Matter of On-Line Games Contract

653 A.2d 1145, 279 N.J. Super. 566
CourtNew Jersey Superior Court Appellate Division
DecidedFebruary 17, 1995
StatusPublished
Cited by48 cases

This text of 653 A.2d 1145 (Matter of On-Line Games Contract) is published on Counsel Stack Legal Research, covering New Jersey Superior Court Appellate Division primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Matter of On-Line Games Contract, 653 A.2d 1145, 279 N.J. Super. 566 (N.J. Ct. App. 1995).

Opinion

279 N.J. Super. 566 (1995)
653 A.2d 1145

IN THE MATTER OF THE PROTEST OF THE AWARD OF THE ON-LINE GAMES PRODUCTION AND OPERATION SERVICES CONTRACT, BID NO. 95-X-20175.

Superior Court of New Jersey, Appellate Division.

Argued January 4, 1995.
Decided February 17, 1995.

*573 Before Judges BRODY, LONG, and ARNOLD M. STEIN.

Clive S. Cummis argued the cause for appellant Autotote Lottery Corp. (Sills, Cummis, Zuckerman, Radin, Tischman, Epstein & Gross, attorneys; Mr. Cummis, of counsel; Kenneth F. Oettle and Paul P. Josephson, on the brief).

Joel H. Sterns argued the cause for appellant GTECH Corp. (Sterns & Weinroth; Skadden, Arps, Slate, Meagher & Flom; and Williams & Connolly, of the Washington, D.C., bar, attorneys; Mr. Sterns, of counsel; Mark D. Schorr, on the brief).

Patrick D. Kennedy argued the cause for respondent Automated Wagering International, Inc. (McCarter & English; Picco, Mack, Herbert; and Oppenheimer, Wolff & Donnelly, of the New York Bar, attorneys; Christopher W. Jones, of counsel; William T. Reilly and Mr. Kennedy, of counsel and on the brief; Maeve E. Cannon, Sean Byrnes and James E. McGuire, on the brief).

Deputy Attorney General Ellen M. Casey argued the cause for respondent Treasurer (Deborah T. Poritz, Attorney General of *574 New Jersey, attorney; Joseph L. Yannotti, Assistant Attorney General, of counsel; Ms. Casey, on the brief).

The opinion of the court was delivered by LONG, J.A.D.

This appeal arises out of the State Treasurer's award of a five-year contract to respondent, Automated Wagering International, Incorporated (AWI), for equipment, materials and services to implement and operate the on-line gaming system of the New Jersey State Lottery Commission. Appellants, GTECH Corporation (GTECH), the incumbent vendor, and Autotote Lottery Corporation (Autotote), challenge the Treasurer's determination that AWI's bid conformed to the Request for Proposals (RFP). Autotote also challenges the Treasurer's decision that its bid was non-conforming. We reverse the determination that AWI's bid was conforming, affirm the determination that Autotote's bid was non-conforming, and remand the case to the Treasurer to decide whether to award the contract to GTECH or to rebid it.

I

A. The RFP

On August 9, 1993, the Division of Purchase and Property issued an RFP for On-Line Games Production and Operation Services, Division of Lottery, Contract No. 95-X-20175. The 250-page RFP contained many requirements; only those which are relevant to this appeal will be set forth.

1. Terminals and Customer Display

The technical section relating to terminals stated that: "The Contractor must provide terminals that meet the requirements as specified below." Those requirements included:

The Contractor must provide (a) customer visual display unit(s), for each on-line Agent location. Due to the wide diversity of space in Agent locations, the visual display unit may be terminal mounted in some locations, or mounted elsewhere (wall, pole, window, etc.) in others. All unit messages must be clearly visible from *575 fifteen feet (15') by customers. Special features (scrolling, flashing, etc.) are welcomed and must be described fully.
[RFP § 6.3.2 (emphasis added).]

The purpose of a customer display visible from fifteen feet is advertising. It is meant to catch the attention of other individuals at the premises at which lottery tickets are sold and induce them to buy. Each bidder had to

respond to this section by addressing each and every portion of subsection 6.3 of the RFP, entitled, "Terminals." The response must ensure fulfillment of the Scope of Work. In doing so, the bidder must ensure that all terms cited below are incorporated in his response.
Bidders must provide complete documentation on the terminals proposed, including pictorial exhibits and the technical specifications for the terminal equipment including, but not limited to, the functional capabilities and physical and environmental characteristics for each proposed terminal.
[RFP § 7.5.2 (emphasis added).]

In addition, the bids had to clarify which terminal features were included and which were excluded from the basic bid price.

2. Implementation and Backup

RFP § 6.9 incorporated a "Big Bang" approach to convert from the current lottery system to the new system. "Big Bang" was defined as:

A form of terminal network conversion in which the new agent terminals are installed gradually in retail locations but do not take over sales until a complete cutover following the last sales day on the existing Contract. All new agent terminals go into production on the same day. The old terminal can then be removed from the premises.
[RFP § 4.0.]

RFP § 6.9 further explained that the new contractor's secondary site would be used to stage and test the new system, and that operations would proceed from November 24, 1994, supported only by that site until the primary site could be fitted out and installed. The RFP envisioned that the remote backup location would serve as the primary site for the first six months of implementation. During that period, GTECH, the incumbent vendor, would remove its equipment now located adjacent to Lottery headquarters in Lawrenceville, and the new vendor would prepare and install the central processing systems that would eventually become the *576 primary operations site. In other words, when the primary site became operational, the secondary site was to assume its original backup function.

During the conversion when the secondary site was initially operating the Lottery, RFP § 6.9 required:

For the period between November 24, 1994, and the availability of the data center at Lottery Headquarters as the primary site, the Contractor must provide sufficient backup capabilities equal to the current contingency plan: A hot backup system for the active primary system, and the ability to restore service within seventy-two (72) hours following a disaster at the single processing site.

RFP § 6.9 also required each bidder to propose a specific implementation plan for conversion, with a detailed discussion of, among other things, the installation and testing of the system's hardware and software components and the training of agents and Lottery personnel. Specifically, RFP § 6.9 stated:

If the Contractor proposed (an) alternative(s) to the specified implementation approach and schedule, it (they) must meet or exceed all the requirements specified in the RFP resulting in this Contract.
The Contractor is required to carry out their proposed implementation plan. The plan must detail hardware production capability, software development, and installation and testing of hardware and software components.
The implementation plan must also detail the structuring of the network and the installation of the network through the combined efforts of the communications carrier, the State, and the Contractor....

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In the Matter of New Jersey Transit Corporation, Etc.
New Jersey Superior Court App Division, 2026
In the Matter of Bid Solicitation 23dpp00796, Etc.
New Jersey Superior Court App Division, 2025
Ml, Inc. v. Edison Township Board of Education
New Jersey Superior Court App Division, 2025
In the Matter of Protest of Sisbarro Towing & Recovery, LLC, Etc.
New Jersey Superior Court App Division, 2025
Earle Asphalt Company v. County of Gloucester
New Jersey Superior Court App Division, 2025
Anselmi & Decicco, Inc. v. J. Fletcher Creamer & Son, Inc.
New Jersey Superior Court App Division, 2025
United Services Inc. v. City of Newark
New Jersey Superior Court App Division, 2024
Suburban Disposal, Inc. v. City of Paterson
New Jersey Superior Court App Division, 2024
In the Matter of Higbee Beach Restoration Project, Etc.
New Jersey Superior Court App Division, 2024

Cite This Page — Counsel Stack

Bluebook (online)
653 A.2d 1145, 279 N.J. Super. 566, Counsel Stack Legal Research, https://law.counselstack.com/opinion/matter-of-on-line-games-contract-njsuperctappdiv-1995.