Iowa Planners Network v. Iowa State Commerce Commission

373 N.W.2d 106, 1985 Iowa Sup. LEXIS 1121, 1985 WL 1083667
CourtSupreme Court of Iowa
DecidedAugust 21, 1985
Docket84-1429
StatusPublished
Cited by11 cases

This text of 373 N.W.2d 106 (Iowa Planners Network v. Iowa State Commerce Commission) is published on Counsel Stack Legal Research, covering Supreme Court of Iowa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Iowa Planners Network v. Iowa State Commerce Commission, 373 N.W.2d 106, 1985 Iowa Sup. LEXIS 1121, 1985 WL 1083667 (iowa 1985).

Opinion

*108 WOLLE, Justice.

In this appeal ratepayers challenge a decision of the Iowa Commerce Commission granting rate increases to Iowa-Illinois Gas and Electric Company (utility) in response to its proposed tariff filed with the Iowa State Commerce Commission (commission) in February of 1981. Iowa Planners Network (IPN), an advocate for residential ratepayers, intervened in contested case proceedings before the commission to seek elimination of the utility’s proposed return on its investment in excess generating capacity. The commission concluded that the utility was entitled to some return on its excess generating capacity, then adopted a formula which allowed the utility a diminishing rate of return as capacity progressively increased above 125% of the utility’s annual peak load during 1980. The commission also found that the utility correctly allocated to its investors the capital gain on sale of an electric transmission line.

Both the utility and IPN petitioned for judicial review of that final agency decision. The district court rejected the utility’s constitutional challenge to the commission’s rate reduction and ruled on its own motion that IPN lacked standing to contest the commission order. In Iowa-Illinois Gas & Electric Co. v. Iowa State Commerce Commission, 347 N.W.2d 423 (Iowa 1984), we decided that the utility’s challenge lacked merit but concluded that the district court erred in dismissing IPN’s petition for judicial review.

Following remand, the district court addressed IPN’s petition on the merits and upheld the commission decision. IPN has appealed the district court’s judicial review decision, contending that the commission erred (1) in refusing to apply a strict used and useful test to deny the utility any return on its investment in excess generating capacity; (2) in allowing the utility a return on its investment in excess capacity even though the costs associated with that capacity were allegedly excessive and unreasonable; and (3) in allocating to shareholders the gain on sale of capital equipment, a transmission line. We conclude these contentions are without merit and affirm.

Relevant background facts are set forth in our prior decision. When reviewing commission decisions the district court functions in an appellate capacity to apply the standards of Iowa Code section 17A.19(8) and correct errors of law on the part of the agency. Iowa Southern Utilities Co. v. Iowa State Commerce Commission, 372 N.W.2d 274, 277 (Iowa 1985). On appeal we apply those standards in determining whether our conclusions are the same as those of the district court. Northwestern Bell Telephone Co. v. Iowa State Commerce Commission, 359 N.W.2d 491, 495 (Iowa 1984); Lefebure Corp. v. Iowa Department of Job Service, 341 N.W.2d 768, 770 (Iowa 1983). In exercising that function, we must accord proper respect to the expertise of the agency. Northwestern Bell Telephone Co., 359 N.W.2d at 499; United Telephone Co. v. Iowa State Commerce Commission, 257 N.W.2d 466, 470 (Iowa 1977). Unless the evidence would compel the agency to rule in a particular way as a matter of law, the reviewing court must leave it to the agency to make the decisions vested by statute in the agency. Johnston v. Iowa Real Estate Commission, 344 N.W.2d 236, 240 (Iowa 1984).

I. Return on Excess Capacity.

IPN contends that the commission erred in allowing the utility to obtain a return on that portion of its investment which resulted in excess generating capacity. It argues that the commission should have applied a rigid “used and useful” test rather than its own modified formula to determine whether and to what extent the utility was entitled to a return on that investment.

The commission found that the utility had 199 megawatts of excess capacity, defined as that capacity exceeding 125% of the utility’s peak load during 1980. Iowa-Illinois Gas & Electric Co., 347 N.W.2d at 428. It then addressed the question whether that excess capacity should be included in the utility’s rate base, defined as “the utility’s investment in property, used and *109 useful at the time of inquiry, in rendering utility service.” Id. at 427; Davenport Water Co. v. Iowa State Commerce Commission, 190 N.W.2d 583, 588 (Iowa 1971). The commission rejected IPN’s argument that this definition necessarily excluded from the utility’s rate base any property not “used and useful.” It cited with approval the following language of the proposed commission decision:

[The used and useful] approach assumes the utility can accurately predict demand_ However, we must recognize advanced forecasting methods are of recent origin and should not be used in this proceeding to measure the reasonableness of [the utility’s] past decisions. The “used and useful” approach also requires a decision on how much capacity is needed to meet customer demands. [That] may establish a standard of precision that no utility manager can reasonably be expected to meet.

The commission found:

The used and useful test did not provide an answer to the question of whether ratepayers should reimburse Iowa-Illinois for its admittedly prudent investment in total capacity in 1981.

The commission then adopted a formula which allowed the utility to recover a diminishing rate of return on its excess capacity as that capacity exceeded 125% of its 1980 peak load, based on the proportion of common equity investment in that capacity.

The district court on judicial review rejected IPN’s assertion that the commission was required to apply a strict used and useful test to exclude excess capacity from the utility’s rate base. It explained that the commission had authority to use its expertise, background, and experience in selecting an appropriate formula. We agree.

The traditional “used and useful” standard for determining what investments will be included in a utility’s rate base provides that a utility cannot charge its ratepayers for facilities that are not in use or reasonably necessary to furnish the service. See Tennessee Gas Pipeline Co. v. Federal Energy Regulatory Commission, 606 F.2d 1094, 1109 (D.C.Cir.1979); Davenport Water Co., 190 N.W.2d at 588; 73B C.J.S. Public Utilities § 34 (1983).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
373 N.W.2d 106, 1985 Iowa Sup. LEXIS 1121, 1985 WL 1083667, Counsel Stack Legal Research, https://law.counselstack.com/opinion/iowa-planners-network-v-iowa-state-commerce-commission-iowa-1985.