Larson v. Commonwealth Edison Co.

211 N.E.2d 247, 33 Ill. 2d 316, 1965 Ill. LEXIS 249
CourtIllinois Supreme Court
DecidedSeptember 29, 1965
Docket38637
StatusPublished
Cited by255 cases

This text of 211 N.E.2d 247 (Larson v. Commonwealth Edison Co.) is published on Counsel Stack Legal Research, covering Illinois Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Larson v. Commonwealth Edison Co., 211 N.E.2d 247, 33 Ill. 2d 316, 1965 Ill. LEXIS 249 (Ill. 1965).

Opinion

* Mr. Justice Daily

delivered the opinion of the court:

Based upon a claimed violation of the Structural Work Act, more commonly known as the Scaffold Act, (Ill. Rev. Stat. 1957, chap. 48, pars. 60-69,) the plaintiff, Stanley Larson, brought this action in the circuit court of Cook County against Commonwealth Edison Company and A. Kolflat, the latter doing business as Sargent & Lundy, to recover for personal injuries sustained when a scaffold on which plaintiff was working broke and fell. The trial court directed a verdict and judgment for defendant Sargent & Lundy, and a jury returned a verdict for defendant Edison upon which judgment was entered. On appeal by plaintiff both judgments were affirmed by the Appellate Court. (48 Ill. App. 2d 349.) We have granted plaintiff’s petition for leave to appeal and, in addition, have permitted the filing of briefs by amici curiae.

Factual background shows that in November, 1955, Edison commenced the remodeling and rehabilitation of an electric generating plant it owned and operated in the city of Chicago. The plant consisted of several buildings, occupying an area of three city blocks, and the project entailed the removal of old equipment, cleaning out the interior of the buildings to the walls, and the installation of new equipment. To provide for continued plant operation, the work was accomplished in a progressive fashion and was done in “units.” For example, prior to the removal of old turbines from Unit 8, new turbines were installed in Unit 7 and, before the work progressed to Unit 8, a temporary barricade or partition was erected between the two units so that demolition in Unit 8 could proceed without damaging what had been accomplished in Unit 7.

Edison entered into from 70 to 80 contracts with numerous contractors, each of whom was to perform specific work on the over-all project. The majority of the contracts were prepared by Sargent & Lundy, (hereinafter referred to as Sargent) a firm of consulting engineers specializing in the design of electrical generating stations, as were the work plan, structural designs, and specifications used in the construction work. These contracts specifically required the contractors to comply with the provisions of the Scaffold Act.

Plaintiff’s employer, Paschen, had a contract for the work in Unit 7, one provision of which stated: “The work shall be done under the general supervision and to the satisfaction of owner’s Station Construction Department * * The contract also obligated Paschen to perform additional work as directed by Edison and, in accordance therewith, a “purchase order” was drawn by Edison whereby Paschen was directed to erect the barricade between Units 7 and 8. By the terms of the purchase order, Paschen was to: “Furnish all labor, materials, tools and equipment required to install preliminary structural work for Unit No. 8, Crawford Station, as directed by the Station Construction Department, and in accordance with drawings to be issued by Sargent & Lundy.” To aid in the construction of the barricade, scaffolds were erected by Paschen employes and it was one of such scaffolds which broke, causing plaintiff to be thrown to the floor. As may be seen in greater detail from the opinion of the Appellate Court, (48 Ill. App. 2d 349,) it is undisputed that the scaffold did not comply with rules promulgated by the Industrial Commission to implement the statute, and that plaintiff, who had no part in the erection of the scaffold, was injured as a direct result of such noncompliance.

Apart from intermittent visits by its chief engineer, Sargent had no personnel working at that construction site. However, six employees of Edison, all members of its Station Construction Department, were on the job at all times. According to one of the group, they exercised no control over the work, but merely inspected to see that the terms and specifications of the contracts were complied with. So far as the barricades were concerned, the same witness stated that the scope of their inspection did not extend to the kind or safety of the scaffold employed, but only to a determination of whether Edison “got the type of barricade specified.” Representatives of Edison’s Safety Department also visited the site periodically, and while their primary concern was the safety of Edison’s operating personnel still on the premises, it appears they could make, but not enforce, safety suggestions to the contractors and their employees. Weekly work progress reports were compiled by Edison and, adhering to a long practice between the two firms for many years, copies of the reports were forwarded to Sargent. In addition weekly or bi-weekly meetings, presided over by Edison, were held to co-ordinate the sequence of the work, and were attended by representatives of all the contractors and by a representative of Sargent.

Although there is general accord between the other participants to the appeal that both Edison and Sargent may be sued as' persons potentially having duties under the Scaffold Act, it is the contention of one amicus curiae, based principally on Breton v. Levinson, (1917), 207 Ill. App. 406, that we should discard all prior decisions and reconstrue the act as meaning that only the person or persons who actually erect a scaffold are subject to duty and liability under its terms. We see no beneficial purpose to be served by an extended discussion of this proposal. Suffice it to say, first, that such a construction was rejected, in principle at least, in Gannon v. Chicago, Milwaukee, St. Paul and Pacific Railway Co. 22 Ill.2d 305, after an exhaustive analysis of the statute and prior decisions; and second, that when sections 1 and 9 of the act are read together, (Ill. Rev. Stat. 1957, chap. 48, pars. 60 arid 69,) the construction contended for cannot be sustained. (See also: Kennerly v. Shell Oil Co. 13 Ill.2d 431.) Moreover, the legislature has apparently agreed with our interpretation of the act, since it has not seen fit to nullify or limit such construction by amending the statute.

The principal controversy between plaintiff and defendant Edison is whether the trial court erred when, over plaintiff’s objection, it instructed the jury as follows: “The Court instructs the jury that the plaintiff is not entitled to recover damages under the provisions of the Structural Work Act unless he has proven by a preponderance, or greater weight of the evidence, that the defendant, Commonwealth Edison Company, had charge of the work by retaining control and supervision of such work being performed by Paschen Contractors, Inc.” (Emphasis added.) The controlling section of the statute, which is section 9, makes no mention of either the retention or exercise of control and supervision, but imposes a duty of compliance, and liability for either wilful violation or a failure to comply with the terms of the act, upon “any owner * * * having charge of the erection * * * [or] alteration * * * of any building * * * or other structure * * Ill. Rev. Stat. 1957, chap. 48, par. 69. (Emphasis added.)

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Neisendorf v. Abbey Paving & Sealcoating Co.
2024 IL App (2d) 230209 (Appellate Court of Illinois, 2024)
Neisendorf v. Abbey Paving & Sealcoating Co., Inc.
2024 IL App (2d) 230209-U (Appellate Court of Illinois, 2024)
People v. Taylor
2021 IL App (5th) 180295-U (Appellate Court of Illinois, 2021)
Lederer v. Executive Construction, Inc.
2014 IL App (1st) 123170 (Appellate Court of Illinois, 2014)
Cain v. Contarino
2014 IL App (2d) 130482 (Appellate Court of Illinois, 2014)
Jones v. DHR Cambridge Homes
Appellate Court of Illinois, 2008
Jones v. DHR Cambridge Homes, Inc.
885 N.E.2d 330 (Appellate Court of Illinois, 2008)
Aguirre v. Turner Construction Co.
501 F.3d 825 (Seventh Circuit, 2007)
Cochran v. George Sollitt Construction Co.
Appellate Court of Illinois, 2005
Martens v. MCL Construction Corp.
807 N.E.2d 480 (Appellate Court of Illinois, 2004)
Moss v. Rowe Construction Co.
Appellate Court of Illinois, 2003
Bieruta v. Klein Creek Corp.
Appellate Court of Illinois, 2002
Noble, Robert v. United States
Seventh Circuit, 2000
Bokodi v. Foster Wheeler Robbins, Inc.
728 N.E.2d 726 (Appellate Court of Illinois, 2000)
Rangel v. Brookhaven Constructors, Inc.
Appellate Court of Illinois, 1999
Axen v. Ockerlund Construction Co.
666 N.E.2d 693 (Appellate Court of Illinois, 1996)
Cromer v. Joseph Behr & Sons, Inc.
845 F. Supp. 572 (N.D. Illinois, 1994)
Manisca v. Rakstang Associates, Inc.
628 N.E.2d 408 (Appellate Court of Illinois, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
211 N.E.2d 247, 33 Ill. 2d 316, 1965 Ill. LEXIS 249, Counsel Stack Legal Research, https://law.counselstack.com/opinion/larson-v-commonwealth-edison-co-ill-1965.