Metropolitan Edison Co. v. Pennsylvania Public Utility Commission

437 A.2d 76, 62 Pa. Commw. 460, 33 U.C.C. Rep. Serv. (West) 483, 1981 Pa. Commw. LEXIS 1865
CourtCommonwealth Court of Pennsylvania
DecidedNovember 18, 1981
DocketAppeal, No. 1509 C.D. 1980
StatusPublished
Cited by25 cases

This text of 437 A.2d 76 (Metropolitan Edison Co. v. Pennsylvania Public Utility Commission) is published on Counsel Stack Legal Research, covering Commonwealth Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Metropolitan Edison Co. v. Pennsylvania Public Utility Commission, 437 A.2d 76, 62 Pa. Commw. 460, 33 U.C.C. Rep. Serv. (West) 483, 1981 Pa. Commw. LEXIS 1865 (Pa. Ct. App. 1981).

Opinion

Opinion by

Judge Williams, Jr.,

Metropolitan Edison Company (Met-Ed) has appealed from an order of the Pennsylvania Public Utility Commission (Commission) directing the company to refund to its ratepaying customers a total sum of $4,657,955.

On March 15, 1976, the Commission filed against Met-Ed a Complaint and Investigation Upon Commission Motion. The complaint averred that components of the company’s fuel cost adjustment surcharge passed on or charged to its ratepayers may have been unjust, unreasonable or unlawful, in that the surcharge may have been used to recover from customers excessive and unjustifiable prices the company had paid to its fuel suppliers. The order instituting the complaint also directed that an investigation be made into the fairness, reasonableness and legality of the charges made and rates received by Met-Ed pursuant of the fuel cost surcharge.1

On January 19, 1977, the Commission amended and supplemented its original complaint to allege that [463]*463Met-Ed had unjustifiably paid more than the contract price on eight specified contracts for the delivery of coal; and that, further, Met-Ed had accepted under those contracts coal that did not meet the British Thermal Unit (BTU) specifications of the contracts. The relief sought by the Commission’s amended complaint was a refund to ratepayers of: (1) the amount Met-Ed paid in excess of the contract base prices and (2) the additional cost associated with the company’s acceptance of BTU-deficient coal from its suppliers. The questioned contract payments and coal deliveries were made during the calendar year of 1974; and, it is the fuel cost adjustment surcharge for that same year which is here in issue.

Met-Ed responded to the amended complaint with an answer which asserted, as an affirmative defense, that the company had a right of managerial discretion in selecting suppliers, in administering its coal contracts, and in accepting the price demands of its coal suppliers. Met-Ed’s answer also asserted that: (1) the prices it paid for the coal were just and reasonable; (2) the Commission’s original complaint was defective; and (3) the fuel cost adjustment provision of the company’s tariff, under which the increased cost of the coal had been passed on to ratepayers, was a “Commission-made rate” and thus not subject to retroactive alteration and refund.

Met-Ed also filed a motion to dismiss the original and amended complaints on the following grounds: (1) that both pleadings were vague and unspecific; and (2) that the refund action was barred by the statute of limitations. In addition, Met-Ed petitioned for a declaratory order granting the motion to dismiss or, in the alternative, an order denying that motion and certifying it for appeal. On June 6, 1977, the Administrative Law Judge denied the motion to [464]*464dismiss and the alternatively petitioned for relief, as well. On November 18, 1977, the Commission affirmed that decision.

Met-Ed next requested a preliminary ruling as to how the burden of proof would be allocated in the proceedings on the merits. On September 5, 1978, the Administrative Law Judge ruled that the utility had to bear the proof burden. That ruling, too, was affirmed by the Commission.

Between September 14 and November 15, 1978, fourteen days of evidentiary hearings were conducted. On October 25, 1979, after the filing of briefs by all parties, the Administrative Law Judge entered his Initial Decision. He found that Met-Ed had failed to exercise managerial prudence in the administration of its coal contracts with three specified coal brokers; and had, thereby, caused its ratepayers to pay unjust rates in 1974. The three named coal brokers were Crown Coal and Coke Company (Crown), Allegheny and Eastern Coal Company (Allegheny) and Kittanning-Freeport Coal Company (Kittanning). The Administrative Law Judge also ordered Met-Ed to refund to its ratepaying customers the total sum of $2,661,639, with interest.

Exceptions to the Initial Decision were filed by all parties. On May 23, 1980, the Commission entered an order whereby it agreed with the determination that the utility had failed to exercise managerial prudence in the administration of the three mentioned contracts and had caused its ratepayers to bear unjust and unreasonable rates under the 1974 fuel cost adjustment provision.2 However, the Commission dis[465]*465agreed with the Administrative Law Judge’s calculation of the refund due: The Commission calculated the utility’s total refund liability to be $4,657,955. From that order followed Met-Ed’s appeal to this Court.

Before this Court, Met-Ed’s threshold contention is that the fuel cost adjustment provision in its tariff represents a “Commission-made rate” and thus cannot be retroactively changed. As support for this argument Met-Ed relies on the decision of the Pennsylvania Supreme Court in Cheltenham & Abington Sewerage Co. v. Pennsylvania Public Utility Commission, 344 Pa. 366, 25 A.2d 334 (1942). In our view, that decision does not address the issue in the case at bar and, accordingly, does not support Met-Ed’s contention.

It is true that in Cheltenham & Abington Sewerage Co. the Supreme Court reversed a Commission decision ordering reparations or refunds for certain years, even though the Commission had found the rates for those years to be unreasonable. However, the basis for the Court’s reversal was that the rates for the years in question had been previously approved by the Commission itself. When the Supreme Court spoke of rates that were “Commission-made,” it was referring to rates stamped with antecedent Commission approval; it was such rates that were held to be immune from retroactive alteration. In the instant case there was no prior Commission proceeding or action giving antecedent approval of the specific surcharges collected by Met-Ed in 1974 pursuant to its fuel cost adjustment provision. Therefore, the concept of a “Commission-made rate” has no application to the present case; and, thus, Met-Ed could not validly expect that the surcharges in issue were insulated from retroactive modification by the Commission.

[466]*466Met-Ed next seeks to defend its managerial decision to pay increased prices in 1974 for the contract coal obtained through the Crown, Allegheny, and Kit-tanning Qompanies. Met-Ed does not dispute that prices actually paid to these brokers exceeded the prices originally contracted for. Moreover, the utility concedes in its Brief that the increased payments to the Crown and Allegheny companies, and most of those to Kittanning, were not justified under any contractual provision. Met-Ed asserts, however, that its decision to accede to the brokers’ demands for the higher prices was sound business judgment in light of “the runaway coal market created by the Arab oil embargo.” In that regard, Met-Ed further argues that when confronted by its brokers with demands for prices higher than the contract terms, it was faced with two options: (1) demand strict adherence to the contract terms, coupled with a threat of legal action; or (2) negotiate contract modifications.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Johnson v. Acc
438 P.3d 656 (Court of Appeals of Arizona, 2019)
Philadelphia Suburban Water Co. v. Pennsylvania Public Utility Commission
808 A.2d 1044 (Commonwealth Court of Pennsylvania, 2002)
Exxon Pipeline v. La Public Service Com'n
728 So. 2d 855 (Supreme Court of Louisiana, 1999)
Indianapolis Power & Light Co. v. Pennsylvania Public Utility Commission
711 A.2d 1071 (Commonwealth Court of Pennsylvania, 1998)
Loma, Inc. v. Pennsylvania Public Utility Commission
682 A.2d 424 (Commonwealth Court of Pennsylvania, 1996)
Popowsky v. Pennsylvania Public Utility Commission
674 A.2d 1149 (Commonwealth Court of Pennsylvania, 1996)
Wisconsin Power & Light Co. v. Public Service Commission
511 N.W.2d 291 (Wisconsin Supreme Court, 1994)
W.C. McQuaide, Inc. v. Pennsylvania Public Utility Commission
585 A.2d 1151 (Commonwealth Court of Pennsylvania, 1991)
Braun v. McKay (In Re McKay)
110 B.R. 764 (W.D. Pennsylvania, 1990)
Allegheny Center Associates v. Pennsylvania Public Utility Commission
570 A.2d 149 (Commonwealth Court of Pennsylvania, 1990)
Pennsylvania Public Utility Commission v. Philadelphia Electric Co.
561 A.2d 1224 (Supreme Court of Pennsylvania, 1989)
Peoples Natural Gas Co. v. Pennsylvania Public Utility Commission
552 A.2d 1135 (Commonwealth Court of Pennsylvania, 1989)
Cunningham v. INS. CO. OF NORTH AMER.
530 A.2d 407 (Supreme Court of Pennsylvania, 1987)
Cunningham v. Insurance Co. of North America
530 A.2d 407 (Supreme Court of Pennsylvania, 1987)
Equitable Gas Co. v. Pennsylvania Public Utility Commission
526 A.2d 823 (Commonwealth Court of Pennsylvania, 1987)
Duquesne Light Co. v. Pennsylvania Public Utility Commission
507 A.2d 433 (Commonwealth Court of Pennsylvania, 1986)
Process Gas Consumers Group v. Pennsylvania Public Utility Commission
480 A.2d 1273 (Commonwealth Court of Pennsylvania, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
437 A.2d 76, 62 Pa. Commw. 460, 33 U.C.C. Rep. Serv. (West) 483, 1981 Pa. Commw. LEXIS 1865, Counsel Stack Legal Research, https://law.counselstack.com/opinion/metropolitan-edison-co-v-pennsylvania-public-utility-commission-pacommwct-1981.