Pennsylvania Electric Co. v. Pennsylvania Public Utility Commission

467 A.2d 1367, 78 Pa. Commw. 402
CourtCommonwealth Court of Pennsylvania
DecidedNovember 18, 1983
DocketAppeals, Nos. 1645 C.D. 1981, 2018 C.D. 1981,1641 C.D. 1981 and 2019 C.D. 1981
StatusPublished
Cited by5 cases

This text of 467 A.2d 1367 (Pennsylvania Electric Co. v. Pennsylvania Public Utility Commission) is published on Counsel Stack Legal Research, covering Commonwealth Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pennsylvania Electric Co. v. Pennsylvania Public Utility Commission, 467 A.2d 1367, 78 Pa. Commw. 402 (Pa. Ct. App. 1983).

Opinion

Opinion by

President Judge Crumlish, Jr.,

We have consolidated for argument and disposition the four appeals of Pennsylvania Electric Company (Penelec) and Metropolitan Edison Company (MetEd) from four orders of the Public Utility Commission (Commission) entered June 8, 1981 and July 27, 1981. The two Commission orders entered June 8, 1981 dismissed the complaints of Penelec and Met-Ed against temporary rates previously fixed by the Commission by orders entered May 23, 1980. The two Commission orders of July 27, 1981, allowed Penelec and Met-Ed annual rate increases of $55,445,000 and $51,804,000, respectively. We affirm.

History oe the Case

This proceeding is another repercussion of -the March 28, 1979 accident at the Three Mile Island nuclear-powered generating station Unit No. 2 (TMI-2). Met-Ed and Penelec own a 50% and 25% interest, respectively, in the generating station.1 In response to the accident, the Commission set temporary rates for Met-Ed on April 19, 1979 and for Penelec on April 25, 1979, reflecting the removal of TMI-2 related costs. The Commission adopted an order on June 15, 1979, [405]*405concluding in part that TMI-2 was no longer used and useful in public service and all costs associated with that unit must be removed from rates.2 Pursuant to this conclusion, the Commission made permanent the temporary rates then in effect.

At the time of the accident, Unit No. 1 (iTMI-1) had been shut down for refueling. On September 20, 1979, the Commission ordered Met-Ed and Penelee to show cause why TMI-1 should be considered used and useful and why all co.sts associated therewith .should not be removed from rates.3 On November 27, 1979, MetEd and Penelee proposed that a future test year be utilized to provide the necessary factual basis for revision of the rates of the companies if TMI-1 were to be removed from their respective rates. In a prehearing order adopted December 21, 1979, the Commission declined to set a test year for such purposes on the grounds that the level of just and reasonable rates for Met-Ed and Penelee were not then an issue before the Commission in that proceeding.

By order of May 23, 1980, the Commission determined that TMI-1 was not used or useful in the public service. Accordingly, TMI-1 was excluded from the rate bases of Met-Ed and Penelee. Pursuant to Section 1310 of the Public Utility Code (Code), 66 Pa. C. S. §1310, the Commission established temporary rates for Met-Ed and Penelee at an annual level which was $26.9 million and $11.7 million, respectively, less than their existing rates. This decrease reflected the exclusion of TMI-1 from the companies ’ rate bases.

[406]*406On July 29, 1980, both Met-Ed and Penelec filed complaints against tbe respective temporary rates, alleging that these temporary rates were unjust and unreasonable. Pursuant to .Section 1308(d) of tbe Code, Met-Ed and Penelec also filed Tariff No. 44 seeking a $76.4 million increase in rates and Tariff No. 75, seeking a $67.4 million increase in rates, respectively. Testimony was taken before tbe ALJ on twenty-two days between October 20, 1980 and January 23, 1981. The ALJ recommended in bis March 20, 1981 decision that Met-Ed’s and Penelec’s complaints against temporary rates be dismissed. Tbe Commission’s order of June 8, 1981, adopted this decision. Tbe Commission’s final orders of July 27, 1981, allowed Met-Ed an annual rate increase of $51,804,000 (including $11 million covering TMI-,1 restart costs) over and above tbe temporary rates and allowed Penelec an annual rate increase of $55,445,000 (including $5.5 million covering TMI-1 restart costs) over and above tbe temporary rates.

Tbe companies bave raised a number of issues on appeal. First, with regard to tbe temporary rates, the companies contend that tbe record compels the conclusion that they bave proven tbe need for an increase in tbe level of their temporary rates of at least $11.7 million for Penelec and $26.9 million for Met-Ed. Further, tbe companies contend that retroactive recoupment is required in connection with any shortfall which is found to exist in tbe adequacy of tbe Commission fixed temporary rates. Second, the companies contend that tbe final rates under tbe July 27, 1981 order are not just and reasonable pursuant to statutory and constitutional standards. Third, tbe companies pray that tbe Commission’s order of July 27, 1981, should be clarified to ensure that benefits of present reserve capacity expense credits shall flow in tbe future only to those parties who are reasonably entitled to those benefits.

[407]*407Our scope of review is limited to a determination of whether constitutional rights have been violated, an error of law has been committed, or the findings or order of the Commission are not supported by substantial evidence. Park Towne v. Pennsylvania Public Utility Commission, 61 Pa. Commonwealth Ct. 285, 289, 433 A.2d 610, 613 (1981).

Temporary Rate Increase

The companies’ argument as to the Commission’s fixed temporary rates is twofold. They contend first that the ALJ’s findings as adopted by the Commission are inconsistent; and second, that retroactive recoupment is required in connection with any shortfall which is found to exist in the adequacy of the temporary rates. The alleged inconsistency lies in that the ALJ found, based on the future test year ending March 31, 1981, the annual revenue requirements of Penelec and Met-Ed to be $54,890,000 and $49,789,000 above the temporary rates. Yet, he also found that neither Met-Ed nor Penelec met their burden of .showing that the temporary rates were not just and reasonable.

We hold that the ALJ’s finding as to the future test year revenue requirements entitles the companies to prospective rate relief only. The fact that the Commission has granted a prospective rate increase does not establish the unreasonableness of the lower temporary rates previously in effect. See Pendergast v. New York Telephone Co., 262 ILS. 43 (1923). Indeed, the very reason for the lower temporary rates was continued and followed by the Commission in its granting of the permanent rate increases. Just as the operating expenses and capital costs of TMI-1 were removed from the companies ’ then-existing rate bases to establish the temporary rates, these expenses and costs were not included in the rate bases to determine [408]*408the permanent rate increases granted by the Commission.

The companies also submit that retroactive recoupment is required in connection with any shortfall which is found to exist in. the adequacy of the Commission’s fixed temporary rates. They argue that, since the Commission endorsed the AUJ’s recommended finding as to the required permanent rate increases, there are shortfalls, per se, in the level of the temporary rates. Therefore, they contend that they should be able to recoup, at the very least, $26.9 million for Met-Ed and $11.7 million for Penelec of these shortfalls.

'Section 1310 of the Code does create a “retroactive ratemaking mechanism by requiring the Commission to consider the effect of inadequate rates set on a temporary basis when fixing the amount of permanent rates thereafter approved.” See Bell Telephone Co. of Pennsylvania v. Pennsylvania Public Utility Commission, 69 Pa. Commonwealth Ct.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bell Atlantic-Pennsylvania, Inc. v. Pennsylvania Public Utility Commission
763 A.2d 440 (Commonwealth Court of Pennsylvania, 2000)
Pennsylvania Electric Co. v. Pennsylvania Public Utility Commission
502 A.2d 130 (Supreme Court of Pennsylvania, 1985)
Lukens Steel Co. v. Pennsylvania Public Utility Commission
499 A.2d 1134 (Commonwealth Court of Pennsylvania, 1985)
Iowa Planners Network v. Iowa State Commerce Commission
373 N.W.2d 106 (Supreme Court of Iowa, 1985)
Middletown Township v. Pennsylvania Public Utility Commission
482 A.2d 674 (Commonwealth Court of Pennsylvania, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
467 A.2d 1367, 78 Pa. Commw. 402, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pennsylvania-electric-co-v-pennsylvania-public-utility-commission-pacommwct-1983.