LePretre v. Lend Lease Construction, Inc.

2017 IL App (1st) 162320
CourtAppellate Court of Illinois
DecidedJune 26, 2017
Docket1-16-2320
StatusUnpublished
Cited by1 cases

This text of 2017 IL App (1st) 162320 (LePretre v. Lend Lease Construction, Inc.) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
LePretre v. Lend Lease Construction, Inc., 2017 IL App (1st) 162320 (Ill. Ct. App. 2017).

Opinion

FIRST DIVISION June 26, 2017

No. 1-16-2320 2017 IL App (1st) 162320

IN THE APPELLATE COURT OF ILLINOIS FIRST JUDICIAL DISTRICT

) WILLIAM LePRETRE, ) Appeal from the ) Circuit Court of Plaintiff-Appellant, ) Cook County. ) v. ) ) No. 13 L 13896 LEND LEASE (US) CONSTRUCTION, INC., ) a Corporation, ) Honorable ) Kathy M. Flanagan, Defendant-Appellee. ) Judge Presiding. )

PRESIDING JUSTICE CONNORS delivered the judgment of the court, with opinion. Justices Simon and Mikva concurred in the judgment and opinion.

OPINION

¶1 Plaintiff William M. LePretre brought a cause of action against Lend Lease (US)

Construction, Inc. (Lend Lease) and other defendants for injuries he allegedly sustained while

working at a construction site at 515 North Clark Street in Chicago. Lend Lease filed a motion

for summary judgment, and the trial court granted it, finding that Lend Lease owed no duty to

plaintiff under which it could be subject to vicarious or direct liability. The trial court also denied

plaintiff’s motion to reconsider, and plaintiff now appeals. We affirm. No. 1-16-2320

¶2 BACKGROUND

¶3 Plaintiff filed a nine-count complaint against Lend Lease and other defendants seeking

damages for injuries he sustained when he slipped and fell while installing iron rebar on

February 15, 2012. Count I was directed at Lend Lease, and it is the only count at issue in this

appeal. Lend Lease was the general contractor for the project, and it retained Adjustable Forms,

Inc. (Adjustable), as the concrete sub-contractor, which in turn retained plaintiff’s employer,

Bond Steel, to install and reinforce the iron rebar for the concrete pour.

¶4 Plaintiff alleged that Lend Lease failed to make a reasonable inspection of the premises;

improperly operated, managed, maintained, and controlled the premises; failed to provide

plaintiff with a safe place to work; failed to warn plaintiff of the dangerous conditions there

existing; failed to provide adequate safeguards; failed to supervise work being done on the

premises; failed to provide a safe and proper excavation; and failed to provide safe and proper

material to be placed within the excavation.

¶5 Lend Lease filed a motion for summary judgment contending that it owed no duty under

section 414 of the Restatement (Second) of Torts because, although it retained some general

supervisory powers, it did not control the incidental aspects of the work of Adjustable or Bond

Steel. Lend Lease noted that in plaintiff’s discovery deposition, plaintiff attributed his injury to

three factors: the rebar pieces that he was installing were too long, the workspace he was in was

too confined, and there was loose, falling dirt. Lend Lease argued that the contract between it

and Adjustable, and the one between Adjustable and Bond Steel, showed that it retained no

control over the rebar length, the work space, or debris removal and did not direct or control

plaintiff’s work.

2 No. 1-16-2320

¶6 Lend Lease attached relevant portions of the contracts to its motion for summary

judgment. These attachments showed that Lend Lease entered into a contract with the owner of

the project, ClarGran, for the construction of Clark and Grand Hotels. Section 3.3.1 of the

General Conditions of that contract provided:

“The Contractor [Lend Lease] shall be solely responsible for and have control

over construction means, methods, techniques, sequences, and procedures and for

coordinating all portions of the Work under the Contract, unless the Contract

Documents give other specific instructions concerning these matters ***.”

¶7 Section 10.2.1 of the General Conditions provided:

“The Contractor shall take reasonable precautions for the safety of, and shall

provide reasonable protection to prevent damage, injury or loss to:

1. employees on the Work and other persons who may be affected thereby ***.”

¶8 Lend Lease then entered into a subcontract with Adjustable for the concrete work on the

project. Portions of this subcontract were attached to Lend Lease’s motion for summary

judgment. “Exhibit B—Scope of Work” in the subcontract provided:

“Subcontractor [Adjustable] shall provide all labor, material, equipment,

supervision as required to complete all scope-of-work items on this Concrete

Subcontract and related work, in accordance with the Drawings, Specifications

and the Contract Documents (‘Work’).”

¶9 Article 15 of the subcontract provided:

“Subcontractor agrees that the prevention of accidents to workers engaged upon

or in the vicinity of the work is its responsibility, even if the Contractor [Lend

3 No. 1-16-2320

Lease] establishes a safety program for the entire Project. Subcontractor shall

establish and implement safety measures, policies and standards ***.”

¶ 10 Article 16 provided:

“Subcontractor shall, at its own expense: (a) keep the premises at all times free

from waste materials *** and other debris accumulated in connection with the

Work by collecting and removing such debris from the jobsite on a daily or other

basis ***.”

¶ 11 Adjustable then hired Bond Steel to perform the rebar reinforcement installation portion

of the concrete work. Lend Lease attached portions of that subcontract to its motion for summary

judgment, which indicated that the prevention of accidents and injuries shall be the primary

concern of Bond Steel and that it should maintain a safe and healthful work environment with its

safety program. The contract also noted that Bond Steel “shall submit a copy of [its] safety

program together with the name and experience of [its] on-site safety representative.” The

contract stated that Bond Steel agreed to comply with OSHA and all safety and health

requirements imposed by Adjustable and Adjustable’s “Subcontractor Safety Handbook” and

would conduct operations in a safe and healthy manner.

¶ 12 Lend Lease noted that Adjustable hired Gerdau Ameristeel to design and provide all the

reinforcing steel needed to complete the concrete work in accordance with the project

construction documents. The purchase order was attached to the motion for summary judgment.

¶ 13 Lend Lease also attached several deposition transcripts to its motion for summary

judgment. Plaintiff stated in his discovery deposition that he was Bond Steel’s foreman on the

project and was in charge of the Bond Steel crew. Plaintiff and his crew took directions with

respect to what they would do on a daily basis from Adjustable’s superintendent, Eric Blank.

4 No. 1-16-2320

Plaintiff testified that he did not take any direction as to how to install steel, what materials to

use, or where to work from anyone employed by Lend Lease. Plaintiff testified in his deposition

that Lend Lease never stopped Bond Steel’s work for safety reasons, and did not provide safety

direction specifically relating to the installation of the rebar. He further testified that Lend Lease

conducted a site orientation for all new employees to discuss general safety.

¶ 14 Plaintiff also testified that at the time of his accident, he and his crew were installing a

27-foot long piece of rebar and that plaintiff believed the rebar was too long and the work space

was too tight because he had to leverage the bars into place. Plaintiff testified that he complained

to Blank about the length of the rebar and the size of the work space, and asked him to get

shorter bars.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

LePretre v. Lend Lease Construction, Inc.
2017 IL App (1st) 162320 (Appellate Court of Illinois, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
2017 IL App (1st) 162320, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lepretre-v-lend-lease-construction-inc-illappct-2017.