Northeast Fence & Iron Works, Inc. v. Murphy Quigley Co.

933 A.2d 664, 2007 Pa. Super. 287, 2007 Pa. Super. LEXIS 3092
CourtSuperior Court of Pennsylvania
DecidedSeptember 18, 2007
StatusPublished
Cited by82 cases

This text of 933 A.2d 664 (Northeast Fence & Iron Works, Inc. v. Murphy Quigley Co.) is published on Counsel Stack Legal Research, covering Superior Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Northeast Fence & Iron Works, Inc. v. Murphy Quigley Co., 933 A.2d 664, 2007 Pa. Super. 287, 2007 Pa. Super. LEXIS 3092 (Pa. Ct. App. 2007).

Opinion

OPINION BY

BOWES, J.:

¶ 1 Murphy Quigley Co., Inc. appeals the grant of relief to Appellee, Northeast Fence & Iron Works, Inc., based on a claim of unjust enrichment. We affirm.

¶ 2 Appellee instituted this action on May 21, 2004, seeking recovery against Appellant based upon breach of contract, unjust enrichment, and violation of the Contractor and Subcontractor Payment Act, 73 P.S. § 501 et seq. The matter proceeded to a nonjury trial, where these facts were adduced. In 2003, Appellant was general contractor for a construction project at Bucks County Correctional Facility. The project consisted of modifications to perimeter security through installation of perimeter fencing, creation of seven fence-enclosed recreational yards for the inmates, demolition work, and the upgrading of some aspects of the security *666 system. The first two components of the project comprised a significant amount of the work associated with it. The contract was valued at $713,000. Eagle Fence was awarded the original contract for the fencing work. After completing approximately ten to fifteen percent of that work, Eagle Fence left the worksite, apparently due to nonpayment.

¶ 3 In November 2003, Appellant obtained estimates for both completion of the fencing and repair of some of Eagle Fence’s work, which was not in compliance with contract specifications between the prison and Appellant. Appellee was one of the companies contacted in that regard and was hired to complete the job. Conflicting testimony was presented, however, on the issue of whether a verbal contract for the work was reached between Appellant and Appellee.

¶ 4 There was no dispute regarding the pricing of the perimeter fencing; both parties acknowledged that they had agreed that that work would be completed for a fixed amount of $26,500. Raymond Long-streath, Appellee’s owner, testified that the fixed price for that work was acceptable because the perimeter fence was on a level piece of ground, some of the materials were in place, and he was able to ascertain exactly what was needed in order .to complete the job. However, the parties differed as to the agreed price for the installation of the fencing surrounding the recreational yards.

¶ 5 Dan O’Connell, project manager for Appellant, testified that the proposal for the seven recreation yards was $3,500 per day for two iron workers, two laborers, and two trucks with four to five days estimated work on each yard. Although believing this estimate to be excessive, Mr. O’Connell nevertheless accepted it, concluding that the maximum for each yard would be $17,500 and overall $122,500. Adding $26,500 for the perimeter fencing, Mr. O’Connell calculated that the subcontract with Appellee would not exceed $149,000 and testified specifically that he understood that the subcontract would be limited to that amount.

¶ 6 Mr. Longstreath, who considered the contract an emergency contract due to Eagle Fence’s abandonment of the work coupled with Appellant’s contractual timing obligations with the prison, contested Mr. O’Connell’s recollection of the agreement regarding fencing for the recreational yards. He stated that when he reviewed the site for the yards, it was in disarray and muddy, which created construction difficulties, and he was unable to determine the exact amount of work needed to complete that aspect of the project. He testified that he presented a per diem proposal of $3,500 with no maximum and that this bid was accepted by Appellant.

¶ 7 Based on the discrepancy over the contract price for the recreational yards, the trial court determined that there was no meeting of the minds on the overall contract cost and that Appellee could not recover on a breach of contract theory. It did find in favor of Appellee, and awarded $114,264.06 in damages based on the unjust enrichment cause of action. The following evidence was considered in the calculation of the damage award. Diane Charlton, bookkeeper for Appellee, testified that her outstanding invoices on the project indicated that Appellant owed Ap-pellee $134,428.30 when Appellee left the jobsite. She also testified that she was promised payment by Mr. O’Connell and Appellant’s owner and that in her conversations with those men, no issues about the quality of the work or the credentials of Appellee’s workers were raised. The trial court accepted this testimony as credible.

¶ 8 Appellant presented countervailing evidence on damages. Mr. O’Connell *667 maintained that some invoices were not paid because Appellee was using nonunion workers in violation of Appellant’s contract with the prison and that after Appellee left the jobsite, Appellant had to expend $26,220 to correct defective work and $52,014.22 to complete the job. The trial court did not credit this evidence, noting that Mr. O’Connell’s “testimony regarding the sums allegedly expended by Murphy Quigley to correct work and to complete the job were not accepted by the court and appeared to be created solely for litigation.” Trial Court Opinion, 5/12/06, at 8. The court calculated the value of Appel-lee’s unpaid work at $114,264.06, which represented $134,428.30, the amount owed on the invoices, less the fifteen percent that Eagle Fence had performed on the project.

¶ 9 On appeal, Appellant raises a number of contentions, some of which are related. 1 We will consolidate resolution of the connected legal questions presented. One of Appellant’s positions, repeated throughout its brief, see appellant’s brief at 20, 24, 26, is that Appellee did not plead a theory of quantum meruit. This contention is incorrect. Count one of the complaint was for breach of contract, and count two pertained to the Contractor and Subcontractor Payment Act, 73 P.S. § 501 et seq. Count three was titled “unjust enrichment,” and after incorporating the previous paragraphs, indicated that Appellant was “unjustly enriched at plaintiffs expense.” Complaint, 5/21/04, at ¶¶ 33-37. Unjust enrichment is a synonym for quantum meruit. See Mitchell v. Moore, 729 A.2d 1200, 1202 n. 2 (Pa.Super.1999) (“cause of action in quasi-contract for quantum meruit, a form of restitution, is made out where one person has been unjustly enriched at the expense of another”). We therefore reject this contention.

¶ 10 Appellant also avers that the court erroneously denied its motion in limine for “Unjust Enrichment.” Appellant’s brief at 14. Appellant posits that “Northeast Fence was unprepared to introduce any evidence of unjust enrichment; rather, Northeast Fence would only introduce evidence of a purported written agreement, which would preclude any recovery under the theory of unjust enrichment.” Id. (citations to record omitted). In making this argument, Appellant misperceives the nature and purpose of a motion in limine. A motion in limine is a “device for obtaining rulings on the admissibility of evidence prior to trial.” Packel and Poulin, Pennsylvania Evidence, § 103.3 at 12; see Commonwealth v. Gordon, 543 Pa. 513, 517, 673 A.2d 866, 868 (1996) (motion in limine

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Com. v. Cronin, D.
Superior Court of Pennsylvania, 2025
Knight, T. v. Nesler, B.
Superior Court of Pennsylvania, 2025
Doe v. Post Acute Medical, LLC
M.D. Pennsylvania, 2025
Constantine, K. v. Lenox Instr. Co.
2024 Pa. Super. 216 (Superior Court of Pennsylvania, 2024)
Com. v. Holewski, R.
Superior Court of Pennsylvania, 2024
Bennett Williams Reality Inc. v. Four Brothers LLC
Superior Court of Pennsylvania, 2023
Waverly Custom Homes v. Smith, M.
Superior Court of Pennsylvania, 2023
Dugan, J. v. Gallo, D.
Superior Court of Pennsylvania, 2023
Rubin, B. v. Stewart, P.
Superior Court of Pennsylvania, 2023
COTE v. SCHNELL INDUSTRIES
M.D. Pennsylvania, 2022
SOLEM v. HORSESHOE TRAIL FARM, LLC
E.D. Pennsylvania, 2022
Artisan Builders, Inc. v. Jang, S.
2022 Pa. Super. 36 (Superior Court of Pennsylvania, 2022)
Moore v. Granlund
M.D. Pennsylvania, 2021

Cite This Page — Counsel Stack

Bluebook (online)
933 A.2d 664, 2007 Pa. Super. 287, 2007 Pa. Super. LEXIS 3092, Counsel Stack Legal Research, https://law.counselstack.com/opinion/northeast-fence-iron-works-inc-v-murphy-quigley-co-pasuperct-2007.