Joyce v. Mastri

CourtAppellate Court of Illinois
DecidedJanuary 11, 2007
Docket1-06-0086 Rel
StatusPublished

This text of Joyce v. Mastri (Joyce v. Mastri) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Joyce v. Mastri, (Ill. Ct. App. 2007).

Opinion

FOURTH DIVISION January 11, 2007

No. 1-06-0086

TIMOTHY JOYCE, ) Appeal from ) the Circuit Court Plaintiff-Appellant, ) of Cook County. ) v. ) ) JAY J. MASTRI, JAY’S HVAC, INC., an ) Illinois Corporation, and MADISON SERVICES, INC., ) a Mississippi Corporation, ) Honorable ) Cheryl A. Starks, Defendants-Appellees. ) Judge Presiding.

PRESIDING JUSTICE QUINN delivered the opinion of the court:

Plaintiff, Timothy Joyce, an employee of an independent contractor, suffered injuries

when he fell off a ladder at a construction site. Plaintiff filed a complaint at law with two counts

against defendant, Madison Services, Inc. (Madison Services), the general contractor of the site,

alleging common-law negligence. Plaintiff appeals from orders of the circuit court granting

summary judgment in defendant’s favor.1 Plaintiff contends that defendant had a duty to prevent

his injuries in light of its contract with plaintiff’s employer, its retention of control over certain

aspects of the construction site, its contract with the federal government and nondelegable duty to

comply with applicable safety regulations, and as the possessor of the land where his injury

occurred. For the following reasons, we affirm.

1 Defendants Jay J. Mastri and Jay’s HVAC, Inc. are not parties in this appeal. 1-06-0086

I. Background

Plaintiff’s injuries occurred on April 16, 2001, at a construction site at the United States

Army Reserve Base in Arlington Heights, Illinois. Madison Services acted as the general

contractor at the construction project to demolish and install air handling systems. Madison

Services hired plaintiff’s employer, Elk Grove Mechanical, Inc. (EGM), to perform certain

demolition and construction work at the site. EGM contracted to work on demolishing air

handling units and their appurtenances in mechanical rooms 110 and 115 at the site.

Pursuant to section 8.1 of the contract between Madison Services and EGM, EGM was

required to execute the work contracted for and provide “all labor, materials, equipment, services

and other items required to complete such portion of the Work.” Section 3.2.2 of the contract

provided that Madison Services “shall not give instructions or orders directly to employees or

workmen of [EGM], except to persons designated as authorized representatives of [EGM].”

Under section 2.1, Madison Services and EGM agreed to be “mutually bound by the terms of

[the] Agreement and, to the extent that provisions of the Prime Contract apply to the Work of the

Subcontractor, the Contractor apply to the Work of the Subcontractor all obligations and

responsibilities that the Owner, under the Prime Contractor assumes toward the Owner and the

Architect.” Also, under section 4.3.1, EGM agreed that it “shall take reasonable safety

precautions with respect to performance of this Subcontract, shall comply with safety measures,

initiated by [Madison Services] and with applicable laws, ordinances, rules, regulations and

orders of public authorities for the requirements of the Prime Contract [between Madison

Services and the United States Government]. [EGM] shall report within three days an injury to

-2- 1-06-0086

an employee or agent of [EGM] which occurred at the site.”

Additionally, section 4.4.1 of the contract provided that “[EGM] shall keep the premises

and surrounding area free from accumulation of waste materials or rubbish caused by operations

performed under this Subcontract. [EGM] shall not be held responsible for unclean conditions

caused by other contractors and subcontractors.” Section 4.6.1 provided:

“To the fullest extent permitted by law, [EGM] shall indemnify and hold

harmless the Owner, Contractor, Architect, Architect’s consultants, and agents

and employees of any of them from and against claims, damages, losses and

expenses, including but not limited to attorney’s fees, arising out of or under this

Subcontract, provided that such claim, damage, loss or expense is attributable to

bodily injury, sickness, disease or death, or to injury to or destruction of tangible

property (other than the Work itself) including loss of use resulting therefrom, but

only to the extent caused in whole or in part by negligent acts or omissions of

[EGM], [EGM’s] Sub-subcontractor, anyone directly or indirectly employed by

them or anyone for whose acts they may be liable, regardless whether or not such

claim, damage, loss or expense is caused in part by a party indemnified

hereunder.”

Plaintiff testified at his deposition that on April 16, 2001, he arrived at the work site on

the Army Reserve Base at approximately 8 a.m. Plaintiff testified that after first arriving at the

work site, he set up extension cords to plug in saws and swept the larger mechanical room. At

approximately 9:20 a.m., plaintiff testified that he began setting up in the smaller mechanical

-3- 1-06-0086

room where he was injured. Plaintiff testified that his employer, EGM, was contracted to tear out

several 15-ton air handlers at the time. Plaintiff was attempting to remove duct work at the time

of his fall.

Plaintiff testified that in order to set up for the removal of duct work, he used a ladder that

was brought to the work site by defendant Jay Mastri, from Jay’s HVAC. Plaintiff testified that

he set up the ladder near the west wall of the mechanical room and extended it to approximately

15 feet. Plaintiff testified that the feet of the ladder were four feet from the wall. Plaintiff

testified that when he climbed about 10 to 12 feet up the ladder to begin working, the ladder

started to retract back to its normal position. Plaintiff testified that he heard part of the locking

mechanism flapping against the rungs of the ladder as it retracted. Plaintiff testified that the

noise sounded like “tick, tick, tick, tick” that one would hear when the locking mechanism on a

ladder is unlatched and the ladder is retracting. Plaintiff testified that he held on to the ladder

and rode the ladder down. Plaintiff testified that when he neared the bottom of the ladder, his

wrist became caught in the rungs and his wrist was shattered. Plaintiff testified that he then fell

to the ground. Plaintiff testified that in his opinion the ladder retracted because there was a

problem with the locking mechanism.

Plaintiff testified that no one told him to use the particular ladder in question. Plaintiff

testified that the ladder was available, so he picked it up and began using it. Plaintiff testified

that Rich Olson was his supervisor at EGM, and that he only saw Olson once to go over things.

Plaintiff testified that Jay Mastri, of Jay’s HVAC, was his day-to-day supervisor, who then

reported to Rich Olson. Plaintiff testified that he had no contact with any employee or anyone

-4- 1-06-0086

related to Madison Services. Plaintiff testified that Madison Services did not provide any of the

equipment for the work project.

Michael Reinersman testified at his deposition that he was employed by Madison

Services, as a project or site manager, at the time of plaintiff’s injury. In April 2001, Reinersman

was responsible for overseeing Madison Services’ projects in the Midwestern region, which

included six states and between 20 to 25 jobs. Reinersman was the only Madison Services

employee performing that job in the Midwestern region, at the time of plaintiff’s injury.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Fris v. Personal Products Co.
627 N.E.2d 1265 (Appellate Court of Illinois, 1994)
Bokodi v. Foster Wheeler Robbins, Inc.
728 N.E.2d 726 (Appellate Court of Illinois, 2000)
Bieruta v. Klein Creek Corp.
770 N.E.2d 1175 (Appellate Court of Illinois, 2002)
Dobsons, Inc. v. Oak Park National Bank
407 N.E.2d 993 (Appellate Court of Illinois, 1980)
Cochran v. George Sollitt Construction Co.
832 N.E.2d 355 (Appellate Court of Illinois, 2005)
Rangel v. Brookhaven Constructors, Inc.
719 N.E.2d 174 (Appellate Court of Illinois, 1999)
Moorehead v. Mustang Construction Co.
821 N.E.2d 358 (Appellate Court of Illinois, 2005)
Bucheleres v. Chicago Park District
665 N.E.2d 826 (Illinois Supreme Court, 1996)
Downs v. Steel and Craft Builders, Inc.
831 N.E.2d 92 (Appellate Court of Illinois, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
Joyce v. Mastri, Counsel Stack Legal Research, https://law.counselstack.com/opinion/joyce-v-mastri-illappct-2007.