part of its evidentiary challenge, Petitioners assert that the Commission erred in rejecting PJM’s findings as evidence of need for the IEC Project under Pennsylvania law and in focusing only on the negative impacts on local rates. Finally, Petitioners maintain that the Commission erred in rescinding the provisional CPC and not resolving the merits of Petitioners’ other Exceptions based on its decision on the Siting Applications, and, therefore, this matter must be remanded.

1 The ALJ also recommended denying the Siting Applications because Transource did not establish that it met the requirements of the other subparts of Section 57.76(a) of the Regulations and denying applications related to the construction of structures related to the IEC Project in Franklin and York Counties and to exercise the power of eminent domain over properties in Franklin County. (Recommended Decision (R.D.) at 103-24, Order.) Petitioners filed Exceptions to these determinations, but because the Commission affirmed the denial of the Siting Applications on the lack of need, it did not specifically address these Exceptions beyond finding that they were moot. (Commission Opinion and Order (Op. and Order) at 64-65, 67-73.)

2 The Commission and Intervenors, the Office of Consumer Advocate (OCA), the County of Franklin (Franklin County), and Stop Transource Franklin County (STFC), respond that the Commission’s interpretations of the Code and the Regulations were not clearly erroneous and, therefore, are entitled to deference. They further argue that the Commission applied the correct standard in determining that Transource did not meet its burden of proof on the Siting Applications and rescinding the provisional CPC. The Commission and Franklin County also assert that Petitioners have waived certain of these issues as they had not been raised before the Commission. Intervenors and the Commission further argue that the findings of fact are supported by substantial evidence and that Petitioners’ arguments to the contrary improperly seek to have this Court reweigh the evidence or to preclude the Commission from performing its own evidentiary review and consideration of the IEC Project. Finally, the Commission asserts there was no error in it not considering Petitioners’ other Exceptions based on its determination on the Siting Applications.

I. BACKGROUND A. Relevant Statutory Provisions This matter involves the denial of the Siting Applications and the rescission of Transource’s provisional CPC pursuant to Section 57.76(a) of the Regulations and Section 1501 of the Code. Section 1501 of the Code addresses, generally, the character of services and facilities of a public utility and provides, in pertinent part:

Every public utility shall furnish and maintain adequate, efficient, safe, and reasonable service and facilities, and shall make all such repairs, changes, alterations, substitutions, extensions, and improvements in or to such service and facilities as shall be necessary or proper for the accommodation, convenience, and safety of its patrons, employees, and the public. . . . Such service and facilities shall be in conformity with the regulations and orders of the [C]ommission.

3 66 Pa.C.S. § 1501. Section 57.76(a) of the Regulations relates to the siting and construction of HV lines and states:

(a) The Commission will issue its order, with its opinion, if any, either granting or denying the application, in whole or in part, as filed or upon the terms, conditions or modifications, of the location, construction, operation or maintenance of the line as the Commission may deem appropriate. The Commission will not grant the application, either as proposed or as modified, unless it finds and determines as to the proposed HV line:

(1) That there is a need for it.

52 Pa. Code § 57.76(a)(1). Pursuant to Section 57.75(e)(1) of the Regulations, in reviewing a siting application, the Commission must accept evidence of, among other things, the “present and future necessity of the proposed HV line in furnishing service to the public.” 52 Pa. Code § 57.75(e)(1). In addition, this matter implicates Pennsylvania’s participation in regional interstate power pools with other states, which is addressed in Section 2805(a) of the Code. Section 2805(a) provides:

The [C]ommission shall take all necessary and appropriate steps to encourage interstate power pools to enhance competition and to complement industry restructuring on a regional basis. The Commonwealth, the [C]ommission and Pennsylvania electric utilities shall work with the Federal Government, other states in the region and interstate power pools to accomplish the goals of restructuring and to establish independent system operators or their functional equivalents to operate the transmission system and interstate power pools. The [C]ommission, Pennsylvania electric utilities and all electricity suppliers shall work with the Federal Government, other states in the region, the North American Electric Reliability Council [(NERC)] and its regional coordinating councils or their successors, interstate power pools, and with the independent system operator or its functional equivalent to ensure the continued provision of adequate, safe and reliable electric service to the citizens and businesses of this Commonwealth.

4 66 Pa.C.S. § 2805(a).2

B.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Elite Industries, Inc. v. Pennsylvania Public Utility Commission
832 A.2d 428 (Supreme Court of Pennsylvania, 2003)
Borough of Duncannon v. Pennsylvania Public Utility Commission
713 A.2d 737 (Commonwealth Court of Pennsylvania, 1998)
Riverwalk Casino, L.P. v. Pennsylvania Gaming Control Board
926 A.2d 926 (Supreme Court of Pennsylvania, 2007)
Samuel J. Lansberry, Inc. v. Pennsylvania Public Utility Commission
578 A.2d 600 (Commonwealth Court of Pennsylvania, 1990)
Popowsky v. Pennsylvania Public Utility
706 A.2d 1197 (Supreme Court of Pennsylvania, 1997)
Energy Conservation Council v. Public Utility Commission
995 A.2d 465 (Commonwealth Court of Pennsylvania, 2010)
Se-Ling Hosiery, Inc. v. Margulies
70 A.2d 854 (Supreme Court of Pennsylvania, 1950)
In Re Condemnation by the County of Allegheny
633 A.2d 1325 (Commonwealth Court of Pennsylvania, 1993)
Slawek v. BD. OF MED. ED. & LICENSURE
586 A.2d 362 (Supreme Court of Pennsylvania, 1991)
Popowsky v. Pennsylvania Public Utility Commission
910 A.2d 38 (Supreme Court of Pennsylvania, 2006)
Popowsky v. Pennsylvania Public Utility Commission
937 A.2d 1040 (Supreme Court of Pennsylvania, 2007)
HIKO Energy, LLC v. Pennsylvania Public Utility Commission
163 A.3d 1079 (Commonwealth Court of Pennsylvania, 2017)
Hess v. Pennsylvania Public Utility Commission
107 A.3d 246 (Commonwealth Court of Pennsylvania, 2014)
Uniontown Area School District v. Pennsylvania Human Relations Commission
313 A.2d 156 (Supreme Court of Pennsylvania, 1973)

Cite This Page — Counsel Stack

Bluebook (online)
Transource PA, LLC, & PPL Electric Utilities Corp. v. PA PUC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/transource-pa-llc-ppl-electric-utilities-corp-v-pa-puc-pacommwct-2022.