Wisconsin Power & Light Co. v. Public Service Commission

511 N.W.2d 291, 181 Wis. 2d 385, 1994 Wisc. LEXIS 15
CourtWisconsin Supreme Court
DecidedFebruary 8, 1994
Docket91-1096
StatusPublished
Cited by33 cases

This text of 511 N.W.2d 291 (Wisconsin Power & Light Co. v. Public Service Commission) is published on Counsel Stack Legal Research, covering Wisconsin Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wisconsin Power & Light Co. v. Public Service Commission, 511 N.W.2d 291, 181 Wis. 2d 385, 1994 Wisc. LEXIS 15 (Wis. 1994).

Opinions

STEINMETZ, J.

The issue presented in this case is: Does the Public Service Commission of Wisconsin (PSC or commission) have the authority to order a utility to pay a lump sum penalty based on the utility's past imprudent management?

In 1989, the PSC determined that Wisconsin Power and Light Company (WPL or utility) had imprudently administered a coal contract. The commission found that as a result of this alleged imprudence, WPL overcharged its customers for electricity from 1974 until 1989. Accordingly, the PSC ordered WPL to pay $9 million in penalties.

The Dane county circuit court, the Honorable Robert A. De Chambeau, reversed the PSC's order, holding that the penalty constitutes impermissible retroactive ratemaking. The court of appeals affirmed the trial court's order. Wis. Power & Light v. Public Service Comm., 171 Wis. 2d 553, 572, 492 N.W.2d 159 (Ct. App. 1992).

WPL, Madison Gas and Electric (MGE) and Wisconsin Public Service Corporation (WPSC) jointly own [389]*389the Columbia generating station near Portage, Wisconsin. WPL operates the facility. In 1972, WPL entered into a 20-plus-year contract to purchase coal for the Columbia station from Western Energy Coal Company (WECO). Under the terms of the contract, WECO would adjust the cost of the coal to reflect changes in various price indices , and WECO's actual cost of mining. Between October, 1974, when WECO began delivering coal to the Columbia station, and December, 1987, the price WECO charged WPL for coal rose from $2.05 per ton to $10.40 per ton — an average increase of 13.3 percent each year.

As WPL's coal costs increased, so did the rate WPL charged its customers for electricity. WPL set its rates using two different procedures during the period of time in question. From 1974 until October, 1984, the utility based future rates on automatic fuel adjustment clauses (FACs). A FAC is a rate formula, approved by the PSC, that enables a utility to pass on increases in fuel costs directly to the utility's customers without, going through the otherwise mandatory administrative review. Accordingly, while FACs were in place, WPL's customers bore the burden of WECO's higher coal prices.

Beginning in October, 1984, pursuant to the passage of sec. 196.20(4)(b), Stats., the legislature prohibited electric utility companies from setting rates based on FACs. From that time on, the PSC fully scrutinized each projected increase in WPL's rates under standard administrative procedures involving audits and test year estimates. Under these two very distinct rate setting methods — with and without FACs — the PSC did approve 14 WPL rate orders in the 15-year period at issue.

[390]*390In 1985, one of the commission's newly hired fuel auditors suggested to WPL that the utility was paying an unreasonably high price for coal under the WECO contract. Following both an internal audit and an audit conducted by an outside accounting firm, WPL concluded that WECO had overcharged WPL for coal between 1974 and 1987. WPL and WECO subsequently entered into negotiations concerning their contract. As a result of these negotiations, WECO reduced the price of coal from $10.40 per ton to $8.70 per ton and WPL agreed to continue to purchase coal from WECO for an additional ten years. WECO did not, however, refund any money to WPL to cover the overcharges. In addition, WPL waived its right to recover any of the overcharges.

WPL filed an application with the PSC on December 30, 1988, to increase its retail electric rate. Pursuant to this application, the commission conducted an audit of WPL's books, accounts, practices and activities and discovered that WECO had grossly overcharged WPL for coal and that WECO had never refunded any money to WPL. Following extensive hearings, the PSC concluded that WPL had acted imprudently in administering the WECO contract by: 1) failing to notice the overcharges sooner; 2) neglecting to inform the other owners of the Columbia generating station about the overcharges; and 3) waiving any claim to the past overcharges when renegotiating the WECO contract. The commission ordered WPL to pay a penalty of $9 million, substantially less than the estimated $13 million to $52 million in actual overcharges. However, the PSC's findings of fact make it clear that the commission derived the amount of the penalty directly from the actual overcharges. The order requires WPL to pay a portion [391]*391of the penalty in the form of credits to its customers and the remainder as lump sum payments to MGE and WPSC to pass on to their customers.

On November 22, 1989, WPL petitioned the Dane county circuit court for judicial review of the PSC's order pursuant to ch. 227, Stats. In particular, WPL asked the court to decide whether the PSC has the authority to assess the $9 million penalty against the utility and whether the commission's finding that WPL acted imprudently was correct. The trial court reversed the PSC's order, finding that the penalty constitutes impermissible retroactive ratemaking, in violation of sec. 196.37(1), Stats.1 Because this decision disposed of the entire matter, the court did not reach the issue of WPL's alleged imprudence. Before the trial court, WPSC intervened on behalf of WPL. Six corporations, collectively referring to themselves as the Wisconsin Industrial Energy Group (WIEG), intervened on behalf of the PSC.

The PSC and WIEG appealed from the trial court's order. The court of appeals affirmed this order, agreeing with the trial court that the commission violated the rule against retroactive ratemaking. Wis. Power & Light, 171 Wis. 2d at 572.

WIEG offered an alternative argument to both courts. WIEG contended that while FACs were in place, due to WPL's imprudence, the utility had charged a rate above the rate filed with the PSC. This [392]*392violated the filed rate doctrine, codified in see. 196.22, Stats.2 According to WIEG, when a utility violates the filed rate doctrine, the PSC has the power to order the utility to refund excess revenue. Hence, the order does not constitute retroactive ratemaking, but rather a valid exercise of the PSC's authority. Both lower courts rejected this argument. This court accepted the petition for review filed by the PSC and WIEG.

This review presents a question concerning the statutory authority of the PSC to order a utility to refund validly collected revenue. The extent of an agency's statutory authority is a question of law. Thus, courts owe no deference to an agency's determination concerning its own statutory authority. Wis. Environmental Decade v. Public Service Comm., 81 Wis. 2d 344, 351, 260 N.W.2d 712 (1978); GTE North, Inc. v. Public Service Comm., 176 Wis. 2d 559, 564, 500 N.W.2d 284 (1993).

As a creation of the legislature, the PSC "has only those powers which are expressly conferred or which are necessarily implied by the statutes under which it operates." Kimberly Clark Corp. v. Public Service Comm., 110 Wis. 2d 455, 461-62, 329 N.W.2d 143 (1983). No provision in ch. 196, Stats., expressly authorizes the commission to order a utility to refund money to its customers when the utility may have acted imprudently.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Timothy Zignego v. Wisconsin Elections Commission
2020 WI App 17 (Court of Appeals of Wisconsin, 2020)
Alaska Exchange Carriers Ass'n v. Regulatory Commission
262 P.3d 204 (Alaska Supreme Court, 2011)
Andersen v. Department of Natural Resources
2011 WI 19 (Wisconsin Supreme Court, 2011)
LaBeree v. Labor & Industry Review Commission
2010 WI App 148 (Court of Appeals of Wisconsin, 2010)
Centerpoint Energy Entex v. Railroad Commission
208 S.W.3d 608 (Court of Appeals of Texas, 2006)
Fitchburg Gas & Electric Light Co. v. Department of Telecommunications & Energy
801 N.E.2d 220 (Massachusetts Supreme Judicial Court, 2004)
Wisconsin Bell, Inc. v. Public Service Commission
2003 WI App 193 (Court of Appeals of Wisconsin, 2003)
CenturyTel of Midwest-Kendall, Inc. v. Public Service Commission
2002 WI App 236 (Court of Appeals of Wisconsin, 2002)
Matanuska Electric Ass'n v. Chugach Electric Ass'n
53 P.3d 578 (Alaska Supreme Court, 2002)
State Ex Rel. Treat v. Puckett
2002 WI App 58 (Court of Appeals of Wisconsin, 2002)
Wicor Inc. v. United States
117 F. Supp. 2d 855 (E.D. Wisconsin, 1999)
State Public Service Commission v. Wisconsin Bell, Inc.
566 N.W.2d 496 (Court of Appeals of Wisconsin, 1997)
Faber v. Musser
550 N.W.2d 808 (Wisconsin Supreme Court, 1997)
Schenkoski v. Labor & Industry Review Commission
552 N.W.2d 120 (Court of Appeals of Wisconsin, 1996)
Matter of Petition for Incorporation of Town of Pewaukee
521 N.W.2d 453 (Court of Appeals of Wisconsin, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
511 N.W.2d 291, 181 Wis. 2d 385, 1994 Wisc. LEXIS 15, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wisconsin-power-light-co-v-public-service-commission-wis-1994.