City & County of San Francisco v. Public Utilities Commission

703 P.2d 381, 39 Cal. 3d 523, 217 Cal. Rptr. 43, 1985 Cal. LEXIS 319
CourtCalifornia Supreme Court
DecidedAugust 15, 1985
DocketS.F. 24687
StatusPublished
Cited by21 cases

This text of 703 P.2d 381 (City & County of San Francisco v. Public Utilities Commission) is published on Counsel Stack Legal Research, covering California Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City & County of San Francisco v. Public Utilities Commission, 703 P.2d 381, 39 Cal. 3d 523, 217 Cal. Rptr. 43, 1985 Cal. LEXIS 319 (Cal. 1985).

Opinions

Opinion

MOSK, J.

The present petition for a writ to review Decision No. 83-10-035 of respondent California Public Utilities Commission (hereinafter [528]*528the commission) in essence raises a single issue: Did the commission regularly pursue its authority in estimating that real party in interest Pacific Bell, then known as Pacific Telephone and Telegraph Company (hereinafter Pacific), would incur $402.1 million in total company service connection costs—commonly known as installation costs—and consequently authorizing Pacific to raise its intrastate rates by $264 million to offset the effect of such costs on its intrastate operations? The commission and Pacific answer the question in the affirmative, petitioners City and County of San Francisco and City of San Diego (hereinafter the cities) in the negative. We conclude that the commission and Pacific are correct and that the decision must accordingly be affirmed.

In August 1980 Pacific filed an application for a general rate increase. The commission initially authorized a rate increase of $610 million in August 1981. The cities applied for a rehearing, arguing that the commission had not been consistent in its treatment of the anticipated effects of the increased use of PhoneCenter Stores by Pacific’s customers.1 Specifically, the cities contended that while the commission recognized Pacific would experience a reduction of $63.7 million in installation revenues in a 1981 test year as a result of increased use of PhoneCenter Stores, it failed to consider whether Pacific would experience a corresponding reduction in installation costs. The cities alleged that Pacific would indeed experience such a corresponding reduction and that it would be substantial—$70 million. Because installation costs were at that time capitalized, or included in the rate base, a $70 million reduction in such costs would require a reduction of $12.8 million in the annual rate increase initially authorized by the commission. The commission rejected the cities’ argument and denied their application in October 1981.

The cities then petitioned this court for a writ to review this issue. In March 1982 we granted the petition. Before oral argument, however, the parties settled the dispute: Pacific requested an order reducing its rate base by $70 million and its rate increase by $12.8 million; the commission issued such an order; and the cities and Pacific stipulated that the dispute had been mooted. We accordingly dismissed the petition for writ of review.

In the meantime the Federal Communications Commission (hereinafter the FCC) adopted a decision in November 1980 amending the Uniform System of Accounts for Class A and Class B Telephone Companies to pro[529]*529vide for the expensing of future installation costs and the amortization of embedded installation costs over a period of 10 years. Previously such costs had been treated as capital expenditures.2 In response to the FCC action, the commission initiated a proceeding in December 1980 on the revision of accounting and related ratemaking effects by its Order Instituting Investigation 84 (hereinafter Oil 84). In March 1981 the FCC released the accounting revision decision, to become effective October 1, 1981.

Along with other California telephone utilities, Pacific then initiated the present proceeding by filing an application for increased revenues to offset the increased costs associated with the accounting revision. During the period in which installation costs were capitalized, they were not directly considered in the cost of service in determining the utility’s revenue requirement, that is, the amount of revenue needed to cover its operating expenses and to provide it with a reasonable return on its investment. With the accounting revision, there was an immediate and automatic increase in operating expenses for accounting purposes and accordingly an immediate and automatic increase in revenue requirement to offset such an increase: installation costs would now immediately be recognized in full as a cost of service, instead of, as previously, being recognized over time as capital costs. Pacific’s application was combined with Oil 84 for hearing and decision.

In November 1981 the commission, in a decision in Oil 84, adopted the FCC proposal and ordered that all California telephone utilities expense their future installation costs and amortize their embedded installation costs over a period of 10 years.3 In the same decision the commission, estimating that Pacific would incur $402.1 million in total company installation costs in a 1981 test year, found that Pacific needed an additional $264 million in revenue to offset the effect of such costs on its intrastate operations, and accordingly authorized it to increase its intrastate rates by that amount. The cities applied for a rehearing, alleging that the appropriate level of rate increase for Pacific could be affected by the disposition of their then-pending [530]*530petition for writ of review in the general rate proceeding. In January 1982 the commission denied the cities’ application, but modified its decision to make Pacific’s rate increase subject to refund and to reserve jurisdiction to consider what effect if any the disposition of the general rate proceeding issue would have on the present proceeding.

After the 1982 settlement in the general rate proceeding, the commission turned to consider whether it should make any adjustment in the $264 million allowed to Pacific in the present proceeding. In October 1983 the commission issued Decision No. 83-10-035, which is the subject of the present petition. In that decision the commission concluded that the $264 million rate increase was supported by the record in this proceeding and that it was therefore not reasonable to reduce it automatically as a result of the settlement in the general rate proceeding: the 1981 test-year installation cost estimate presupposed in the general rate proceeding and the 1981 test-year installation cost estimate developed in the present proceeding were different and were based on materially different evidentiary records. Accordingly, the commission declined to reduce the additional rate increase allowed to Pacific. The cities now petition for a writ to review that decision.

The scope of our review of a commission decision is limited: “The review shall not be extended further than to determine whether the commission has regularly pursued its authority, including a determination of whether the order or decision under review violates any right of the petitioner under the Constitution of the United States or of this State.” (Pub. Util. Code, § 1757; accord Toward Utility Rate Normalization v. Public Utilities Com. (1978) 22 Cal.3d 529, 537 [149 Cal.Rptr. 692, 585 P.2d 491].) Moreover, the commission’s findings are ordinarily conclusive and not subject to review: “The findings and conclusions of the commission on questions of fact shall be final and shall not be subject to review except as provided in this article. Such questions of fact shall include ultimate facts and the findings and conclusions of the commission on reasonableness and discrimination.” (Pub. Util. Code, § 1757.) Further, if they are supported by any evidence, such findings may not be set aside. (See Yucaipa Water Co. No. 1 v. Public Utilities Com. (1960) 54 Cal.2d 823, 828 [9 Cal.Rptr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

City and County of S.F. v. Public Utilities Com.
California Court of Appeal, 2025
Bullseye Telecom, Inc. v. Cal. P.U.C.
California Court of Appeal, 2021
Ponderosa Telephone Co. v. CAPUC
California Court of Appeal, 2019
Ponderosa Tel. Co. v. Cal. Pub. Utilities Comm'n
249 Cal. Rptr. 3d 200 (California Court of Appeals, 5th District, 2019)
New Cingular Wireless PCS, LLC v. Public Utilities Commission
246 Cal. App. 4th 784 (California Court of Appeal, 2016)
Pacific Gas & Electric Co. v. Public Utilities Commission
237 Cal. App. 4th 812 (California Court of Appeal, 2015)
SFPP v. Public Util. Com.
California Court of Appeal, 2013
SFPP, L.P. v. Public Utilities Commission
217 Cal. App. 4th 784 (California Court of Appeal, 2013)
City of Huntington Beach v. Public Utilities Commission
214 Cal. App. 4th 566 (California Court of Appeal, 2013)
Mountain Fuel Supply Co. v. Public Service Commission
861 P.2d 414 (Utah Supreme Court, 1993)
Napa Valley Wine Train, Inc. v. Public Utilities Commission
787 P.2d 976 (California Supreme Court, 1990)
Southern California Gas Co. v. Public Utilities Commission
784 P.2d 1373 (California Supreme Court, 1990)
City & County of San Francisco v. Public Utilities Commission
703 P.2d 381 (California Supreme Court, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
703 P.2d 381, 39 Cal. 3d 523, 217 Cal. Rptr. 43, 1985 Cal. LEXIS 319, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-county-of-san-francisco-v-public-utilities-commission-cal-1985.