Meccon, Inc. v. University of Akron

2010 Ohio 3297, 126 Ohio St. 3d 231
CourtOhio Supreme Court
DecidedJuly 21, 2010
Docket2009-0950
StatusPublished
Cited by13 cases

This text of 2010 Ohio 3297 (Meccon, Inc. v. University of Akron) is published on Counsel Stack Legal Research, covering Ohio Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Meccon, Inc. v. University of Akron, 2010 Ohio 3297, 126 Ohio St. 3d 231 (Ohio 2010).

Opinion

Cupp, J.

{¶ 1} The question before us is whether bid-preparation costs may be recovered as damages by a bidder who establishes that its bid on a public-improvement project was wrongfully rejected because the public authority awarding that contract failed to comply with state competitive-bidding laws. We conclude that reasonable bid-preparation costs may be recovered if the rejected bidder promptly sought but was denied a timely injunction to suspend the public-improvement project pending resolution of the dispute and a court later determines that the bidder was wrongfully rejected by the public authority but injunctive relief is no longer available because the project has already been started or is completed under a contract awarded to another bidder. Therefore, we affirm the judgment of the court of appeals and remand the matter for further proceedings before the Court of Claims.

{¶ 2} According to the complaint of Meccon, Inc., and Roñal Bassak, appellees (“Meccon”), the University of Akron proposed to award plumbing, fire-protection, and heating, ventilation, and air-conditioning (“HVAC”) contracts for public-improvement work in its football stadium. Meccon submitted a bid for the *232 separate HVAC project, as did other contractors. Another contractor, S.A. Comunale, submitted four bids: one for each of the stand-alone fire-protection, plumbing, and HVAC contracts and a combined bid to perform all three contracts.

{¶ 3} When the bids were opened, S.A. Comunale’s combined bid was the lowest of the combination bids submitted. S.A. Comunale’s bid was $1.2 million less than the next-lowest combination of bids. S.A. Comunale was also the low bidder for each of the stand-alone fire-protection, plumbing, and HVAC contracts. Meccon submitted the second-lowest bid for the HVAC work.

{¶ 4} Thereafter, S.A. Comunale withdrew its combined bid and its stand-alone plumbing bid. The university awarded the stand-alone fire-protection and HVAC contracts to S.A. Comunale. After the university rebid the stand-alone plumbing contract and S.A. Comunale was once again the low bidder, S.A. Comunale also won that contract.

{¶ 5} Meccon alleges that the university’s award to S.A. Comunale of the three stand-alone contracts, after S.A. Comunale had withdrawn both its combined bid and its plumbing bid, was in violation of the university’s own “Instructions to Bidders” documents and comparable provisions within Ohio statutes. Meccon filed suit in the Court of Claims, seeking a temporary restraining order, a declaratory judgment, preliminary and permanent injunctive relief, damages for its bid-preparation costs, and any other appropriate legal and equitable relief resulting from the university’s failure to award the HVAC contract to Meccon.

{¶ 6} In response, the university filed a motion to dismiss for lack of subject-matter jurisdiction. It argued that disappointed bidders were entitled only to injunctive relief and that Meccon’s claim for bid-preparation costs and other money damages was not cognizable. The Court of Claims granted the university’s motion, concluding that only the court of common pleas had jurisdiction because Meccon’s remaining claim was only for equitable relief. On the same basis, the Court of Claims also denied the motion for a temporary restraining order, denied all other motions as moot, and dismissed the complaint.

{¶ 7} Meccon appealed to the Tenth District Court of Appeals, and the court reversed the Court of Claims with respect to the jurisdiction question. 182 Ohio App.3d 85, 2009-Ohio-1700, 911 N.E.2d 933. The court concluded that disappointed bidders can recover bid-preparation costs and that because such costs are monetary damages, the Court of Claims does have subject-matter jurisdiction to hear all of Meccon’s claims. Id. at ¶26. The court also determined that Meccon’s argument that the Court of Claims erred when it failed to consider Meccon’s motion for a temporary restraining order was moot. Id. at ¶ 27, 29. *233 We accepted the university’s appeal under our discretionary jurisdiction. 122 Ohio St.3d 1502, 2009-Ohio-4233, 912 N.E.2d 107. 1

{¶ 8} The university contends that Cementech, Inc. v. Fairlawn, 109 Ohio St.3d 475, 2006-Ohio-2991, 849 N.E.2d 24, controls the disposition of this case. In Cementeeh, a public authority solicited bids for a public project. In the process of awarding the contract, the public authority unlawfully rejected Cementech’s bid. The trial court awarded Cementeeh bid-preparation costs but denied lost profits. Cementeeh appealed the trial court’s order limiting damages to the bid-preparation costs. The appellate court reversed and allowed the lost profits.

{¶ 9} In reversing the appellate court, this court held: “When a municipality violates competitive-bidding laws in awarding a competitively bid project, the rejected bidder cannot recover its lost profits as damages.” Id. at paragraph one of the syllabus. The holding was founded on the principle that “punishing government entities through lost-profit damages to rejected bidders in effect punishes the very persons competitive bidding is intended to protect — the taxpayers.” Id. at ¶ 12. We also explained that the purposes of competitive bidding, which are to prevent excessive costs and corrupt practices and to provide open and honest competition in bidding for public-improvement contracts, clearly militate against allowing lost-profit damages to wrongfully rejected bidders. Id. at ¶ 9. Allowing such damages harms taxpayers by forcing the taxpayers to bear extra costs, which include both the unjustifiably higher prices paid to the wrongfully chosen bidder for the public contract and, if awarded, the damages established by the disappointed bidder that did not perform the work, including lost profits, which are often speculative and significant. Id. In that setting, we concluded that injunctive relief and the resulting delays in commencing the project serve as a sufficient deterrent to a public authority’s violation of competitive-bidding laws. Id. at ¶ 11.

{¶ 10} According to the university, Cementeeh holds that bid-preparation costs and other money damages cannot be recovered by a rejected bidder for a public project and that injunctive relief is the only available remedy. The university further asserts that since the remaining relief requested in Meccon’s action is equitable, the Court of Claims has no jurisdiction over that claim and the Court of Claims properly granted the university’s motion to dismiss. Correspondingly, the university argued before the appellate court that Meccon’s appeal to that court was also moot because injunctive relief requested by Meccon had been denied earlier in the proceedings.

*234 {¶ 11} The issue of whether bid-preparation costs could be recovered by a wrongfully rejected bidder was not answered in Cementech. 2 Upon consideration of the arguments in this case on the availability of reasonable bid-preparation costs as damages, we decline to extend the holding in Cementech

Free access — add to your briefcase to read the full text and ask questions with AI

Related

ParkPlay Solutions, L.L.C. v. Avon Lake
2023 Ohio 3103 (Ohio Court of Appeals, 2023)
Sparks v. Ohio Dept. of Rehab. & Corr.
2023 Ohio 3164 (Ohio Court of Claims, 2023)
Delasoft, Inc. v. Ohio Dept. of Adm. Servs.
2022 Ohio 3403 (Ohio Court of Appeals, 2022)
Speed Way Transp., L.L.C. v. Gahanna
2021 Ohio 4455 (Ohio Court of Appeals, 2021)
Colosseo USA, Inc. v. Univ. of Cincinnati
2019 Ohio 2026 (Ohio Court of Appeals, 2019)
Swan Super Cleaners, Inc. v. Franklin Cnty. Bd. of Comm'rs
2017 Ohio 8978 (Ohio Court of Appeals, 2017)
Univ. of Akron v. Jones
2013 Ohio 4999 (Ohio Court of Appeals, 2013)
Meccon, Inc. v. Univ. of Akron
2012 Ohio 6334 (Ohio Court of Claims, 2012)
Suburban Maintenance & Constr., Inc. v. Dept. of Transp.
2012 Ohio 3993 (Ohio Court of Claims, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
2010 Ohio 3297, 126 Ohio St. 3d 231, Counsel Stack Legal Research, https://law.counselstack.com/opinion/meccon-inc-v-university-of-akron-ohio-2010.