PC Construction Co. v. City of Salisbury

871 F. Supp. 2d 475, 2012 WL 2552864, 2012 U.S. Dist. LEXIS 91700
District Court, D. Maryland·Decided June 29, 2012·No. Civil Case No. L-12-0062·Published·Cited by 36 cases

Opinion

MEMORANDUM

BENSON EVERETT LEGG, District Judge.

I. Introduction

This action arises under the Federal Arbitration Act (“FAA”), 9 U.S.C. § 1 et [477] seq. PC Construction Co. f/k/a Pizzagalli Construction Co. and Travelers Casualty and Surety Co. of America (collectively “Petitioners”) seek an order compelling the City of Salisbury, O’Brien & Gere Engineers, Inc., and Construction Dynamics Group, Inc. (collectively “Respondents”) to arbitrate all disputes among the parties pursuant to a written agreement containing an arbitration provision. Pet., Docket No. 1. The issues have been fully briefed; a hearing is unnecessary. See Local Rule 105.6 (D. Md. 2010). For the reasons stated herein, the Court hereby declines to enter an order compelling Respondents to submit to arbitration.

II. Background

This case stems from various claims filed by Respondents in a Wicomico County, Maryland lawsuit involving a Waste Water Treatment Plant (“Plant”) in Salisbury, Maryland that was principally designed, engineered, and constructed from 2002 through 2008. The Respondents are (i) the City of Salisbury (“the City”), which owns the Plant and entered into separate contracts with each of the parties in the case at bar to facilitate an upgrade and expansion project at the Plant, (ii) O’Brien & Gere Engineers, Inc. (“OBG”), the project engineer, and (iii) Construction Dynamics Group, Inc. (“CDG”), the project construction manager. Alleging that the Plant did not perform as intended due to design defects and post-completion performance issues, the City initially sued OBG in October 2009, adding CDG as a defendant shortly thereafter. On November 30, 2011, the City amended its complaint to include breach of contract and bond claims against Petitioners: (i) PC Construction Co. f/k/a Pizzagalli Construction Co. (“PCC”), the project contractor, and (ii) Travelers Casualty and Surety Co. of America (“Travelers”), which issued a performance bond for the project naming the City as obligee and PCC as bond principal. See Pet. Ex. D, Docket No. 1-4 (Compl., City of Salisbury v. O’Brien & Gere Engineers, Inc. et al., No. 22-C-11-313 (Wicomico Cnty. Cir. Ct.)).1 The City alleges that PCC and Travelers are responsible for performance problems at the Plant. Both OBG and CDG have filed third-party complaints in the state action naming PCC as a third-party defendant.

While simultaneously defending the suit in state court, PCC and Travelers have petitioned this Court for an order compelling arbitration of the dispute. The Petition is based on a June 2005 construction contract executed by the City and PCC (“the Contract”) in connection with the Plant expansion project. The Contract is expressly incorporated into the performance bond issued by Travelers. See Pet. Ex. C (Performance Bond). Although OBG and CDG are not signatories to the Contract, Petitioners argue that they are nevertheless subject to arbitration.

III. Standard of Review

“[Mjotions to compel arbitration exist in the netherworld between a motion to dismiss and a motion for summary judgment.” Shaffer v. ACS Gov’t Servs., Inc., 321 F.Supp.2d 682, 683-84 (D.Md.2004). Whether the motion should be treated as a motion to dismiss or a motion for summary judgment turns on whether the court must consider documents outside the pleadings. See id. (treating motion to compel arbitration as a motion for summary judgment because consideration of documents outside the pleadings was required). Because no documents outside the pleadings are [478] necessary to decide this case, it will be treated as a motion to dismiss.

To survive a motion to dismiss under Federal Rule of Civil Procedure 12(b)(6), a plaintiff must plead plausible, not merely conceivable, facts in support of his claim. See Bell Atl. Corp. v. Twombly, 550 U.S. 544, 570, 127 S.Ct. 1955, 167 L.Ed.2d 929 (2007). The complaint must state “more than labels and conclusions, and a formulaic recitation of the elements of a cause of action will not do.” Id. at 555, 127 S.Ct. 1955. The court must, however, assume the veracity of well-pleaded factual allegations “and then determine whether they plausibly give rise to an entitlement to relief.” Ashcroft v. Iqbal, 556 U.S. 662, 679, 129 S.Ct. 1937, 173 L.Ed.2d 868 (2009).

IV. Analysis

Under the FAA, “[a] party aggrieved by the alleged failure, neglect, or refusal of another to arbitrate under a written agreement for arbitration may petition ... for an order directing that such arbitration proceed in the manner provided for in such agreement.” 9 U.S.C. § 4. In the Fourth Circuit, a court must enter an arbitration order if the petitioner demonstrates:

(1) the existence of a dispute between the parties, (2) a written agreement that includes an arbitration provision which purports to cover the dispute, (3) the relationship of the transaction, which is evidenced by the agreement, to interstate or foreign commerce, and (4) the failure, neglect or refusal of the defendant to arbitrate the dispute.

Adkins v. Labor Ready, Inc., 303 F.3d 496, 500-01 (4th Cir.2002) (quoting Whiteside v. Teltech Corp., 940 F.2d 99, 102 (4th Cir.1991)). In determining whether arbitration is required, courts must be mindful that the FAA reflects “a liberal federal policy favoring arbitration agreements.” See, e.g., Moses H. Cone Mem’l Hosp. v. Mercury Constr. Corp., 460 U.S. 1, 24, 103 S.Ct. 927, 74 L.Ed.2d 765 (1983); Hightower v. GMRI, Inc., 272 F.3d 239, 242 (4th Cir.2001) (acknowledging “the clear federal directive in support of arbitration”). As the Supreme Court explained in Moses, “any doubts concerning the scope of the arbitral issues should be resolved in favor of arbitration.... ” 460 U.S. at 24-25, 103 S.Ct. 927. Although federal policy favors arbitration, however, “a court must first determine whether the parties actually agreed to arbitrate.” Shaffer, 321 F.Supp.2d at 685 (explaining that state-law principles apply to the issue of contract formation while federal substantive law applies to the issue of arbitrability).

Free access — add to your briefcase to read the full text and ask questions with AI

PC Construction Co. v. City of Salisbury, 871 F. Supp. 2d 475, 2012 WL 2552864, 2012 U.S. Dist. LEXIS 91700 (D. Md. 2012).

871 F. Supp. 2d 475 (PC Construction Co. v. City of Salisbury) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related