Lederer v. Executive Construction, Inc.

2014 IL App (1st) 123170
Appellate Court of Illinois·Decided October 21, 2014·No. 1-12-3170·Published·Cited by 8 cases

Opinion

Illinois Official Reports

Appellate Court

Lederer v. Executive Construction, Inc., 2014 IL App (1st) 123170

Appellate Court ROGER LEDERER, Plaintiff-Appellant, v. EXECUTIVE Caption CONTRUCTION, INC., Defendant-Appellee and Third-Party Plaintiff (Midwest Interstate Electrical Construction Company, Defendants, and Alliance Drywall and Acoustical Company, Third-Party Defendant).

District & No. First District, Fifth Division Docket No. 1-12-3170

Filed August 29, 2014

Held In an action for the injuries suffered by a drywall taper employed by a (Note: This syllabus subcontractor who tripped over some exposed and unprotected constitutes no part of the conduit protruding from the floor of the room where he was using opinion of the court but drywall stilts to work on the ceiling, the trial court’s entry of summary has been prepared by the judgment for defendant general contractor was reversed and the cause Reporter of Decisions was remanded, since there was sufficient evidence to show that for the convenience of defendant had more than a general right of supervision and was the reader.) potentially subject to liability under section 414 of the Restatement (Second) of Torts, defendant’s safety manual specifically prohibited the use of stilts by a subcontractor’s employees, and defendant had authority to stop unsafe work and order it remedied.

Decision Under Appeal from the Circuit Court of Cook County, No. 09-L-221; the Review Hon. Kathy M. Flanagan, Judge, presiding.

Judgment Reversed and remanded.

Counsel on Keith L. Young, of Chicago, for appellant. Appeal Franco & Moroney, LLC, of Chicago (Robert J. Franco, Christopher G. Beunik, and Christopher M. Cano, of counsel), for appellee.

Panel JUSTICE PALMER delivered the judgment of the court, with opinion. Presiding Justice Gordon and Justice McBride concurred in the judgment and opinion.

OPINION

¶1 Plaintiff, Roger Lederer, appeals the circuit court’s July 26, 2012, grant of summary judgment in favor of defendant-appellee Executive Construction, Inc. (Executive). On appeal, Lederer contends that the circuit court erred in granting summary judgment because section 414 of the Restatement (Second) of Torts (Restatement (Second) of Torts § 414 (1965)) established a duty of reasonable care in the present case. Plaintiff argues that the undisputed facts established, as a matter of law, that the degree of control Executive exercised over the construction project imposed a duty of reasonable care upon Executive. Plaintiff also argues that, as a matter of law, a duty of reasonable care was imposed upon Executive as it had notice of the dangerous condition. For the reasons that follow, we reverse the circuit court’s ruling and remand for further proceedings.

¶2 I. BACKGROUND1

¶3 Executive was the general contractor for the construction of an office space on several floors of an existing building located at 115 South LaSalle Street (the project) in Chicago, Illinois, for BMO Capital Markets (BMO). Executive subcontracted with Midwest Interstate Electrical Construction Company (Midwest) for the electrical work at the site. Executive also subcontracted with third-party defendant, Alliance Drywall and Acoustical Company (Alliance), for the drywall and acoustical ceiling work at the site. Plaintiff, a drywall taper employed by Alliance at the site, was working on the ceiling of a conference room on the thirty-seventh floor on July 22, 2008, which was his second day on the job. While performing the work, plaintiff stood on stilts to reach the ceiling, and he fell after allegedly tripping over an exposed and unguarded electrical conduit or pipe protruding from the floor in the conference room.

¶4 Following the accident, plaintiff filed a personal injury action against Executive and Midwest in 2009. Against Executive, plaintiff alleged negligence for failing to ensure that warning cones were placed over the electrical conduit, failing to remove construction debris

1

The factual allegations are drawn from the complaint, discovery documents filed in the circuit court, and briefing on the motion to dismiss and attached exhibits.

from the area, failing to warn plaintiff about the conduit, allowing plaintiff to use stilts in performing the drywall work, failing to require the use of a scaffold, and otherwise failing to provide a safe workspace and follow job safety rules. Against Midwest, plaintiff alleged that it failed to place warning cones over the conduit, failed to remove construction debris, failed to warn plaintiff about the conduit, and failed to follow and enforce its own job safety rules. Executive and Midwest both filed third-party complaints against Alliance and counterclaims against plaintiff for contributory negligence. Executive filed a counterclaim for contribution against Midwest.

¶5 Executive moved for summary judgment pursuant to section 2-1005 of the Illinois Code of Civil Procedure (the Code) (735 ILCS 5/2-1005 (West 2010)) as to plaintiff’s complaint. Executive argued that it owed no duty of care to plaintiff under section 414 of the Restatement (Second) of Torts as it did not retain sufficient control over plaintiff’s methods of work or operative details to impose such a duty, and it had no knowledge of the allegedly unsafe conditions. Plaintiff countered that the evidence showed that Executive retained supervisory control over the operative details of his work, had the authority to halt work being done in an unsafe manner and had notice that he was using stilts and of the unsafe conditions, and the use of stilts was prohibited by Executive’s safety manual. In connection with the motion, Executive and plaintiff submitted the pertinent construction contracts, safety manuals, and other documentation, along with the deposition testimony of plaintiff and several individuals employed by the parties.

¶6 A. The Contracts and Safety Manuals Involved

¶7 Executive had a master contract with BMO that permitted Executive to subcontract portions of the work it did not customarily perform. In a letter that was included with the master contract attached to Executive’s motion for summary disposition, Executive vice president Glenn Kamin set forth Executive’s proposal for the project and wrote that the services that Executive would provide included “Project Control Coordination and Supervision.” The letter indicated that Executive “controls construction activities closely. These activities include subcontractor supervision, quality of workmanship, sequencing of work, material deliveries, documentation of decisions, and adherence to the schedule.” Further, the letter stated that the proposed cost the project included, among other things, “Full time site supervision,” “Project Management,” “First aid supplies & equipment,” and “Safety program & OSHA compliance.”

Free access — add to your briefcase to read the full text and ask questions with AI

Lederer v. Executive Construction, Inc., 2014 IL App (1st) 123170 (Ill. Ct. App. 2014).

2014 IL App (1st) 123170 (Lederer v. Executive Construction, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Foley v. Builtech Construction, Inc.
2019 IL App (1st) 180941 (Appellate Court of Illinois, 2019)
LePretre v. Lend Lease Construction, Inc.
2017 IL App (1st) 162320 (Appellate Court of Illinois, 2017)
Carney v. Union Pacific R.R. Co.
2016 IL 118984 (Illinois Supreme Court, 2016)
Lederer v. Executive Construction, Inc.
2014 IL App (1st) 123170 (Appellate Court of Illinois, 2014)