Southern California Edison Co. v. Public Utilities Commission

576 P.2d 945, 20 Cal. 3d 813, 144 Cal. Rptr. 905, 24 P.U.R.4th 588, 1978 Cal. LEXIS 203
CourtCalifornia Supreme Court
DecidedMarch 23, 1978
DocketS.F. 23500
StatusPublished
Cited by38 cases

This text of 576 P.2d 945 (Southern California Edison Co. v. Public Utilities Commission) is published on Counsel Stack Legal Research, covering California Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Southern California Edison Co. v. Public Utilities Commission, 576 P.2d 945, 20 Cal. 3d 813, 144 Cal. Rptr. 905, 24 P.U.R.4th 588, 1978 Cal. LEXIS 203 (Cal. 1978).

Opinions

Opinion

MOSK, Acting C. J.

By this petition for writ of review Southern California Edison Company (Edison) challenges the lawfulness of portions of Decision No. 85731 of respondent Public Utilities Commission which require it to amortize, by 36 months of billing credit to its customers, substantial overcollections generated by operation of its “fuel cost adjustment clause.” Edison’s principal contention is that because the funds in issue were lawfully collected pursuant to a rate structure found by the commission to be just and reasonable at the time, the order to return them constitutes illegal “retroactive ratemaking.” We conclude that the contention is without merit and the decision should be affirmed.

[816]*816If the prohibition against retroactive ratemaking is to remain a useful principle of regulatory law and not become a device to fetter the commission in the exercise of its lawful discretion, the rule must be properly understood. In Pacific Tel. & Tel. Co. v. Public Util. Com. (1965) 62 Cal.2d 634 [44 Cal.Rptr. 1, 401 P.2d 353] (hereinafter Pacific Tel. & Tel.), the first decision of this court on the question,1 we construed Public Utilities Code section 728 to vest the commission with power to fix rates prospectively only.2 But we did not require that each and every act of the commission operate solely in futuro; our decision was limited to the act of promulgating “general rates.” Thus we held (at p. 650 of 62 Cal.2d) that “the Legislature has not undertaken to bestow on the commission the power to roll back general rates already approved by it under an order which has become final, or to order refunds of amounts collected by a public utility pursuant to such approved rates and prior to the effective date of a commission decision ordering a general rate reduction.” (Italics added.) And we concluded by reaffirming (at p. 655) “the rule that general rate making is legislative in character and looks to the future.” (Italics added.)

Pacific Tel. & Tel. was precisely such a general ratemaking case. There the commission conducted an extensive investigation of the rates charged by the utility in question, found them to be unreasonably high, and fixed new lower rates. In addition, however, the commission ordered the utility to refund to its customers all charges collected in excess of the new rate level since the beginning of the investigation. The order, of course, resulted in the new general rate structure taking effect retroactively, a disposition which we ruled beyond the statutory power of the commission.3

[817]*817The second decision of this court applying the rule against retroactive ratemaking was City of Los Angeles v. Public Utilities Commission (1972) 7 Cal.3d 331 [102 Cal.Rptr. 313, 497 P.2d 785] (hereinafter City of Los Angeles I). There the commission, after full hearings, found a utility’s rates to be unreasonably low and fixed new higher rates. We issued a stay permitting the increased rates to be collected subject to refund pending our ruling on the petition for writ of review. In due course we annulled the decision, while recognizing that some rate increase was justified. The utility requested that we remand the case to the commission for the fixing of new rates and that the refunds be limited to the difference between such rates and those prescribed in the annulled decision. Again such an order would evidently have had the effect of permitting a new general rate structure to operate retroactively. We therefore reiterated the rule of Pacific Tel. & Tel. that “general rate making is legislative and looks to the future” (7 Cal.3d at p. 338), and directed refund of the entire rate increase. (Id. at pp. 356-357.)

We question neither the rule stated in the foregoing decisions nor its application to the facts there presented. But this is not such a case. At the risk of belaboring the obvious, we observe that before there can be retroactive ratemaking there must at least be ratemaking. There undoubtedly was ratemaking in both Pacific Tel. & Tel. and City of Los Angeles I; as we shall explain, however, ratemaking within the meaning of the cited decisions did not occur in the case at bar.

We begin with a review of the factual and legal background of this dispute. In a general rate proceeding in 1971 the commission granted Edison a rate increase of $105.5 million so that it might realize a return of 7.9 percent in the test year 1972. (Re So. Cal. Edison Co. (1971) 72 Cal.P.U.C. 282, 317.) The commission’s estimate for Edison’s cost of fuel in 1972 was based on actual prices paid in the period preceding the decision.. In the months following the decision, however, Edison’s fossil fuel costs—together with those of all utilities—rose substantially. Edison thereupon filed an application for immediate rate relief and for authority to amend its tariff to include an adjustment clause permitting periodic future billing adjustments “to reflect future increases in the cost of fuel.” The commission granted an immediate rate increase of $14.3 million, and authorized the requested fuel clause. (Re So. Cal. Edison Co. (1972) 73 Cal.P.U.C. 180.)

[818]*818The clause operated as follows: at regular intervals Edison prepared a forecast of the quantity of fossil fuel it would need to purchase in the ensuing 12-month period under average weather conditions. It then calculated the cost of such fuel at current prices, and compared that figure with the cost of the same quantity of fuel at the prices reflected in its existing base rates. If the difference worked out to .001 cent per kilowatt-hour or more,4 Edison notified the commission of this fact by filing an “advice letter” requesting authority to increase future billings to compensate for its predicted higher fuel expenses.

Formal hearings on such requests were not contemplated; during the period here in issue none was held, and commission approval was routinely granted. In each instance the ensuing adjustment was then a matter of simple arithmetic: on each bill the number of kilowatt-hours sold was multiplied by the “fuel cost adjustment billing factor” necessary to raise the additional revenue, and the resulting “adjustment amount” was added to the customer’s monthly charge. The process was repeated in each billing until the next such adjustment was granted and took effect, and revisions of the billing factor were permitted as often as every three months. (Id. at pp. 184-185.)5

It is important to keep in mind that the periodic adjustments in Edison’s rates brought about by operation of the fuel clause were intended to contain no element of profit whatever. A utility’s rates are essentially the sum of two distinct components: its operating expenses and its return on invested capital. “The basic principle [of ratemaking] is to establish a rate which will permit the utility to recover its cost and expenses plus a reasonable return on the value of property devoted to public use.” (Italics added.) (City and County of San Francisco v. Public Utilities Com. (1971) 6 Cal.3d 119, 129 [98 Cal.Rptr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Securus Technologies v. Public Utilities Com.
California Court of Appeal, 2023
Ponderosa Telephone Co. v. Public Utilities Commission
197 Cal. App. 4th 48 (California Court of Appeal, 2011)
Gordon v. Council of City of New Orleans
9 So. 3d 63 (Supreme Court of Louisiana, 2009)
Centerpoint Energy Entex v. Railroad Commission
208 S.W.3d 608 (Court of Appeals of Texas, 2006)
Matanuska Electric Ass'n v. Chugach Electric Ass'n
53 P.3d 578 (Alaska Supreme Court, 2002)
Wise v. Pacific Gas & Electric Co.
77 Cal. App. 4th 287 (California Court of Appeal, 1999)
Entergy Gulf States v. LPSC
730 So. 2d 890 (Supreme Court of Louisiana, 1999)
Michael v. City of Minden
704 So. 2d 409 (Louisiana Court of Appeal, 1997)
Wisconsin Power & Light Co. v. Public Service Commission
511 N.W.2d 291 (Wisconsin Supreme Court, 1994)
Daily Advertiser v. TRANS-LA, ETC.
612 So. 2d 7 (Supreme Court of Louisiana, 1993)
South Cent. Bell v. PUBLIC SERVICE COM'N
594 So. 2d 357 (Supreme Court of Louisiana, 1992)
Toward Utility Rate Normalization v. Public Utilities Commission
750 P.2d 787 (California Supreme Court, 1988)
MGTC, Inc. v. Public Service Commission of Wyoming
735 P.2d 103 (Wyoming Supreme Court, 1987)
City & County of San Francisco v. Public Utilities Commission
703 P.2d 381 (California Supreme Court, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
576 P.2d 945, 20 Cal. 3d 813, 144 Cal. Rptr. 905, 24 P.U.R.4th 588, 1978 Cal. LEXIS 203, Counsel Stack Legal Research, https://law.counselstack.com/opinion/southern-california-edison-co-v-public-utilities-commission-cal-1978.