Meccon, Inc. v. University of Akron

911 N.E.2d 933, 182 Ohio App. 3d 85, 2009 Ohio 1700
CourtOhio Court of Appeals
DecidedApril 9, 2009
DocketNo. 08AP-727.
StatusPublished
Cited by7 cases

This text of 911 N.E.2d 933 (Meccon, Inc. v. University of Akron) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Meccon, Inc. v. University of Akron, 911 N.E.2d 933, 182 Ohio App. 3d 85, 2009 Ohio 1700 (Ohio Ct. App. 2009).

Opinion

Tyack, Judge.

{¶ 1} This is an appeal from the Ohio Court of Claims. At issue is whether the Court of Claims has subject-matter jurisdiction over a competitive-bidding dispute between plaintiffs-appellants, Meecon, Inc., and Ronald R. Bassak (“Meecon”), and defendant-appellee, University of Akron.

{¶ 2} In April 2008, the University of Akron invited bids for the University of Akron’s Football Stadium Project. Ohio’s public-bidding laws require that contracts be awarded to the lowest responsive and responsible bidder. R.C. 153.08, 9.312. Meecon submitted a bid for the heating, ventilation, and air conditioning (“HVAC”) contract. Another contractor, S.A. Comunale, submitted four bids for the project: three separate bids for the stand-alone prime-plumbing, fire-protection, and HVAC contracts, and a fourth combined bid for a package of the individual contracts.

{¶ 3} When the bids were opened, S.A. Comunale was the low bidder for each of the stand-alone plumbing, fire-protection, and HVAC contracts. Meccon’s bid for the stand-alone HVAC package was the second lowest bid. Additionally, S.A. Comunale’s combined bid was more than $1.2 million lower than the next lowest bid.

{¶ 4} After it discovered the large disparity in its low bids from the next lowest bidders, S.A. Comunale withdrew its combined bid and withdrew its stand-alone plumbing bid. Despite language in the bid documents themselves and statutory language that prohibits withdrawal of a bid “when the result would be the awarding of the contract on another bid of the same bidder,” the University of Akron awarded the stand-alone HVAC and fire-protection contracts to S.A. Comunale. R.C. 9.31.

{¶ 5} On August 6, 2008, Meecon filed suit in the Court of Claims, seeking a temporary restraining order, a declaratory judgment, preliminary and permanent injunctive relief, damages for its bid-preparation costs, and other such damages and relief resulting from the University of Akron’s failure to award the HVAC contract to Meecon.

*87 {¶ 6} Before the court could hold an evidentiary hearing on the temporary restraining order (“TRO”), the University of Akron filed a motion to dismiss for lack of subject-matter jurisdiction. The university argued that an Ohio Supreme Court case limited disappointed bidders to injunctive relief only. The Court of Claims granted the motion, finding that Meccon’s claim for bid-preparation costs and other money damages was not cognizable due to the decision in Cementech, Inc. v. Fairlawn, 109 Ohio St.3d 475, 2006-Ohio-2991, 849 N.E.2d 24. Without a legally cognizable claim for money damages, the complaint was for equitable relief only. Therefore, the Court of Claims decided that it lacked subject-matter jurisdiction. The Court of Claims then denied the motion for a TRO, dismissed the claim, and denied all remaining motions as moot. This appeal followed, with Meccon assigning as error the following:

1. The Trial Court erred when it dismissed Appellants’ case for lack of Subjeck-Matter Jurisdiction.
2. The Trial Court erred when it failed to rule on Appellants’ Motion for Temporary Restraining Order.

{¶ 7} We review an appeal of a dismissal for lack of subject-matter jurisdiction under a de novo standard of review. Reynoldsburg City School Dist. Bd. of Edn. v. Licking Hts. Local School Dist., 10th Dist. No. 08AP-415, 2008-Ohio-5969, 2008 WL 4927406. The question we must decide is whether any cause of action cognizable by the forum has been raised in the complaint. Id. Here, the issue turns on whether Meccon’s complaint states a legally cognizable claim for money damages, for without a claim for money damages, the Court of Claims lacks subject-matter jurisdiction.

{¶ 8} It is undisputed that Meccon’s complaint requests bid-preparation costs and any additional costs and damages incurred due to the failure of the University of Akron to award the HVAC contract to Meccon. This court has concluded that if an action in the Court of Claims is one for money damages against the state coupled with a request for declaratory and injunctive relief, the appropriate forum is the Court of Claims. Tiemann v. Univ. of Cincinnati (1998), 127 Ohio App.3d 312, 318, 712 N.E.2d 1258. In Tiemann, the plaintiffs sought to enjoin the university from proceeding with a construction project that bypassed Ohio’s public-works and bidding requirements. The plaintiffs stated in their complaint that their suit was without a claim for monetary damages, but this court found that the Court of Claims did have jurisdiction because the complaint asked for declaratory, injunctive, and “any further” relief. Id. at 319, 712 N.E.2d 1258.

{¶ 9} Some years later, the Ohio Supreme Court decided Cementech. Cementech came before the Ohio Supreme Court as a certified conflict. The issue before the court was:

*88 Does the availability of injunctive relief, if timely filed but denied, preclude an award of lost profits in a municipal contract case?

Cementech, Inc. v. Fairlawn, 106 Ohio St.3d 1479, 2005-Ohio-3978, 832 N.E.2d 733.

{¶ 10} In the ensuing opinion, the Ohio Supreme Court held:
When a municipality violates competitive-bidding laws in awarding a competitively bid project, the rejected bidder cannot recover its lost profits as damages.

Cementech, Inc. v. Fairlawn, 109 Ohio St.3d 475, 2006-Ohio-2991, 849 N.E.2d 24, syllabus.

{¶ 11} At the trial level, the trial court had awarded Cementech its bid-preparation costs, and that award was not appealed. Consequently, the issue of whether a rejected bidder could recover its bid-preparation costs was not squarely before the Ohio Supreme Court. However, in resolving the certified conflict and holding that a rejected bidder cannot recover its lost profits as damages, the Ohio Supreme Court went further and stated, “[A] rejected bidder is limited to injunctive relief.” Id. at ¶ 10.

{¶ 12} The Ohio Supreme Court then discussed the rationale for injunctive relief:

It is clear that in the context of competitive bidding for public contracts, injunctive relief provides a remedy that prevents excessive costs and corrupt practices, as well as protects the integrity of the bidding process, the public, and the bidders. Moreover, the injunctive process and the resulting delays serve as a sufficient deterrent to a municipality’s violation of competitive-bidding laws.

Id. at ¶ 11.

{¶ 13} Meccon characterizes the Ohio Supreme Court’s statement limiting relief as dicta beyond the scope of the syllabus and the narrow issue that was before the court. Meccon argues that this court should not interpret Cementech

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Haueisen v. Worthington
2019 Ohio 5085 (Ohio Court of Appeals, 2019)
Meccon, Inc. v. Univ. of Akron
2012 Ohio 6317 (Ohio Court of Claims, 2012)
Lucki v. Ohio Department of Rehabilitation & Correction
966 N.E.2d 308 (Ohio Court of Appeals, 2011)
Meccon, Inc. v. University of Akron
2010 Ohio 3297 (Ohio Supreme Court, 2010)
Meccon, Inc. v. Univ. of Akron
919 N.E.2d 218 (Ohio Supreme Court, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
911 N.E.2d 933, 182 Ohio App. 3d 85, 2009 Ohio 1700, Counsel Stack Legal Research, https://law.counselstack.com/opinion/meccon-inc-v-university-of-akron-ohioctapp-2009.