Martens v. MCL Construction Corp.

807 N.E.2d 480, 347 Ill. App. 3d 303, 282 Ill. Dec. 856, 2004 Ill. App. LEXIS 164
Appellate Court of Illinois·Decided February 27, 2004·No. 1-02-1557·Published·Cited by 74 cases

Opinion

JUSTICE FITZGERALD SMITH

delivered the opinion of the court:

Plaintiff John Martens appeals the trial court’s order granting summary judgment for defendants MCL Construction Corporation (MCL) and Shelco Steel Works, Inc. (Shelco). Based on the dismissal of all plaintiffs claims, the trial court deemed moot Shelco’s motions for partial summary judgment, and to strike and dismiss plaintiffs strict products liability claim. Plaintiff argues the trial court erred in granting MCL and Shelco summary judgment, contending there was a genuine issue of material fact regarding whether those defendants owed plaintiff, an employee of an independent contractor, a duty of care pursuant to section 414 of the Restatement (Second) of Torts (Restatement (Second) of Torts § 414 (1965)). Plaintiff also seeks reinstatement of his strict products liability claim against Shelco. We affirm the judgment of the trial court.

BACKGROUND

The following facts are taken from the pleadings, depositions and affidavits. Plaintiff filed an amended complaint alleging (count I) defendants breached their duty to provide plaintiff a safe place to work by failing to provide fall protection. Plaintiff also alleged (count II) a strict products liability claim against Shelco, contending Shelco fabricated an unreasonably dangerous steel beam by adding stiffeners and failing to mark the beams to warn users of the presence of the stiffeners.

Plaintiff was an ironworker employed by F.K. Ketler Company (Ketler), an independent contractor, which was hired as part of a project to construct condominiums and single-family homes. MCL was the construction manager and hired Shelco to fabricate and erect steel for a multistory building. Shelco subcontracted Ketler to perform the actual steel erection work. On July 10, 1997, plaintiff fell from a steel beam and sustained injuries.

MCL president Dan McLean testified that MCL did not perform any construction work but, rather, hired qualified, union-licensed contractors who were in charge of how they performed their own work. MCL supervised only its own work — not the work of the subcontractors. The purpose of the contract between the owner and MCL was to satisfy the requirements of a lender, and the contract primarily addressed overhead costs MCL received from the owners. The contract between the owner and MCL consisted of multiple documents, including a 14-page agreement, a 24-page, 14-article general conditions document, and the drawings, specifications and addenda.

Only a few provisions of the general conditions document between the owner and MCL are relevant to the matters raised on appeal. Specifically, MCL was responsible for and had control “over construction means, methods, techniques, sequences and procedures and for coordinating all portions of the Work under the Contract, unless Contract Documents give other specific instructions concerning these matters.” MCL required subcontractors to be bound by the terms of the contract documents and to assume toward MCL all the obligations and responsibilities MCL assumed toward the owner and architect. MCL was “responsible for initiating, maintaining and supervising all safety precautions and programs in connection with the performance of the Contract.” Regarding safety, MCL would give notices and comply with applicable laws, ordinances, rules and regulations bearing on the safety of persons or property or their protection from damage, injury or loss; erect and maintain, as required by existing conditions and performance of the contract, reasonable safeguards for safety and protection; and designate a member of MCL at the site whose duty was to prevent accidents.

According to the contract between MCL and Shelco, Shelco was responsible for providing materials, equipment and labor with proper supervision of the steel fabrication and erection. Shelco warranted that it was familiar with and in compliance with all applicable laws, regulations and rulings, including Occupational Safety and Health Administration (OSHA) and workers’ compensation. Shelco agreed to abide by MCL’s directives, policies and procedures, including safety procedures. Shelco excluded from the contract responsibility for OSHA safety cables at the perimeter of mechanical openings in the floors and roofs and for maintaining such safety cables.

According to the subcontract between Shelco and Ketler, Ketler was responsible for furnishing the required field labor and facilities to unload and erect the structural steel in accord with the architect’s plans and specifications. Ketler was also responsible for OSHA safety cables at the floors and roofs. All applicable OSHA requirements were part of the subcontract, and the American Institute of Steel Construction (AISC) Code of Standard Practice applied except where overridden by project plans or specifications. The AISC, an association that sets forth guidelines for steel erection, is recognized in the industry as authoritative. According to the AISC Code, the fabricator was not responsible for erection safety if the structure was erected by others.

Ketler furnished a safety manual to MCL in accordance with the safety plan as part of the contract between MCL and Shelco. Ketler’s safety manual provided that those “working aloft on skeleton steel shall tie off their safety lines except when moving from one point to another.” Ketler’s safety manual also provided that the foreman has the greatest burden of responsibility for putting the safety rules into practice.

Plaintiff had been an ironworker since 1975 and had been on the job in question for about two months before he fell. He exclusively took his directions from Ketler foremen Bill Gaynor and John Kirincich. On the morning he fell, plaintiff was teamed up with Kirincich to land, position and connect steel bar joists to steel beams to form the decking between the ceilings and floors. They were at the top of the erected structural steel, which was the seventh floor, and decking was in place on the fifth floor. Plaintiff had attached a safety line or lanyard to his personal tool belt but was not tied off because he had to move freely as part of the job. Plaintiff was working in an interior bay of beams as opposed to the perimeter of the structural steel.

Penetrations in the webs of steel beams were common at a jobsite and allowed other trades to install utilities and ductwork through the penetrations. Because penetrations compromised the strength of a beam, pieces of steel called stiffeners were welded around the penetrations for reinforcement. Stiffeners surrounded the penetrations like a box and protruded about four inches beyond each side of the beam web and about one inch beyond each side of the beam flanges. Shelco shipped the beams to the jobsite with the penetrations and stiffeners prefabricated. There were no regulations or industry standards concerning marking the beams to indicate the presence of penetrations or stiffeners. Plaintiff knew penetrations and stiffeners were prevalent on beams throughout the job.

Plaintiff was standing on a beam that was bolted to columns and part of the structural skeleton of the building. As he waited for the next load of bar joists, he attempted to sit down and straddle the beam. However, when he lowered one foot onto the lower flange of the beam, his foot apparently hit a stiffener, which allegedly caused him to lose his balance.

Free access — add to your briefcase to read the full text and ask questions with AI

Martens v. MCL Construction Corp., 807 N.E.2d 480, 347 Ill. App. 3d 303, 282 Ill. Dec. 856, 2004 Ill. App. LEXIS 164 (Ill. Ct. App. 2004).

807 N.E.2d 480 (Martens v. MCL Construction Corp.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Lyons v. Wells
S.D. Illinois, 2024
Neisendorf v. Abbey Paving & Sealcoating Co.
2024 IL App (2d) 230209 (Appellate Court of Illinois, 2024)
Neisendorf v. Abbey Paving & Sealcoating Co., Inc.
2024 IL App (2d) 230209-U (Appellate Court of Illinois, 2024)
SCHUELER VS. AD ART, INC.
2020 NV 52 (Nevada Supreme Court, 2020)
Schueler v. Ad Art, Inc.
472 P.3d 686 (Court of Appeals of Nevada, 2020)
Donley v. Craig Properties, Inc.
2020 IL App (3d) 190336-U (Appellate Court of Illinois, 2020)
Snow v. Power Construction Co.
2017 IL App (1st) 151226 (Appellate Court of Illinois, 2017)
Snow v. Power Construction Co., LLC
2017 IL App (1st) 151226 (Appellate Court of Illinois, 2017)
Carney v. Union Pacific R.R. Co.
2016 IL 118984 (Illinois Supreme Court, 2016)
Rivers v. Central Illinois Arena Management, Inc.
129 F. Supp. 3d 643 (C.D. Illinois, 2015)
Dunning v. Dynegy Midwest Generation, Inc.
2015 IL App (5th) 140168 (Appellate Court of Illinois, 2015)
O'Gorman v. F.H. Paschen, S.N. Nielsen, Inc.
2015 IL App (1st) 133472 (Appellate Court of Illinois, 2015)
O'Gorman v. F.H. Paschen
2015 IL App (1st) 133472 (Appellate Court of Illinois, 2015)
Illini Environmental, Inc. v. The Environmental Protection Agency
2014 IL App (5th) 130244 (Appellate Court of Illinois, 2014)
Illini Environmental, Inc. v. The Environmental Protection Agency
2014 IL App (5th) 130244 (Appellate Court of Illinois, 2014)
Lederer v. Executive Construction, Inc.
2014 IL App (1st) 123170 (Appellate Court of Illinois, 2014)
Cain v. Contarino
2014 IL App (2d) 130482 (Appellate Court of Illinois, 2014)
Lee v. Six Flags Themes Parks, Inc.
2014 IL App (1st) 130771 (Appellate Court of Illinois, 2014)
Justin Time Transportation, LLC v. Harco National Insurance Co.
2014 IL App (5th) 130124 (Appellate Court of Illinois, 2014)