Colosseo USA, Inc. v. Univ. of Cincinnati

2019 Ohio 2026
Ohio Court of Appeals·Decided May 24, 2019·No. C-180223·Published·Cited by 6 cases

Opinion

[Cite as Colosseo USA, Inc. v. Univ. of Cincinnati, 2019-Ohio-2026.]

IN THE COURT OF APPEALS

FIRST APPELLATE DISTRICT OF OHIO HAMILTON COUNTY, OHIO

COLOSSEO USA, INC., : APPEAL NO. C-180223 TRIAL NO. A-1703142

Plaintiff-Appellant, :

vs. : O P I N I O N. UNIVERSITY OF CINCINNATI, :

Defendant-Appellee.

:

Civil Appeal From: Hamilton County Court of Common Pleas Judgment Appealed From Is: Affirmed Date of Judgment Entry on Appeal: May 24, 2019

Stites & Harbison PLLC, William G. Geisen and Andrew J. Poltorak, for Plaintiff- Appellant,

Brickler & Eckler LLP, Jeffrey P. McSherry and Mark E. Evans, for Defendant- Appellee.

MYERS, Presiding Judge.

{¶1} Colosseo, USA, Inc., (“Colosseo”) appeals the trial court’s judgment granting the motion of the University of Cincinnati (“UC”) to dismiss for lack of subject-matter jurisdiction Colosseo’s claims for a declaratory judgment stemming from UC’s award of a contract for the replacement of a video scoreboard at UC’s Nippert Stadium to another bidder, and for other future projects.

Background

{¶2} In February 2017, UC issued a Request for Proposal (“RFP”) that sought proposals from vendors for an integrated videoboard and digital signage system for six of UC’s athletic facilities, including Nippert Stadium, Fifth Third Arena, Schott Stadium, Gettler Stadium, Keating Natatorium, and Sheakley Athletic Center. The RFP made clear that awards for each of the facilities would be made separately as funding became available.

{¶3} Four vendors submitted responses to the RFP. On April 11, 2017, UC notified two of them, Colosseo and Daktronics, Inc., that they were the vendors under primary consideration and that UC would contact each of them to schedule a final interview.

{¶4} Before the final interview, UC notified Colosseo and Daktronics that the interview would be focused solely on the replacement of the scoreboard for Nippert Stadium. Then UC asked them to submit supplemental proposals limited to that scoreboard.

{¶5} Colosseo and Daktronics submitted supplemental proposals for only the replacement of the Nippert Stadium scoreboard. After reviewing both proposals, UC’s outside consultant and UC’s review committee recommended that the contract for the Nippert Stadium scoreboard project be awarded to Daktronics.

{¶6} On May 11, 2017, UC advised Colosseo and Daktronics that the contract for the replacement of the Nippert Stadium scoreboard was awarded to Daktronics. UC informed Colosseo that, even though it did not win the award for Nippert Stadium, Colosseo was selected as one of two firms qualified to bid on the remaining projects.

{¶7} Accordingly, UC issued a term contract that identified Colosseo and Daktronics as approved vendors who were qualified to participate in the replacement of scoreboards for the facilities identified in the RFP. The term contract specified that each of the athletic-facility projects would “be individually bid, scored, and awarded.” The contract stated that it was not an “exclusive” commitment, and contemplated the possibility of “multiple awards.” In addition, the contract specified that “[c]ontractors may be added and assignments may be changed.”

{¶8} On May 12, 2017, UC issued a purchase order to Daktronics for the Nippert Stadium scoreboard replacement, requiring installation to be completed by the end of August 2017, the date of the first home game for UC’s football team.

{¶9} On June 12, 2017, Colosseo filed a complaint for a temporary restraining order, preliminary injunction, and permanent injunction to enjoin UC from proceeding on the Nippert Stadium scoreboard replacement project and on any other work related to the RFP. In addition, Colosseo sought a declaratory judgment that the Nippert Stadium contract with Daktronics was void because in awarding the contract to Daktronics, UC had violated Ohio’s competitive-bidding laws, UC’s competitive-bidding rules established by its board of trustees, and the standards set forth in the RFP. It argued that it was the lowest and best bidder for both the Nippert Stadium contract and for the contract awarded under the RFP, and that the contract for the RFP should be awarded solely to Colosseo.

{¶10} Simultaneously, Colosseo moved for a temporary restraining order and a preliminary injunction to enjoin UC from continuing work related to the Nippert

Stadium scoreboard project. UC responded that the contract for the procurement of the scoreboard involved the purchase of goods and services and was not a public- improvement contract subject to competitive-bidding laws and rules.

{¶11} Following a hearing on June 16, 2017, the trial court denied Colosseo’s motion for a temporary restraining order and a preliminary injunction. The court

reasoned that Colosseo was unlikely to succeed on the merits because the contract for the Nippert Stadium project was a goods and services contract not subject to competitive-bidding laws and rules. In addition, the court found that Colosseo had not demonstrated that it would suffer irreparable harm if the requested relief was denied because it was still an approved vendor for the other five projects. The court also found that any injury suffered by Colosseo would not outweigh the potential harm to UC, and that the public interest would not be served by an award of injunctive relief. Colosseo did not appeal the denial of its motion for a temporary restraining order and a preliminary injunction.

{¶12} In mid-July 2017, UC filed an answer, a motion to stay discovery, and a motion for judgment on the pleadings. After an August hearing, the trial court

issued a written decision in September denying both motions.

{¶13} The case progressed and the parties proceeded with written discovery.

In January 2018, UC filed a motion to dismiss for lack of subject-matter jurisdiction,

or, in the alternative, for reconsideration of its earlier motion for judgment on the pleadings, arguing that the Nippert Stadium scoreboard replacement was now complete and contracts for the remaining projects had not yet been awarded.

{¶14} The trial court granted UC’s motion and dismissed the action. The court determined that, with respect to the Nippert Stadium scoreboard replacement

project, no further controversy existed for the court to decide, and no meaningful relief could be granted to Colosseo. The court dismissed Colosseo’s claims relating to the remaining athletic facilities for lack of subject-matter jurisdiction, concluding

that they were not ripe for review and that no justiciable controversy existed. Colosseo appeals the trial court’s judgment.

1. Dismissal of the Action

{¶15} In its first assignment of error, Colosseo argues that the trial court erred by granting UC’s motion to dismiss for lack of subject-matter jurisdiction.

{¶16} Where a trial court has resolved a declaratory-judgment action by determining that no justiciable controversy exists, we review the determination for

an abuse of discretion. Arnott v. Arnott, 132 Ohio St.3d 401, 2012-Ohio-3208, 972 N.E.2d 586, ¶ 13; Waldman v. Pitcher, 2016-Ohio-5909, 70 N.E.3d 1025, ¶ 17 (1st Dist.). Reversal is therefore warranted only if the trial court’s decision regarding justiciability was unreasonable, arbitrary, or unconscionable. Waldman at ¶ 17. A decision is unreasonable where it is not supported by a sound reasoning process. Id.

{¶17} A common pleas court’s subject-matter jurisdiction is constitutionally limited to “justiciable matters.” Ohio Constitution, Article IV, Section 4(B). A

justiciable matter exists for purposes of a declaratory-judgment action where a real controversy exists between adverse parties and speedy relief is necessary to preserve the parties’ rights. Moore v. Middletown, 133 Ohio St.3d 55, 2012-Ohio-3897, 975 N.E.2d 977, ¶ 49. A declaratory-judgment action does not authorize a court to render an advisory opinion. See Arnott at ¶ 10, quoting Mid-American Fire & Cas. Co. v. Healey, 113 Ohio St.3d 133, 2007-Ohio-1248, 863 N.E.2d 142, ¶ 9.

Free access — add to your briefcase to read the full text and ask questions with AI

Colosseo USA, Inc. v. Univ. of Cincinnati, 2019 Ohio 2026 (Ohio Ct. App. 2019).

2019 Ohio 2026 (Colosseo USA, Inc. v. Univ. of Cincinnati) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Nwafo v. Ugwualor
2024 Ohio 189 (Ohio Court of Appeals, 2024)
Delasoft, Inc. v. Ohio Dept. of Adm. Servs.
2022 Ohio 3403 (Ohio Court of Appeals, 2022)
Kellard v. Cincinnati
2021 Ohio 1420 (Ohio Court of Appeals, 2021)
Riddick v. MLS Homes, L.L.C.
2020 Ohio 897 (Ohio Court of Appeals, 2020)
Nationwide Agribusiness Ins. Co. v. Heidler
2019 Ohio 4311 (Ohio Court of Appeals, 2019)