Foley v. Builtech Construction, Inc.

2019 IL App (1st) 180941
CourtAppellate Court of Illinois
DecidedJuly 23, 2019
Docket1-18-0941
StatusUnpublished

This text of 2019 IL App (1st) 180941 (Foley v. Builtech Construction, Inc.) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Foley v. Builtech Construction, Inc., 2019 IL App (1st) 180941 (Ill. Ct. App. 2019).

Opinion

2019 IL App (1st) 180941 No. 1-18-0941 Opinion filed July 23, 2019

Second Division

IN THE

APPELLATE COURT OF ILLINOIS

FIRST DISTRICT

JOHN FOLEY, ) Appeal from the Circuit Court ) of Cook County. Plaintiff-Appellant, ) ) v. ) No. 16 L 2809 ) BUILTECH CONSTRUCTION, INC., ) The Honorable ) Kathy M. Flanagan, Defendant-Appellee. ) Judge, presiding. )

JUSTICE HYMAN delivered the judgment of the court, with opinion Justice Pucinski concurred in the judgment and opinion. Justice Mason dissented, with opinion.

OPINION

¶1 An employee of a subcontractor was injured while moving rebar used for concrete

installation. He sued the general contractor, Builtech Construction, Inc., for negligence. After

discovery closed, Builtech moved for summary judgment, arguing it had neither actual nor

constructive notice of any dangerous condition at the jobsite. The trial court granted summary

judgment. We reverse and remand for further proceedings.

¶2 We hold that the issue of whether Builtech retained sufficient control over the

subcontractor’s work to trigger liability for its employee’s injury presents a question of fact, No. 1-18-0941

precluding summary judgment. Builtech had a project superintendent who inspected the jobsite

daily, its own safety measures in place, a safety manual, ongoing training, and a safety

supervisor monitoring safety at the worksite who was authorized to halt the subcontractor’s

unsafe work practices. Builtech also employed an outside safety auditor who worked closely

with the safety supervisor. The contract between Builtech and the subcontractor required the

subcontractor to comply with Builtech’s own safety rules. Because a material question of fact

arises regarding the issue of compliance with Builtech’s own safety rules, summary judgment is

inappropriate.

¶3 Background

¶4 Second Amended Complaint

¶5 While attempting to retrieve buried rebar on the jobsite, John Foley was injured. Foley’s

second amended complaint alleged construction negligence in that Builtech had the authority to

stop the work, refuse the work and materials, “and/or order changes in the work, in the event the

work was being performed in a dangerous manner or for any other reason.” Foley also alleged

that Builtech had a duty to exercise reasonable care at the site, including providing proper and

safe placement of the rebar, and failed to (i) provide a safe workplace, (ii) inspect and supervise

the work, (iii) warn of dangerous conditions, and (iv) provide adequate space to store the rebar.

¶6 A second count, “Premises Liability,” alleged Builtech had a duty to maintain the jobsite

and through its negligence caused the premises “to become and remain in a dangerous

condition.” Builtech “improperly operated, managed, maintained, and controlled” the worksite;

failed to properly move the rebar, allowing it to be moved and buried; failed to reasonably

inspect and warn Foley of the dangerous condition; and failed to provide space to adequately

store the rebar.

-2- No. 1-18-0941

¶7 Depositions

¶8 Builtech retained two subcontractors, Chicago Town and Precision Excavation, Inc., to

do the foundation work. Precision would excavate the site, while Chicago Town was to perform

concrete services for the building’s foundation. The concrete structures were reinforced with

steel rebar; Chicago Town’s work included placing rebar into the forms, pouring concrete into

the forms, and then stripping the forms. The rebar was stacked on-site.

¶9 Bob Bokar

¶ 10 Builtech’s superintendent for the project, Bob Bokar, had a storefront office across from

the jobsite. Bokar supervised all the subcontractors on the jobsite and was part of the safety

department. Eliminating jobsite hazards was part of Bokar’s duties. Bokar, on a daily basis,

inspected the workplace, arriving at the jobsite around 6 a.m. Builtech had the authority to direct

people how to properly lift heavy items on the jobsite. Part of Bokar’s job was to stop a worker

from improperly lifting a heavy item. If Bokar determined a subcontractor’s “means and

methods” were unsafe, he had the authority to stop the subcontractor and direct safety or work

method changes. Chicago Town employees were required to comply with all decisions made by

Builtech regarding safety requirements.

¶ 11 Builtech had an auditor who would periodically inspect the jobsite to identify unsafe

conditions or work methods and then notify Bokar of any concerns. John Ribskis, Builtech’s

safety supervisor, accompanied the auditor and possessed the authority to require workers to

change unsafe work means and methods.

¶ 12 Builtech’s safety manual required subcontractors to comply with its “means and

methods” provisions, including lifting and material handling. Builtech held weekly meetings for

its subcontractors on various safety topics.

-3- No. 1-18-0941

¶ 13 Bokar took photographs of the jobsite, “usually daily.” During the deposition he testified

about photographs taken on May 11 and May 15. Bokar stated he did not take photographs to try

to document where the incident occurred.

¶ 14 Chicago Town ordered the rebar for the concrete work and scheduled delivery. Chicago

Town workers unloaded the rebar, but Bokar controlled its storage on-site. Further, if Chicago

Town wanted to store the rebar in a location or manner that could have been hazardous to

workers, Bokar would “not allow that” and had authority to tell Chicago Town to “re-store or re-

organize their rebar.”

¶ 15 Bokar approved certain areas to store the rebar, which required communication with

Chicago Town. The standing agreement for subcontractor work included as a general condition

of all work performed: “the subcontractor shall store its materials within the locations as

approved by the contract.” In Bokar’s experience this was a “smaller” jobsite with limited space.

The project was small enough not to need assistant superintendents.

¶ 16 When Foley’s counsel asked Bokar about Builtech’s safety rules, “hypothetically, if

Chicago Town argued with you, *** your direction would trump Chicago Town’s?” Bokar

answered, “[a]bsolutely.” Bokar stated he had authority to inspect the rebar at any time. If he

inspected and found the rebar “tangled up,” he would have told Chicago Town. The excavating

company brought sand in a dump truck to use as backfill. If the excavators left dirt or “spoils”

(mounds of dirt) on the site, he would have required them to clean it up as improper and

potentially unsafe.

¶ 17 The rebar was delivered to the jobsite on May 1, 2015. Two Chicago Town employees,

Ismael Ramirez, a carpenter, and Juan Alfaro, a laborer, and others moved the rebar from the

-4- No. 1-18-0941

delivery spot to a spot closer to the building. They tried to stack the rebar so that it would not

tangle.

¶ 18 Bokar did not see Foley lifting rebar on May 21, nor did he see Foley hurt himself. Foley

told Bokar he “twinged” his back. Bokar had him fill out an incident report form.

¶ 19 Michael Chapman Deposition

¶ 20 Michael Chapman, the owner and president of Chicago Town, testified that he

decided where to store the rebar on the jobsite but Bokar had the authority to tell Chapman to

move the rebar or to stop work if necessary. Sometime between May 4 and May 15, Ramirez,

Alfaro, and another carpenter moved and restacked the rebar.

¶ 21 Jonathan Ribskis Deposition

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Aguirre v. Turner Construction Co.
501 F.3d 825 (Seventh Circuit, 2007)
Martens v. MCL Construction Corp.
807 N.E.2d 480 (Appellate Court of Illinois, 2004)
Pestka v. Town of Fort Sheridan Company, LLC
862 N.E.2d 1044 (Appellate Court of Illinois, 2007)
Bokodi v. Foster Wheeler Robbins, Inc.
728 N.E.2d 726 (Appellate Court of Illinois, 2000)
Olinger v. Great Atlantic & Pacific Tea Co.
173 N.E.2d 443 (Illinois Supreme Court, 1961)
Grillo v. Yeager Construction
900 N.E.2d 1249 (Appellate Court of Illinois, 2008)
Cochran v. George Sollitt Construction Co.
832 N.E.2d 355 (Appellate Court of Illinois, 2005)
Nowak v. Coghill
695 N.E.2d 532 (Appellate Court of Illinois, 1998)
Mort v. Walter
457 N.E.2d 18 (Illinois Supreme Court, 1983)
Tomczak v. Planetsphere, Inc.
735 N.E.2d 662 (Appellate Court of Illinois, 2000)
Weather-Tite, Inc. v. University of St. Francis
909 N.E.2d 830 (Illinois Supreme Court, 2009)
Robidoux v. Oliphant
775 N.E.2d 987 (Illinois Supreme Court, 2002)
Ward v. K Mart Corp.
554 N.E.2d 223 (Illinois Supreme Court, 1990)
Martinez v. Mobil Oil Corp.
694 N.E.2d 639 (Appellate Court of Illinois, 1998)
Larson v. Commonwealth Edison Co.
211 N.E.2d 247 (Illinois Supreme Court, 1965)
Maggi v. RAS Development, Inc.
2011 IL App (1st) 091955 (Appellate Court of Illinois, 2011)
Fonseca v. Clark Constuction Group, LLC
2014 IL App (1st) 130308 (Appellate Court of Illinois, 2014)
Lederer v. Executive Construction, Inc.
2014 IL App (1st) 123170 (Appellate Court of Illinois, 2014)
Wilkerson v. Paul H. Schwendener, Inc.
884 N.E.2d 208 (Appellate Court of Illinois, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
2019 IL App (1st) 180941, Counsel Stack Legal Research, https://law.counselstack.com/opinion/foley-v-builtech-construction-inc-illappct-2019.