Lederer v. Executive Construction, Inc.

2014 IL App (1st) 123170
CourtAppellate Court of Illinois
DecidedSeptember 2, 2014
Docket1-12-3170
StatusUnpublished
Cited by1 cases

This text of 2014 IL App (1st) 123170 (Lederer v. Executive Construction, Inc.) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lederer v. Executive Construction, Inc., 2014 IL App (1st) 123170 (Ill. Ct. App. 2014).

Opinion

2014 IL App (1st) 123170 No. 1-12-3170 Opinion filed August 29, 2014 FIFTH DIVISION ______________________________________________________________________________

IN THE

APPELLATE COURT OF ILLINOIS

FIRST DISTRICT

______________________________________________________________________________

ROGER LEDERER, ) Appeal from the Circuit Court ) of Cook County. ) Plaintiff-Appellant, ) ) v. ) No. 09 L 221 ) EXECUTIVE CONSTRUCTION, INC., ) ) The Honorable Defendant-Appellee and Third-Party Plaintiff ) Kathy M. Flanagan, ) Judge, presiding. (Midwest Interstate Electrical Construction Company, ) Defendants, and Alliance Drywall and Acoustical ) Company, Third-party Defendant). ) ______________________________________________________________________________

JUSTICE PALMER delivered the judgment of the court, with opinion. Presiding Justice Gordon and Justice McBride concurred in the judgment and opinion.

OPINION

¶1 Plaintiff, Roger Lederer, appeals the circuit court's July 26, 2012, grant of summary judgment in favor of defendant-appellee Executive Construction, Inc. (Executive). On appeal, Lederer contends that the circuit court erred in granting summary judgment because section 414 of the Restatement (Second) of Torts (Restatement (Second) of Torts § 414 (1965)) established a duty of reasonable care in the present case. Plaintiff argues that the undisputed facts established, 1-12-3170

as a matter of law, that the degree of control Executive exercised over the construction project imposed a duty of reasonable care upon Executive. Plaintiff also argues that, as a matter of law, a duty of reasonable care was imposed upon Executive as it had notice of the dangerous condition. For the reasons that follow, we reverse the circuit court's ruling and remand for further proceedings. ¶2 I. BACKGROUND 1 ¶3 Executive was the general contractor for the construction of an office space on several floors of an existing building located at 115 South LaSalle Street (the project) in Chicago, Illinois, for BMO Capital Markets (BMO). Executive subcontracted with Midwest Interstate Electrical Construction Company (Midwest) for the electrical work at the site. Executive also subcontracted with third-party defendant, Alliance Drywall and Acoustical Company (Alliance), for the drywall and acoustical ceiling work at the site. Plaintiff, a drywall taper employed by Alliance at the site, was working on the ceiling of a conference room on the thirty-seventh floor on July 22, 2008, which was his second day on the job. While performing the work, plaintiff stood on stilts to reach the ceiling, and he fell after allegedly tripping over an exposed and unguarded electrical conduit or pipe protruding from the floor in the conference room. ¶4 Following the accident, plaintiff filed a personal injury action against Executive and Midwest in 2009. Against Executive, plaintiff alleged negligence for failing to ensure that warning cones were placed over the electrical conduit, failing to remove construction debris from the area, failing to warn plaintiff about the conduit, allowing plaintiff to use stilts in performing the drywall work, failing to require the use of a scaffold, and otherwise failing to provide a safe workspace and follow job safety rules. Against Midwest, plaintiff alleged that it failed to place warning cones over the conduit, failed to remove construction debris, failed to warn plaintiff about the conduit, and failed to follow and enforce its own job safety rules. Executive and Midwest both filed third-party complaints against Alliance and counterclaims against plaintiff for contributory negligence. Executive filed a counterclaim for contribution against Midwest. ¶5 Executive moved for summary judgment pursuant to section 2-1005 of the Illinois Code of Civil Procedure (the Code) (735 ILCS 5/2-1005 (West 2010)) as to plaintiff's complaint. Executive argued that it owed no duty of care to plaintiff under section 414 of the Restatement

1 The factual allegations are drawn from the complaint, discovery documents filed in the circuit court, and briefing on the motion to dismiss and attached exhibits. -2- 1-12-3170

(Second) of Torts as it did not retain sufficient control over plaintiff's methods of work or operative details to impose such a duty, and it had no knowledge of the allegedly unsafe conditions. Plaintiff countered that the evidence showed that Executive retained supervisory control over the operative details of his work, had the authority to halt work being done in an unsafe manner and had notice that he was using stilts and of the unsafe conditions, and the use of stilts was prohibited by Executive's safety manual. In connection with the motion, Executive and plaintiff submitted the pertinent construction contracts, safety manuals, and other documentation, along with the deposition testimony of plaintiff and several individuals employed by the parties. ¶6 A. The Contracts and Safety Manuals Involved ¶7 Executive had a master contract with BMO that permitted Executive to subcontract portions of the work it did not customarily perform. In a letter that was included with the master contract attached to Executive's motion for summary disposition, Executive vice president Glenn Kamin set forth Executive's proposal for the project and wrote that the services that Executive would provide included "Project Control Coordination and Supervision." The letter indicated that Executive "controls construction activities closely. These activities include subcontractor supervision, quality of workmanship, sequencing of work, material deliveries, documentation of decisions, and adherence to the schedule." Further, the letter stated that the proposed cost the project included, among other things, "Full time site supervision," "Project Management," "First aid supplies & equipment," and "Safety program & OHSA compliance." ¶8 Executive and Alliance entered into a master subcontract agreement and a subcontract work order. The master subcontract agreement provided that Alliance "shall perform all work as authorized and described in Work Orders" and that "all work shall be performed in accordance with all OSHA Standards, Subcontractors' Safety Programs, [and] ECI's [Executive's] Safety Program." The subcontract further provided that Alliance "shall furnish all supervision, materials, plant, scaffolding, hoisting, tools, equipment, supplies and all other things necessary for the construction and completion of the work described in the specific project Work Order." Alliance agreed assume all the obligations and responsibilities that Executive had assumed toward BMO. Additionally, the subcontract required Alliance to "coordinate with other work and shall carefully examine other work, determine whether it is in fit, ready and suitable condition for the proper and accurate performance of the Work hereunder, use all means necessary to discovery any defects in such other work, and before proceeding with the Work

-3- 1-12-3170

hereunder, report promptly any such improper conditions and defects to ECI in writing and allow ECI a reasonable time to have such improper conditions and defects remedied." ¶9 The subcontract work order between Executive and Alliance set forth Alliance's scope of work for the project and authorized Alliance to provide "all labor, materials, tools, equipment and supervision required" to complete the work.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lederer v. Executive Construction, Inc.
2014 IL App (1st) 123170 (Appellate Court of Illinois, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
2014 IL App (1st) 123170, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lederer-v-executive-construction-inc-illappct-2014.