Byrne & Jones Enterprises, Inc. d/b/a Byrne and Jones Construction v. Monroe City R-1 School District

493 S.W.3d 847, 2016 Mo. LEXIS 250, 2016 WL 4036760
CourtSupreme Court of Missouri
DecidedJuly 26, 2016
DocketSC94680
StatusPublished
Cited by29 cases

This text of 493 S.W.3d 847 (Byrne & Jones Enterprises, Inc. d/b/a Byrne and Jones Construction v. Monroe City R-1 School District) is published on Counsel Stack Legal Research, covering Supreme Court of Missouri primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Byrne & Jones Enterprises, Inc. d/b/a Byrne and Jones Construction v. Monroe City R-1 School District, 493 S.W.3d 847, 2016 Mo. LEXIS 250, 2016 WL 4036760 (Mo. 2016).

Opinions

PATRICIA,BRECKENRIDGE,. CHIEF JUSTICE

Byrne & Jones Enterprises, Inc. d/b/a Byrne and-Jones Construction filed an action against Monroe City R-l School District and members of the Board of Education of Monroe City R-l School District (collectively, the school district) alleging that it was denied a fair and equal opportunity to compete in the bidding process for a public works contract to build an athletics stadium because of collusion and favoritism between the school district and another bidder,'ATG Sports, Inc. The trial court dismissed- Byrne & Jones’ petition after finding that Byrne & Jones, as an unsuccessful bidder, lacked standing to challenge the award of the contract because it did not bring the action as a taxpayer or in the interest of the public. Byrne & Jones appealed, asserting that it has standing to challenge the school district’s award of the contract because, as a participant in the competitive bidding process, it has a right to a fair and equal opportunity to compete for public contracts.

The trial court erred in dismissing Byrne & Jones’ petition because competitive bidding procedures for public contracts ensure that all who wish to bid have a fair and equal opportunity to compete in a field without favoritism or collusion. Unsuccessful bidders, therefore, have an interest in having a fair and equal opportunity to compete in the bidding process. Accordingly, because Byrne <& Jones alleged that it was denied a fair and equal opportunity to compete in the bidding process for the athletics stadium, Byrne & Jones had standing to challenge the award of the contract to ATG Sports.

Nevertheless, the trial -court did not err in dismissing Byrne & Jones’ petition because Byrne & Jones is not entitled to the relief requested in its petition. Byrne <&. Jones’ request for injunctive relief is moot in that, at the time of oral argument, the school district had let the contract to ATG Sports, which completed the athletics stadium that is now in use. Furthermore, Byrne & Jones -is not entitled to its bid preparation costs because section 177.086.21 does not create a cause of action for, or authorize the recovery of, such damages. Accordingly, this Court affirms the trial court’s judgment dismissing Byrne <&’ Jones’ petition.

[850]*850Factual and Procedural Background2

In 2013, the school district began planning to build a new athletics stadium at Monroe City High School. The school district subsequently contacted ATG Sports about the proposed stadium and requested ATG Sports’ assistance in designing the project. Throughout 2013, the school district emailed and had meetings with ATG Sports about the stadium project. Over the course of its communications with the school district, ATG Sports submitted unsealed plans and drawings of the proposed stadium to the school district and drafted the request for proposals that the school district later used to solicit bids for the project.

In the request for proposals, the school district sought base bids on the project as well as bids on 13 possible alternates or enhancements to the project. Byrne & Jones and ATG Sports were the only bidders on the project.

Byrne & Jones submitted the lowest base bid as well as the lowest total bid when factoring in all 13 of the proposed enhancements to the project. When the school district selected only seven of the 13 alternates, however, ATG Sports’ total bid was the lowest. In January 2014, the school district awarded the contract to ATG Sports.

On March 25, 2014, Byrne & Jones filed a declaratory judgment action against the school district. In count I of its petition,3 Byrne & Jones alleged that the bidding procedures utilized by the school district did not allow all bidders a fair opportunity to compete on equal terms with ATG Sports. Byrne & Jones further alleged that the school district violated the competitive bidding process prescribed by law when it colluded with and acted with favoritism toward ATG Sports. In its prayer for relief, Byrne & Jones sought to enjoin the school district from entering into any contract with ATG Sports and requested an award of its costs,, attorney fees, and bid preparation costs in connection with the project.

The school district, subsequently, filed a motion to dismiss the petition. In its motion, the school district claimed that, as an unsuccessful bidder, Byrne & Jones lacked standing to challenge the award of the contract to another bidder because Byrne & Jones had no vested or protectable interest in the award of the contract. Byrne & Jones filed suggestions in opposition arguing that an unsuccessful bidder has standing to challenge a contract if the bidding procedures did not afford all bidders a fair and equal opportunity to compete.

On May 22, 2014, the trial court entered its judgment sustaining the school district’s motion to dismiss. The trial court determined that a low bidder has no standing under section 177.086, the school district’s competitive bidding procedures, to challenge the award of a contract to another bidder because the statute is clearly intended to safeguard the interest of the public, not the individual bidders. Therefore, the trial court concluded that Byrne & Jones lacked standing in that it was bringing the action as an unsuccessful bidder, not as a representative of Monroe City R-l School District taxpayers.

[851]*851Byrne & Jones appeals. After an opinion by the court of appeals, the case was transferred to this Court. Mo. Const, art. V, sec. 10.

Standard of Review

This Court reviews the grant of a motion to dismiss de novo. Ambers-Phillips v. SSM DePaul Health Ctr., 459 S.W.3d 901, 905 (Mo. banc 2015). “In reviewing the dismissal of a petition, the sole issue to be decided is whether, after allowing the pleading its broadest intendment, treating all facts alleged as true and construing all allegations favorably to the plaintiff, the plaintiff is entitled to relief.” Doss v. Doss, 822 S.W.2d 427, 428 (Mo. banc 1992). “This Court must affirm the. dismissal if it can be sustained on any ground supported by the motion to- dismiss.” Beck v. Fleming, 165 S.W.3d 156, 158 (Mo. banc 2005).

Standing of Unsuccessful Bidders

Byrne & Jones argues that it has standing to challenge the award of the contract to ATG Sports because it was denied a fair and equal opportunity to compete in the bidding process. To bring an action in a Missouri court, a party must have standing. Lebeau v. Commissioners of Franklin Cnty., Missouri, 422 S.W.3d 284, 288 (Mo. banc 2014). Standing is a threshold issue and “a prerequisite to a court’s authority to address substantive issues.” S.C. v. Juvenile Officer, 474 S.W.3d 160, 163 (Mo. banc 2015). Standing is a necessary component of a justiciable case that must be established prior to adjudication of a base’s merits. Schweich v. Nixon, 408 S.W.3d 769, 774 (Mo. banc 2013). Moreover, “[standing is an antecedent to the right to relief.” Manzara v. State,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Willie Roark v. KC Pet Project
Missouri Court of Appeals, 2024
Debbie M. Earley v. Mary V. Dunn
Missouri Court of Appeals, 2023
LO Management, LLC v. Office of Administration
Missouri Court of Appeals, 2022
Shondel Church v. State of Missouri
913 F.3d 736 (Eighth Circuit, 2019)
Truong v. Truong
564 S.W.3d 761 (Missouri Court of Appeals, 2018)
Agnew v. Mo.-Am. Water Co.
567 S.W.3d 652 (Missouri Court of Appeals, 2018)
Wilson v. Nenninger
561 S.W.3d 804 (Missouri Court of Appeals, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
493 S.W.3d 847, 2016 Mo. LEXIS 250, 2016 WL 4036760, Counsel Stack Legal Research, https://law.counselstack.com/opinion/byrne-jones-enterprises-inc-dba-byrne-and-jones-construction-v-mo-2016.