West Penn Power Co. v. Pennsylvania Public Utility Commission

381 A.2d 1337, 33 Pa. Commw. 403, 1978 Pa. Commw. LEXIS 828
CourtCommonwealth Court of Pennsylvania
DecidedJanuary 26, 1978
DocketAppeals, Nos. 1592 and 1665 C.D. 1976
StatusPublished
Cited by10 cases

This text of 381 A.2d 1337 (West Penn Power Co. v. Pennsylvania Public Utility Commission) is published on Counsel Stack Legal Research, covering Commonwealth Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
West Penn Power Co. v. Pennsylvania Public Utility Commission, 381 A.2d 1337, 33 Pa. Commw. 403, 1978 Pa. Commw. LEXIS 828 (Pa. Ct. App. 1978).

Opinion

Opinion by

President Judge Bowman,

These cross appeals bring before us for review an order of the Pennsylvania Public Utility Commission (PUC) dated July 7, 1976, disallowing in its entirety the second step of a two-stage tariff supplement filed by West Penn Power Company (West Penn), the appellant at No. 1592 C.D. 1976. The appellant at No. 1665 C.D. 1976 is the Commonwealth as a customer protes[405]*405taut before the PUC in the rate proceedings culminating in the contested PUC order.

On October 1, 1974, West Penn filed with the PUC a two-stage tariff supplement, the first stage of which was designed to increase operating revenues by $9,-912,950. or 4.9% based upon the level of operations as of June 30, 1974, the end of the test year employed by West Penn in its projections. The second stage would increase operating revenues an additional $15,-005,900. (7.3%) or a total increase in revenues of $24,-918,850., an overall percentage increase of 12.2% above those of the test year.

The first stage increases were not suspended, they became effective November 30, 1974, and are presently being charged to customers. The second stage proposed tariffs were suspended by the PUC' for two successive periods from November 26, 1974 to August 30, 1975. Since then to the date of the PUC order from which these appeals were taken, these second stage tariffs were, by order of the PUC, designated as temporary rates.

This rate proceeding before the PUC was bitterly contested by a host of protestants, including individual customers of West Penn, industrial customers and state and local government customers. Twenty-one months have expired between the tariff filing and the issuance of the PUC order here contested. Most unfortunately for all concerned, this case must be remanded to'the PUC because of its failure to make adequate factual determinations in support of its conclusion that West Penn’s second stage tariff supplement should be denied in its entirety. Without supporting explanation or reason, the majority of the Commissioners simply concluded that West Penn’s fair value is $816,225,000. and that a reasonable rate of return thereon is 7.92%, which conclusion produced .the remarkable result of. disallowing to the dollar West [406]*406Penn’s second stage tariff supplement. While such a conclusion as to fair value and fair rate of return may be justified, the result it produced not only makes it suspect but, more importantly, the want of adequate discussion and critical findings of fact leading to the conclusion does not enable us to perform our judicial role. To pass upon the merits of these appeals on the present record before us would cast us in the role of making an independent judgment on the merits based upon the whole record before us, a role not given to-us by-law nor one which we are qualified to assume.1 At the conclusion of. the rate proceedings, the PTJC staff was directed to, and some time later did, present its report and a proposed order to be considered by the Commissioners at a public meeting on July 7,1976, the date of the PUC order in issue. The staff report would have allowed over the first stage tariff supplement an additional $8,450,000. of operating revenues of the $15,005,900. sought by West Penn. In itself, this staff report is not controlling nor are the Commissioners bound to accept it in whole or in part.. Its significance in these appeals lies in the fact that the staff report and recommended order, consisting of over 100 pages, comprise, with several exceptions hereinafter noted,- the' order of the PUC in question and was adopted in principle by the minority opinion of the Commissioners.

The dominant difference found in the PUC order and that of the dissenting Commissioners directs itself to the reserve capacity of West Penn as the result of it's completion of a new generating capacity at its Harrison; Unit No. 3 for use in December 1974. In the PUC order, as in the staff report, the generating ca[407]*407pacity of "West Penn is detailed, discussed at length relative to present and future needs and as to complaints of protestors asserting an excessive reserve capacity that should not be charged to present customers. After factually posturing and discussing this issue, the order on this point concludes that West Penn’s reserve capacity is excessive and that “[e]xcess capacity must be considered in determination of our fair value of plant for rate making purposes,” a view not wholly shared by the minority report. However, it is not this finding itself nor the fact that the minority Commissioners disagreed with it that is of controlling significance. Rather it is the total want of the application, of this finding, except by ultimate conclusion, to West Penn’s fair value or its fair rate of return vis-a-vis the second step tariff supplement. One searches in vain to the ultimate conclusion of the order as to the impact of a finding of excess reserve capacity. In reviewing the conclusion that West Penn’s fair value is fixed at $816,225,000., we are informed only that West Penn’s excess reserve capacity has been taken into consideration. We are left uninformed and free to speculate as what percentage of West Penn’s reserve capacity has been found to be excessive and the impact of this “excess” upon West Penn’s fair value of plant.

Without detailing all the pertinent parts of the order, similar statements and critical unsupported conclusions are found in this order. For example, with respect to the fair rate of return as influenced by cost of borrowed money and equity capital, excess reserve capacity is also mentioned. It is stated in that portion of the order dealing with fair rate of return that the finding of excess reserve capacity “shall be taken into consideration” and that the cost of money “probably would have been lower had not West Penn obtained funds to increase reserve capacity.” Having [408]*408been advised that this factor is to be taken into consideration and that West Penn’s cost of money would probably have been lower if it had not invested in excess reserve capacity, we again are left wholly uninformed as to how this was taken into consideration in the ultimate finding of a fair rate of return of 7.92% on fair value-of $816,225,000. and the “probability” of increased cost of capital is left at just that. The minority opinion of the dissenting Commissioners aptly delineates the shortcomings of the order in question.

It states:

It is incomprehensible how the majority can conclude, without the benefit of an analysis of the changes in all figures of the staff report, that respondent is entitled to no additional increase in rates merely because questions were raised about reserve capacity. The key question is what would be the allowable operating revenues if changes were made to all figures in the staff report to delete the effects of Harrison Unit No. 3. That question cannot be answered, as the majority did, by an arbitrary assumption that the temporary-rate level would be the level of the permanent rates. It is the duty of this Commission to base its orders upon facts, and without an analysis of the changes in all figures of the staff report, the action of the majority on July 7, 1976, was without support or justification. The staff was directed to prepare an order reaching the conclusion that the temporary-rate level would be the permanent level of rates, and this can be done only by ignoring the facts, departure from principles of regulatory law and reaching urisupportable conclusions.

In Pennsylvania Gas and Water Co. v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Duquesne Light Co. v. Pennsylvania Public Utility Commission
643 A.2d 130 (Commonwealth Court of Pennsylvania, 1994)
Pennsylvania Electric Co. v. Pennsylvania Public Utility Commission
467 A.2d 1367 (Commonwealth Court of Pennsylvania, 1983)
Cohen v. Pennsylvania Public Utility Commission
463 A.2d 1274 (Commonwealth Court of Pennsylvania, 1983)
Peoples Natural Gas Co. v. Pennsylvania Public Utility Commission
409 A.2d 446 (Commonwealth Court of Pennsylvania, 1979)
Columbia Gas of Pennsylvania, Inc. v. Pennsylvania Public Utility Commission
400 A.2d 1321 (Commonwealth Court of Pennsylvania, 1979)
Philadelphia Suburban Water Co. v. Pennsylvania Public Utility Commission
394 A.2d 1063 (Commonwealth Court of Pennsylvania, 1978)
Octoraro Water Co. v. Commission
391 A.2d 1129 (Commonwealth Court of Pennsylvania, 1978)
City of Pittsburgh v. Commonwealth
386 A.2d 624 (Commonwealth Court of Pennsylvania, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
381 A.2d 1337, 33 Pa. Commw. 403, 1978 Pa. Commw. LEXIS 828, Counsel Stack Legal Research, https://law.counselstack.com/opinion/west-penn-power-co-v-pennsylvania-public-utility-commission-pacommwct-1978.