Cementech, Inc. v. City of Fairlawn

827 N.E.2d 819, 160 Ohio App. 3d 450, 2005 Ohio 1709
CourtOhio Court of Appeals
DecidedApril 13, 2005
DocketNo. 22309.
StatusPublished
Cited by6 cases

This text of 827 N.E.2d 819 (Cementech, Inc. v. City of Fairlawn) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cementech, Inc. v. City of Fairlawn, 827 N.E.2d 819, 160 Ohio App. 3d 450, 2005 Ohio 1709 (Ohio Ct. App. 2005).

Opinion

Whitmore, Presiding Judge.

{¶ 1} Plaintiff-appellant, Cementech, has appealed from a decision of the Summit County Court of Common Pleas that limited the potential damages it could receive for bid-preparation costs. This court affirms in part and reverses in part.

I

{¶ 2} The instant matter stems from a request for bids for a service road in Fairlawn by defendant-appellee, the city of Fairlawn. Plaintiff-appellant, Cementech, submitted a bid for the service-road project. Fairlawn rejected the bid. On December 31, 2001, Cementech filed a “verified complaint for legal and equitable relief and writ of mandamus; temporary, preliminary, permanent injunction and writ of prohibition” against Fairlawn. In its complaint, Cementech alleged damages for bid-preparation costs, lost profits, consequential damages, and litigation costs in excess of $75,000.

{¶ 3} Although already requested in its complaint, Cementech also filed a separate motion for a temporary restraining order and preliminary and permanent injunction enjoining Fairlawn from taking any action or awarding a contract to any other bidder for the project. On January 4, 2002, Fairlawn responded in *453 opposition to Cementech’s motion for a temporary restraining order and preliminary and permanent injunction.

{¶ 4} In a journal entry dated January 7, 2002, the trial court denied Cementech’s motion for a temporary restraining order. The trial court found that “there is not a likelihood or probability of success on the merits by [Cementech] in this case.” The trial court also found that “there is little evidence to show that [Cementech] will suffer irreparable harm if the injunctive relief is not granted.”

{¶ 5} On February 19, 2002, Cementech filed a second request for a temporary restraining order and preliminary and permanent injunction and/or motion to reconsider. On March 4, 2002, the trial court denied Cementech’s second request for a temporary restraining order and preliminary and permanent injunction on its merits and denied its motion for reconsideration on the basis that said relief was not available.

{¶ 6} Fairlawn filed a motion for summary judgment on July 1, 2002. On September 3, 2002, Cementech responded with a motion in opposition to Fair-lawn’s motion for summary judgment. The trial court granted Fairlawn’s motion on November 1, 2002.

{¶ 7} Cementech appealed from the trial court’s decision to this court, and we reversed and remanded the case to the trial court.

{¶ 8} With the matter again before the trial court, Fairlawn and Cementech filed memoranda regarding potential awards of damages. On July 14, 2004, the trial court issued an order concerning the damages Cementech could receive if it was successful on its claims. The trial court ruled that “should [Cementech] prevail on its claims against [Fairlawn], then [Cementech] would be entitled to damages in an amount to compensate for bid preparations, but not for anticipated lost profits.” Rejecting Cementech’s public policy argument concerning damages for lost profits, the trial court found that “[t]he public has already paid for performance under the contract, and should not be expected to pay the same costs twice.”

{¶ 9} The trial court was partially persuaded by Cementech’s public policy arguments that a deterrent was necessary to ensure that Fairlawn and other government entities followed proper bidding procedures. The trial court found that “the prospect of liability for bid preparations to a disappointed bidder who relied on a municipal corporation’s compliance with competitive bidding laws would serve as a reasonable and necessary deterrent to noncompliance with such laws.”

{¶ 10} Although Cementech argued that the trial court had discretion to award attorney fees, the trial court found that “attorney fees [were] not appropriate in this case under these circumstances.”

*454 {¶ 11} A jury trial was held, and the jury found in favor of Cementech and awarded damages in the amount of $3,725.54 for bid-preparation costs. The jury found that Cementech’s bid was the lowest and best bid. The jury also found that Fairlawn abused its discretion in regard to the procedure it used to reject Cementech’s bid and that Cementech’s bid did not contain a material error or irregularity.

{¶ 12} Cementech has timely appealed from the trial court’s ruling prohibiting damages for anticipated lost profits, consequential damages, and attorney fees, asserting two assignments of error.

II

Assignment of Error Number One

The trial court erred as a matter of law in prohibiting an award of lost profits and consequential damages.

{¶ 13} In its first assignment of error, Cementech has argued that the trial court erred when it denied Cementech’s motion to seek damages for lost profits and consequential damages. Specifically, Cementech has argued that, as a matter of law, it was entitled to monetary damages for detrimental reliance and for lost profits, especially since injunctive relief was denied and Fairlawn was found to have acted illegally. 1 We agree.

{¶ 14} When an appellate court is presented with purely legal questions, the standard of review to be applied is de novo. Akron-Canton Waste Oil, Inc. v. Safety-Kleen Oil (1992), 81 Ohio App.3d 591, 602, 611 N.E.2d 955. Under the de novo standard of review, an appellate court does not give deference to a trial court’s decision. Akron v. Frazier (2001), 142 Ohio App.3d 718, 721, 756 N.E.2d 1258.

{¶ 15} The jury in the instant matter determined in its verdict that Cementech was the lowest and best bid. Therefore, by law Cementech should have been awarded the bid. The next issue before the jury was damages, which prior to trial had been limited by the trial court to bid-preparation costs. The jury awarded Cementech damages for its bid-preparation costs, but based on the trial court’s previous ruling, Cementech was not able to recover lost profits. On appeal, Cementech has argued that it is entitled to damages for lost profits. Fairlawn has responded that lost profits are not recoverable because injunctive relief was available.

*455 {¶ 16} We find Fairlawn’s argument that Cementech could not receive monetary damages because it could have received injunctive relief illusory. Cementech requested injunctive relief, and it was denied. When it was determined that Fairlawn had abused its discretion and that Cementech was the lowest and best bid and, thus, injunctive relief was improperly denied, the project was already complete. With the project complete, injunctive relief wrongfully denied, a determination that Cementech was the lowest and best bid, and a trial court ruling limiting damages to bid-preparation costs, Cementech was left with inadequate relief.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Meccon, Inc. v. University of Akron
2010 Ohio 3297 (Ohio Supreme Court, 2010)
Sims v. Dibler
875 N.E.2d 965 (Ohio Court of Appeals, 2007)
Cementech, Inc. v. City of Fairlawn
849 N.E.2d 24 (Ohio Supreme Court, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
827 N.E.2d 819, 160 Ohio App. 3d 450, 2005 Ohio 1709, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cementech-inc-v-city-of-fairlawn-ohioctapp-2005.