Meccon, Inc. v. Univ. of Akron
Opinion
Court of Claims of Ohio
The Ohio Judicial Center
65 South Front Street, Third Floor Columbus, OH 43215
614.387.9800 or 1.800.824.8263 www.cco.state.oh.us
MECCON, INC., et al.
Plaintiffs
v.
THE UNIVERSITY OF AKRON
Defendant
Case No. 2008-08817
Judge Alan C. Travis Magistrate Lewis F. Pettigrew
JUDGMENT ENTRY
{¶ 1} Plaintiffs, Meccon, Inc. and Ronald Bassak (Meccon), brought this action against defendant, The University of Akron (Akron), alleging that Akron wrongfully awarded a public improvement contract in violation of the competitive bidding processes prescribed by the Ohio Revised Code.
{¶ 2} The case was remanded to this court in Meccon v. Univ. of Akron, 126 Ohio St.3d 231, 2010-Ohio-3297. Upon remand, the case was tried to a magistrate of the court. On July 9, 2012, the magistrate issued a decision recommending judgment in favor of defendant. On the same date, pursuant to Civ.R. 53(D)(4)(e)(i), the court adopted the magistrate’s recommendation and entered judgment for defendant.
{¶ 3} Civ.R. 53(D)(3)(b)(i) states, in part: “A party may file written objections to a magistrate’s decision within fourteen days of the filing of the decision, whether or not the court has adopted the decision during that fourteen-day period as permitted by Civ.R. 53(D)(4)(e)(i). If any party timely files objections, any other party may also file objections not later than ten days after the first objections are filed.” On July 23, 2012, plaintiffs filed their objections to the decision of the magistrate adopted by the court.
Portions of the trial transcript were previously filed with the court on March 26, 2012. On August 9, 2012, with leave of court, defendant filed its response.
{¶ 4} The procedural history of this case was set forth in the magistrate’s decision. In summary, on August 6, 2008, Meccon filed both a verified complaint and a motion for a temporary restraining order. After a hearing on Meccon’s motion, this court granted Akron’s motion to dismiss for lack of subject matter jurisdiction and Meccon’s appeal eventually reached the Supreme Court of Ohio. See id.
{¶ 5} In its decision, the Supreme Court of Ohio stated:
{¶ 6} “We conclude that reasonable bid-preparation costs may be recovered if the rejected bidder promptly sought but was denied a timely injunction to suspend the public-improvement project pending resolution of the dispute and a court later determines that the bidder was wrongfully rejected by the public authority but injunctive relief is no longer available because the project has already been started or is completed under a contract awarded to another bidder.
{¶ 7} “* * *
{¶ 8} “Injunctive relief must be promptly sought as a precondition to those damages, however. The university contends that Meccon waited two full months after the bids were opened to seek injunctive relief. Meccon states that it requested injunctive relief four business days after it learned that the university had awarded the plumbing, fire-protection, and HVAC contracts in violation of the state’s competitive- bidding laws. Whether Meccon was timely in its pursuit of injunctive relief satisfying this precondition for an award of its bid-preparation costs as damages is a matter that has
Case No. 2008-08817 -3- ENTRY
not yet been addressed by any court. Consequently, a remand to the Court of Claims to consider this matter is required.” Id. at ¶ 1, 20.1
{¶ 9} The magistrate found that Meccon knew on or before June 13, 2008, both that Akron intended to award the HVAC contract to S.A. Comunale in violation of R.C. 9.31 and that Meccon was the next lowest bidder for the HVAC contract. Accordingly, the magistrate found that Meccon’s right to seek injunctive relief arose on June 13, 2008, at the latest. Because Meccon did not file its claim for injunctive relief until August 6, 2008, the magistrate determined that Meccon did not “promptly seek” injunctive relief.
{¶ 10} In its objections, Meccon asserts that the factual findings made by the magistrate “are absurd” and that the decision “makes a mockery of the judicial system.” With due respect to counsel, the court must disagree with that characterization.
{¶ 11} Meccon’s objections appear to be based upon its belief that it had no duty to seek injunctive relief until Akron gave it “official notification of its decision to illegally award the contract to S.A. Comunale.” (Meccon’s Objections, p. 3.) Because Meccon filed suit four business days after it received Akron’s July 26, 2008 letter, Meccon reasons that it fulfilled its obligation to promptly seek injunctive relief.
{¶ 12} In Meccon, supra, the Supreme Court of Ohio drew from the “wellestablished principle of mitigation of damages” in holding that a wrongfully rejected bidder must first seek injunctive relief before recovering bid preparation costs. Id. at ¶ 14. “For if injunctive relief is timely granted, then a wrongfully rejected bidder will have avoided the damages that would otherwise flow from the public authority’s wrongful conduct by preventing the improper awarding of the contract or suspending the contract before it has been performed to such an extent that the bid award is no longer subject to
1
In the court’s April 12, 2011 decision, plaintiffs’ motion for summary judgment was granted, in part, and the court found that defendant violated R.C. 9.31 by awarding the HVAC contract to S.A. Comunale.
timely correction.” Id. Further, the wrongfully rejected bidder must pursue injunctive relief in a “timely and good-faith manner” in order to be able to recover bid preparation costs. Id. at ¶ 15.
{¶ 13} Injunctive relief serves an important function. “It is clear that in the context of competitive bidding for public contracts, injunctive relief provides a remedy that prevents excessive costs and corrupt practices, as well as protects the integrity of the bidding process, the public, and the bidders. Moreover, the injunctive process and the resulting delays serve as a sufficient deterrent to a municipality’s violation of competitive-bidding laws.” Cementech, Inc. v. City of Fairlawn, 109 Ohio St.3d 475, 2006-Ohio-2991, ¶ 11. However, a party seeking the extraordinary remedy of injunction must act promptly. “In a construction-related case, if an unsuccessful bidder seeking to enjoin the construction of a public-works project fails to obtain a stay of the construction pending judicial resolution of its claims challenging the decision, and construction commences, the unsuccessful bidder’s action will be dismissed as moot.” State ex rel. Gaylor, Inc. v. Goodenow, 125 Ohio St.3d 407, 2010-Ohio-1844, ¶ 11, citing TP Mechanical Contrs. v. Franklin Cty. Bd. of Commrs., 10th Dist. No. 08AP-108, 2008- Ohio-6824, ¶ 20.
{¶ 14} The necessary corollary to timely injunctive relief is that the aggrieved party act promptly in seeking that relief. Hence, it is the obligation of a wrongfully rejected bidder who knows that a public authority violated state competitive-bidding laws in awarding a public-improvement contract to act “promptly” and seek injunctive relief. Meccon, supra. If the rejected bidder fails to act promptly and the successful bidder commences to work on the project, injunctive relief is not available. See State ex rel. Gaylor, supra.
{¶ 15} At trial, Ronald Bassak, president of Meccon, Inc., agreed that shortly after the June 3, 2008 opening of the bids, he knew S.A. Comunale could not perform the plumbing contract as bid. (Excerpt of testimony of Ronald Bassak, Transcript, p. 46-
Free access — add to your briefcase to read the full text and ask questions with AI
2012 Ohio 6334 (Meccon, Inc. v. Univ. of Akron) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.