Meccon, Inc. v. Univ. of Akron

2012 Ohio 6317
CourtOhio Court of Claims
DecidedJuly 9, 2012
Docket2008-08817
StatusPublished

This text of 2012 Ohio 6317 (Meccon, Inc. v. Univ. of Akron) is published on Counsel Stack Legal Research, covering Ohio Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Meccon, Inc. v. Univ. of Akron, 2012 Ohio 6317 (Ohio Super. Ct. 2012).

Opinion

[Cite as Meccon, Inc. v. Univ. of Akron, 2012-Ohio-6317.]

Court of Claims of Ohio The Ohio Judicial Center 65 South Front Street, Third Floor Columbus, OH 43215 614.387.9800 or 1.800.824.8263 www.cco.state.oh.us

MECCON, INC., et al.

Plaintiffs

v.

THE UNIVERSITY OF AKRON

Defendant

Case No. 2008-08817

Judge Alan C. Travis Magistrate Lewis F. Pettigrew

DECISION OF THE MAGISTRATE

{¶ 1} On August 6, 2008, plaintiffs, Meccon, Inc., and Ronald Bassak (Meccon), filed a verified complaint and a motion for a temporary restraining order. In the complaint, plaintiffs allege that defendant, The University of Akron (Akron), wrongfully awarded a contract for a public improvement project in violation the competitive bidding processes prescribed by the Ohio Revised Code. The court granted Akron’s motion to dismiss on jurisdictional grounds, and the appeal of that decision ultimately reached the Supreme Court of Ohio in Meccon, Inc. v. Univ. of Akron, 126 Ohio St.3d 231, 2010- Ohio-3297. {¶ 2} Many of the relevant facts and much of the procedural history of this case is set forth in the opinion of the Supreme Court of Ohio in Meccon, supra, as follows: {¶ 3} “According to the complaint of Meccon, Inc., and Ronald Bassak, appellees (‘Meccon’), the University of Akron proposed to award plumbing, fire-protection, and heating, ventilation, and air-conditioning (‘HVAC’) contracts for public-improvement work in its football stadium. Meccon submitted a bid for the separate HVAC project, as did other contractors. Another contractor, S.A. Comunale, submitted four bids: one for each Case No. 2008-08817 -2- DECISION

of the stand-alone fire-protection, plumbing, and HVAC contracts and a combined bid to perform all three contracts. {¶ 4} “When the bids were opened, S.A. Comunale’s combined bid was the lowest of the combination bids submitted. S.A. Comunale’s bid was $1.2 million less than the next-lowest combination of bids. S.A. Comunale was also the low bidder for each of the stand-alone fire-protection, plumbing, and HVAC contracts. Meccon submitted the second-lowest bid for the HVAC work. {¶ 5} “Thereafter, S.A. Comunale withdrew its combined bid and its stand-alone plumbing bid. The university awarded the stand-alone fire-protection and HVAC contracts to S.A. Comunale. After the university rebid the stand-alone plumbing contract and S.A. Comunale was once again the low bidder, S.A. Comunale also won that contract. {¶ 6} “Meccon alleges that the university’s award to S.A. Comunale of the three stand-alone contracts, after S.A. Comunale had withdrawn both its combined bid and its plumbing bid, was in violation of the university’s own ‘Instructions to Bidders’ documents and comparable provisions within Ohio statutes. Meccon filed suit in the Court of Claims, seeking a temporary restraining order, a declaratory judgment, preliminary and permanent injunctive relief, damages for its bid-preparation costs, and any other appropriate legal and equitable relief resulting from the university’s failure to award the HVAC contract to Meccon. {¶ 7} “In response, the university filed a motion to dismiss for lack of subject- matter jurisdiction. It argued that disappointed bidders were entitled only to injunctive relief and that Meccon’s claim for bid-preparation costs and other money damages was not cognizable. The Court of Claims granted the university’s motion, concluding that only the court of common pleas had jurisdiction because Meccon’s remaining claim was only for equitable relief. On the same basis, the Court of Claims also denied the motion Case No. 2008-08817 -3- DECISION

for a temporary restraining order, denied all other motions as moot, and dismissed the complaint. {¶ 8} “Meccon appealed to the Tenth District Court of Appeals, and the court reversed the Court of Claims with respect to the jurisdiction question. 182 Ohio App.3d 85, 2009-Ohio-1700, 911 N.E.2d 933. The court concluded that disappointed bidders can recover bid-preparation costs and that because such costs are monetary damages, the Court of Claims does have subject-matter jurisdiction to hear all of Meccon’s claims. Id. at ¶ 26. The court also determined that Meccon’s argument that the Court of Claims erred when it failed to consider Meccon’s motion for a temporary restraining order was moot. Id. at ¶ 27, 29. We accepted the university’s appeal under our discretionary jurisdiction. 122 Ohio St.3d 1502, 2009-Ohio-4233, 912 N.E.2d 107.” Id. at ¶ 2-7. {¶ 9} The Supreme Court of Ohio held that when a rejected bidder establishes that a public authority violated state competitive-bidding laws in awarding a public- improvement contract, that bidder may recover reasonable bid-preparation costs as damages if that bidder promptly sought, but was denied, injunctive relief and it is later determined that the bidder was wrongfully rejected and injunctive relief is no longer available. Meccon, supra. The case was then remanded to this court for further proceedings. Upon remand, the first question for this court was whether the contract was awarded illegally.1 The parties filed cross motions for summary judgment on the issue and on April 12, 2011, this court granted partial summary judgment in favor of Meccon. The court’s decision reads, in part, as follows: {¶ 10} “R.C. 9.31, titled, ‘[w]ithdrawing bids made in error’ provides in relevant part: ‘A bidder for a contract with the state * * * may withdraw this bid from consideration if the price bid was substantially lower than the other bids, providing the bid was submitted in good faith, and the reason for the price bid being substantially

1 Akron’s March 19, 2012 motion to dismiss is DENIED. Case No. 2008-08817 -4- DECISION

lower was a clerical mistake as opposed to a judgment mistake, and was actually due to an unintentional and substantial arithmetic error * * *. {¶ 11} “‘No bid may be withdrawn under this section when the result would be the awarding of the contract on another bid of the same bidder.’ {¶ 12} “Although the operative language of the statute is susceptible to alternative interpretations, there is no reasonable interpretation that would permit the awarding of the contract to S.A. Comunale based upon the undisputed facts in this case. A strict interpretation of the statute would mean that any bidder who withdraws a bid cannot be considered for a contract for any portion of the work on the project. A more liberal construction would mean that any bidder who withdraws a bid cannot be considered for a contract involving any portions of the work that were also included in the withdrawn bid. “Here, under either a strict interpretation of the statute or a more liberal interpretation, the award of the contract to S.A. Comunale runs afoul of the statutory proscription. Indeed, the only reason defendant considered the individual bids for HVAC and plumbing and ultimately awarded S.A. Comunale a contract for both was because S.A. Comunale had been permitted to withdraw its combination bid. {¶ 13} “Based upon the foregoing, plaintiffs’ motion for summary judgment shall be granted, in part, as there is no question that defendant violated R.C. 9.31.”2 See April 12, 2011 Decision. {¶ 14} Thereafter, on February 6, 2012, the case was tried to a magistrate of the 3 court. The issue for the court at this juncture is whether Meccon had “promptly” sought injunctive relief and, if so, whether Meccon’s bid was wrongfully rejected.

2 Akron’s motion for summary judgment was granted, in part, as it pertained to the claim asserted by Reliance. Reliance claimed to be the next-lowest bidder for the plumbing contract, but it had never sought injunctive relief.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Meccon, Inc. v. University of Akron
2010 Ohio 3297 (Ohio Supreme Court, 2010)
State ex rel. Gaylor, Inc. v. Goodenow
2010 Ohio 1844 (Ohio Supreme Court, 2010)
Meccon, Inc. v. University of Akron
911 N.E.2d 933 (Ohio Court of Appeals, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
2012 Ohio 6317, Counsel Stack Legal Research, https://law.counselstack.com/opinion/meccon-inc-v-univ-of-akron-ohioctcl-2012.