PDO Ahusaka Joint Venture LLC

Armed Services Board of Contract Appeals·Decided July 23, 2026·No. 64490·Published

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of - )

)

PDO Ahusaka Joint Venture LLC ) ASBCA No. 64490 )

Under Contract No. W56HZV-20-C-L865 )

APPEARANCE FOR THE APPELLANT: Mr. Robert M. Pastorelli Executive Program Manager

APPEARANCES FOR THE GOVERNMENT: Dana J. Chase, Esq.

Army Chief Trial Attorney MAJ Joseph C. Van Dusen, JA Trial Attorney

OPINION BY ADMINISTRATIVE JUDGE HERZFELD PURSUANT TO BOARD RULE 12.2

PDO Ahusaka Joint Venture LLC (PDO) seeks an equitable adjustment from the Department of the Army (Army) based on claimed differing site conditions. PDO elected to proceed under the Board’s Small Claims (Expedited) procedures, ASBCA Rule 12.2. The Contract Disputes Act, 41 U.S.C. §§ 7106(b)(4)-(5), as implemented by ASBCA Rule 12.2, provides that this decision shall have no precedential value, and in the absence of fraud shall be final and conclusive and may not be appealed or set aside. The parties requested that we proceed to the merits without hearing under ASBCA Rule 11 and decide both entitlement and quantum. The Board sustains PDO’s appeal, in part, and denies it, in part.

FINDINGS OF FACT

On September 25, 2020, the Army issued a solicitation to the Small Business Administration through the 8(a) Program, which awarded PDO a firm fixed-price contract to design and build a storm system upgrade and flood control project at the U.S. Army Garrison-Detroit Arsenal in Warren, Michigan (R4, tab 1 at 1, 3-8, 12, 31, 40; id. at 132-33 (incorporating Federal Acquisition Regulation (FAR) 52.219-17, SECTION 8(a) AWARD (OCT 2019)).

The contract required PDO to “obtain utility maps” from the Army and “field verify and mark actual location of utilities in the vicinity of proposed work,” notifying the Army of “any conflicts during early stages of design and prior to start of construction” (R4, tab 1 at 47, 57). The contract warned: “No guaranties are made by the Government to the exactness and/or accuracy of provided utility information” (id.

at 47). The contract stated that the Army “will provide courtesy utility identification of known existing underground utilities in the work area” and “may field locate utilities for the contractor” (id. at 56-57). The contract emphasized this underground utility information was “approximate” and a “courtesy” (id. at 56).

Consistent with the contract, the Army furnished PDO with as-built utility drawings depicting the known locations of buried utilities across the Detroit Arsenal (R4, tabs 21-33). The “utilities as shown are from record data,” but “[n]o guarantees are made to the exactness of size or location” of the utilities (R4, tabs 25-26). All the as-builts stated that they were “NOT FOR CONSTRUCTION – REFERENCE ONLY” (R4, tabs 21-33).

As to field verification of utilities, the contract first required PDO to secure an excavating permit before performing subsurface investigations, which PDO did (R4, tab 1 at 57, tabs 129-31, 136). Second, the contract required PDO to use MISS DIG to mark the underground utilities, which PDO did through one of its subcontractors (R4, tab 1 at 57, tab 137). Third, the contract required PDO to hire a subcontractor to locate “utilities within excavation, boring, tunneling area” and recommended several methods for field verification including “‘Underground Radar Penetration’ and exploratory trenches” (R4, tab 1 at 57). Indeed, the contract required PDO to use “ground penetrating radar to verify all underground utilities,” which PDO did (R4, tab 1 at 18, tabs 126-27). PDO used subcontractors to conduct and analyze soil boring results and geotechnical investigations (R4, tabs 124, 128, 134-35).

During performance, PDO’s subcontractor encountered three underground junction boxes where it was digging on June 3, 2022 (R4, tabs 15, 95, 100, 149). “A junction box is an air-tight, sealed container that is meant to provide additional protection where fiberoptic cables are spliced together” (R4, tab 146, tab 148 at 2). PDO’s subcontractor had been soft excavating this location and moved the three junction boxes to the side (R4, tab 15 at 2, tab 148 at 2). The Army’s drawings (which the contract required PDO to consult) did not identify the junction boxes at this location (R4, tab 15 at 3-5, tab 100 at 3-5, tab 149 at 2).

After several days of significant rain, the Detroit Arsenal fire department notified the contracting officer’s representative of emergency communications service disruptions (R4, tab 15 at 2, tab 147 at 5). The contracting officer’s representative notified the Network Enterprise Center, which determined that the junction boxes were the cause of the disruptions (R4, tab 147 at 5, tab 148 at 2). Notably, the Army’s contracting officer’s representative first learned of the junction boxes from the Detroit Arsenal fire department, not PDO or its subcontractor (R4, tab 147 at 5). More than two weeks passed before PDO informed the contracting officer’s representative regarding the three unidentified junction boxes (id.).

PDO, its subcontractor, and Army personnel met later that week at the site (on June 22, 2022) to discuss the issue and the Army directed PDO’s subcontractor to troubleshoot the problem including determining the level of damage to the cables inside the junction boxes (R4, tab 15 at 2-3). Despite the two-week delay in PDO providing notice, the Army still provided feedback and direction about how PDO should remedy this issue including opening the junction boxes (R4, tab 15 at 2-3, tab 142 at 1). The contracting officer’s representative took the position that “PDO caused the damage to the junction boxes by failing to exercise reasonable care after excavating the junction boxes” (R4, tab 147 at 5, tab 148 at 2-3). PDO objected, asserting that it was not responsible for troubleshooting because “these boxes were not shown on the drawings, and we had no information about their existence or location” (R4, tab 15 at 2, tab 151 at 5). Notwithstanding its objection, PDO excavated and backfilled the area, and repaired the underground fiber splicers that had been damaged (R4, tab 16 at 13).

In a different location (on June 23, 2022), PDO’s subcontractor also unearthed and damaged two communication conduits while machine excavating in preparation to install part of the storm system (R4, tab 14 at 2, tab 142 at 1, tab 147 at 4, tab 149 at 1). Conduits “are tubes that can be made from plastic, rubber, or metal and are meant to protect more sensitive fiberoptic cables running underground between buildings and telecommunications hubs” (R4, tab 148 at 2). The conduits at this location were not identified in the drawings the Army provided but the as-built drawings did identify water, electrical, and gas lines in this location (R4, tab 14 at 4-5, tab 99 at 4-5, tab 149 at 1). Unlike the junction boxes, the damage did not disrupt communications and the Army determined the encased fiberoptic cables were undamaged (R4, tab 14 at 2, tab 148 at 2). PDO repaired the conduits including backfilling the area and performing other work as part of the repairs (R4, tab 16 at 7).

Free access — add to your briefcase to read the full text and ask questions with AI

PDO Ahusaka Joint Venture LLC, (asbca 2026).

PDO Ahusaka Joint Venture LLC (PDO Ahusaka Joint Venture LLC) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Ace Constructors, Inc. v. United States
499 F.3d 1357 (Federal Circuit, 2007)
Metcalf Construction Company v. United States
742 F.3d 984 (Federal Circuit, 2014)
Meridian Engineering Company v. United States
885 F.3d 1351 (Federal Circuit, 2018)
George Sollitt Construction Co. v. United States
64 Fed. Cl. 229 (Federal Claims, 2005)
ACE Constructors, Inc. v. United States
70 Fed. Cl. 253 (Federal Claims, 2006)
Schnip Building Co. v. United States
645 F.2d 950 (Court of Claims, 1981)
Transportation v. Eagle Peak Rock & Paving, Inc.
69 F.4th 1367 (Federal Circuit, 2023)