Northeast Knox Utility District v. Stanfort Construction Co.

206 S.W.3d 454, 2006 Tenn. App. LEXIS 322, 2006 WL 1328779
CourtCourt of Appeals of Tennessee
DecidedMay 16, 2006
DocketE2005-01284-COA-R3-CV
StatusPublished
Cited by25 cases

This text of 206 S.W.3d 454 (Northeast Knox Utility District v. Stanfort Construction Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Northeast Knox Utility District v. Stanfort Construction Co., 206 S.W.3d 454, 2006 Tenn. App. LEXIS 322, 2006 WL 1328779 (Tenn. Ct. App. 2006).

Opinions

OPINION

HERSCHEL PICKENS FRANKS, P.J.,

delivered the opinion of the court,

in which SHARON G. LEE, J., joined, and CHARLES D. SUSANO, JR., J., filed a separate dissenting opinion.

[457]*457The Trial Court granted defendants summary judgment on the grounds the statute of limitations had run on plaintiffs claims. On appeal, we vacate and remand.

In this action, defendants were granted summary judgment on the grounds that the statute of limitations had ran on plaintiffs cause of action.

BACKGROUND

On April 9,1999, Southern Constructors, Inc. (“Southern”) and Northeast Knox Utility District (“NEKUD”) entered into a contract for the construction of a raw water intake on the Holston River in Knox County, Tennessee (the “Project”). Richard Phillips, NEKUD’s general manager, signed the contract on the District’s behalf, and the contract documents designated Robert G. Campbell & Associates L.P. (“Campbell”) as the Project’s engineer. The contract documents included an engineering report prepared by S & ME, an engineering services firm, which had drilled three test bores at the proposed location of the Project. These test results indicated rock at 16.5 feet, 17 feet, and 16.2 feet.

On May 6,1999, Southern subcontracted the excavation portion of the Project to Stanfort Construction Co. (“Stanfort”). In June 1999, Stanfort’s excavation work exposed rock six feet higher than shown in the boring report. In the summer or early fall of 1999, Stanfort demanded extra compensation for excavating the additional rock, pursuant to Articles 4.2.5 and 4.2.6 of the Contract.1

Southern pursued the demand on Stan-fort’s behalf and Campbell sent a letter to Southern dated July 27, 1999 which states, “We understand that you reserve the right to file a claim for additional rock excavation, as provided by the contract documents.” Another letter sent by Phillips to Southern and dated October 7,1999 states, “Your claim for compensation for extra rock excavation is acknowledged and is being evaluated. No determination has been made as of this date. There is no contract requirement to resolve your claim, prior to the work being executed.”

Stanfort completed the excavation on November 17, 1999, and on January 13, 2000, Terry Fortner, Stanfort’s principal, wrote a letter to NEKUD’s general contractor, Southern, detailing the difficulties Stanfort experienced during the excavation project and listing over $83,000.00 in specific extra expenses incurred by Stanfort as a result of the incorrect borings and inaccurate bid documents. Stanfort completed all work related to the Project in the spring of 2000, and had not received any additional compensation. According to Terry Fortner, in November 2000 Stanfort first learned that NEKUD and Southern closed out the contract without granting Stanfort its claim for additional compensation.

On December 20, 2000, Stanfort filed a demand for arbitration against NEKUD [458]*458and Southern. Stanfort claimed that it had not been fully paid for its work on the Project, but on August 24, 2001, NEKUD filed a Complaint against Stanfort, Southern, and the AAA in the Chancery Court of Knox County, seeking an injunction barring Stanfort and the AAA from proceeding with arbitration with NEKUD as a party. Stanfort .filed a Counterclaim against NEKUD’s and a Cross-Complaint against Southern, requesting $128,803.00 in damages plus interest and attorney’s fees. Stanfort filed an Amended Answer and Counter-Claim, and deleted the Cross-Claim against Southern.

On April 8, 2003, Stanfort moved to file an Amended Counter-Complaint and to Add Parties, which Motion the Circuit Court granted on April 11, 2003. Campbell and Phillips were added as parties and Stanfort charged that Campbell and Phillips engaged in reckless or negligent misrepresentation and that all three counter-defendants engaged in fraudulent concealment.

NEKUD and Phillips filed a Motion for Summary Judgment on January 21, 2004, arguing that Stanfort could not succeed under its enumerated causes of action because NEKUD was immune under the GTLA and Stanfort could not satisfy the requirement of justifiable reliance. The Motion was granted as to NEKUD, but denied as to Phillips. Phillips then filed a Motion for Summary Judgment arguing that Stanfort filed suit after the expiration of the applicable statute of limitations, Tenn.Code Ann. § 28-3-105. Stanfort responded by arguing that Phillips did not plead the statute of limitations in his Answer as required by Tenn. R. Civ. P. 8.03, but Phillips then filed a Motion to add the defense of statute of limitations, which was granted by the Court, who then granted Phillips’ Motion for Summary Judgment.

On March 15, 2005, Campbell filed a motion seeking to add the statute of limitations, along with a Motion for Summary Judgment. The Trial Court allowed the Amendment to Campbell’s Answer, and granted Campbell’s Motion for Summary Judgment on the grounds the statute of limitations had run.

These issues are presented on appeal:

1. Whether Mr. Phillips and Campbell waived the defense of the statute of limitations when they failed to include it in their Answers.
2. Whether there was an issue of material fact as to when Stanfort’s cause of action against Mr. Phillips and Campbell accrued.
3. Whether Stanfort’s Second Amended Counter-Complaint relates back to the date of its original Counter-Complaint.

DISCUSSION OF THE ISSUES

“The standard of review of a summary judgment determination is de novo without any presumption of correctness accorded the trial court’s judgment.” Guy v. Mutual of Omaha Ins. Co., 79 S.W.3d 528, 534 (Tenn.2002). The appellate court’s “only task in deciding a motion for summary judgment is to determine whether ‘the pleadings, depositions, answers to interrogatories, and admissions on file, together with the affidavits, if any, show that there is no genuine issue as to any material fact and that the moving party is entitled to a judgment as a matter of law.’ ” Id. When making this determination, “[cjourts must view the evidence in the light most favorable to the nonmoving party and must also draw all reasonable inferences in the non-moving party’s favor.” Staples v. CBL & Associates, Inc., 15 S.W.3d 83, 89 (Tenn.2000).

[459]*459Stanfort initially argues that Phillips and Campbell waived the statute of limitations defense because they did not raise the issue until after extensive discovery had been completed. Stanfort urges that the Trial Court erred in granting the Amendment, since the issue to amend was not raised until Terry Fortner had given his discovery depositions, without advance notice of this defense.

The granting or denying of a motion to amend is within the sound discretion of the trial court. Merriman v. Smith, 599 S.W.2d 548, 559 (Tenn.Ct.App.1979). The factor of primary importance in reviewing exercise of discretion is the amendment’s potential prejudicial effect on the opposing party.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lemeh v. EDMONDSON
M.D. Tennessee, 2025
Colebrook v. Thompson
M.D. Tennessee, 2024
Colebrook v. HUFFMAN
M.D. Tennessee, 2024
Adams v. Delk, Inc.
M.D. Tennessee, 2021
Greene v. Mercedes-Benz, USA
E.D. Tennessee, 2020
Rachel L. Bell v. Michael Gardner
Court of Appeals of Tennessee, 2018
In Re Hailey S.
Court of Appeals of Tennessee, 2016
Samuel Humphreys v. Bank of America
557 F. App'x 416 (Sixth Circuit, 2014)
Rozbeh Zaire v. Amir Roshan-Far
Court of Appeals of Tennessee, 2012
Sally Jo Witty v. Christopher Cantrell
Court of Appeals of Tennessee, 2011
THURSTON HENSLEY v. CSX Transp., Inc.
310 S.W.3d 824 (Court of Appeals of Tennessee, 2009)
Wilson v. Harris
304 S.W.3d 824 (Court of Appeals of Tennessee, 2009)
First American Title Insurance v. Cumberland County Bank
633 F. Supp. 2d 566 (M.D. Tennessee, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
206 S.W.3d 454, 2006 Tenn. App. LEXIS 322, 2006 WL 1328779, Counsel Stack Legal Research, https://law.counselstack.com/opinion/northeast-knox-utility-district-v-stanfort-construction-co-tennctapp-2006.