Snow v. Power Construction Co., LLC

2017 IL App (1st) 151226, 78 N.E.3d 587
CourtAppellate Court of Illinois
DecidedMay 4, 2017
Docket1-15-1226
StatusUnpublished
Cited by4 cases

This text of 2017 IL App (1st) 151226 (Snow v. Power Construction Co., LLC) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Snow v. Power Construction Co., LLC, 2017 IL App (1st) 151226, 78 N.E.3d 587 (Ill. Ct. App. 2017).

Opinion

2017 IL App (1st) 151226

FOURTH DIVISION May 4, 2017

No. 1-15-1226

JOHN T. SNOW, ) Appeal from the ) Circuit Court Plaintiff-Appellant, ) Cook County. ) v. ) ) No. 12 L 3597 POWER CONSTRUCTION COMPANY, LLC, an Illinois ) Limited Liability Company, THORNE ASSOCIATES, ) INC., an Illinois Corporation, and POWER ) CONTRACTING AND ENGINEERING ) Honorable CORPORATION, an Illinois Corporation, ) Eileen Brewer, ) Judge Presiding. Defendants-Appellees. )

JUSTICE McBRIDE delivered the judgment of the court, with opinion. Presiding Justice Ellis and Justice Burke concurred in the judgment and opinion.

OPINION

¶1 Plaintiff John T. Snow filed a negligence action against defendants Power Construction

Company, LLC (PCC), Power Engineering and Contracting Corporation (PCEC) (collectively

Power), and Thorne Associates, Inc. (Thorne), after he was injured when several sheets of

drywall fell on him while at a construction site. Plaintiff was employed by third-party defendant,

Professionals Associated Construction Layout & Survey Co., Ltd. (Professionals), as a surveyor

and was on the site in his professional capacity. The trial court granted summary judgment in

favor of PCC, PCEC, and Thorne.

¶2 Plaintiff appeals, arguing that the trial court erred in (1) granting summary judgment

because there was a material question of fact regarding the stacking of the drywall and the

responsibility for safety of persons on the jobsite, (2) ruling that reliance on an alleged custom No. 1-15-1226

and practice could make an injury unforeseeable as a matter of law; (3) striking portions of the

affidavits of plaintiff and Richard Hislop tendered in response to the motions for summary

judgment, and (4) quashing the notice of deposition for John Karp, president of PCC.

¶3 In May 2010, Alexian Brothers Health System (Alexian), as the owner, entered into a

contract with PCEC, as the construction manager, for the construction of the new children’s

hospital and bed tower (bed tower site) at St. Alexius Medical Center (St. Alexius) in Hoffman

Estates, Illinois. In May 2011, PCEC entered into a project specific agreement with Professionals

to perform surveying work at the bed tower site. A master subcontract agreement between PCC

and Professionals, from October 2004, governed the project specific agreement and was

incorporated by reference. Also in May 2011, PCEC entered into a project specific agreement

with Thorne to perform framing and drywall assembly at the bed tower site. A master

subcontract agreement between PCC and Thorne, dated November 2003, governed and was

incorporated by reference.

¶4 As part of Thorne’s subcontract, it was to construct a temporary corridor connecting the

emergency room of the hospital to the new construction. On June 29, 2011, Thorne completed its

installation of drywall in the temporary corridor. At the end of the work day, Thorne’s

employees vertically stacked approximately 14 sheets, 4 by 8 feet high, of leftover drywall near

the entrance to the corridor. The next morning, on June 30, 2011, plaintiff came to the bed tower

site to check his previously placed benchmarks in the corridor. Plaintiff believed one of his

benchmarks was behind the stacked drywall. He then moved the stack toward himself to check

for his benchmark, but the stack continued to move and fell forward. Plaintiff was struck on his

right leg and trapped under the drywall. He immediately sought care at St. Alexius.

¶5 Plaintiff initially filed his negligence action in April 2012. In December 2012, plaintiff

filed his second amended complaint with one count directed at each of the defendants. The

allegations against PCC and PCEC are identical. The complaint asserts that both PCC and PCEC

were the general contractor for a project at the east pavilion of St. Alexius. Both PCC and PCEC

retained some control over the safety of the work on the project. PCC and PCEC each had a duty

to exercise that control with ordinary care. PCC and PCEC were individually guilty of one or

more negligent and careless acts or omissions: (1) caused drywall to be stacked or stored in such

a manner as to easily topple over; (2) allowed drywall to be stacked or stored in such a way and

in such a manner as to be easily tipped or toppled over; (3) failed to brace drywall stacked in a

vertical manner when it knew or should have known that drywall so stored or stacked could

easily tip over, causing injury; (4) failed to move, alter, or correct drywall stacked or stored in an

unsafe manner or direct that drywall so stacked or stored be moved, braced, or corrected; (5)

scheduled work of the subcontractor Professionals such that its employees would have to move

or disturb stacked or stored drywall, and (6) failed to assure that the drywall was stacked, racked,

blocked, interlocked, or otherwise secured to prevent sliding, falling, or collapse. As a result of

one or more of these acts or omissions, the vertically stacked drywall fell and struck plaintiff,

trapping him underneath and causing injury to his back and legs. As a direct and proximate result

of said accident, plaintiff has experienced and will continue to experience pain, suffering,

disability, loss of normal life, and lost income.

¶6 The third count of the complaint pled the following allegations against Thorne. Thorne

was a drywall subcontractor at the St. Alexius site, and it stacked, moved, and stored drywall,

specifically the drywall involved in the accident which injured plaintiff. Thorne had a duty to use

due care in its stacking, storage, and moving of drywall so as not to cause an unsafe condition

which might injure plaintiff and other employees on the project. Thorne was guilty of one or

more negligent and careless acts or omissions: (1) stored or stacked drywall in an area that was

neither safe nor authorized; (2) caused drywall to be stacked or stored in a manner such that

plaintiff could move or dislodge it; (3) failed to brace, band, or secure the drywall in such a

manner that it would not tip or fall; (4) improperly stacked the drywall; and (5) was otherwise

careless and negligent. As a result of one or more of these acts or omissions, the vertically

stacked drywall fell and struck plaintiff, trapping him underneath and causing injury to his back

and legs. As a direct and proximate result of said accident, plaintiff has experienced and will

continue to experience pain, suffering, disability, loss of normal life, and lost income.

¶7 The parties engaged in lengthy discovery, which included all relevant contracts as well as

several depositions of employees of PCC, PCEC, Thorne, and Professionals. The contract

between Alexian and PCEC included the following provisions in the general conditions of the

contract for construction.

¶8 Article 1.1.3 detailed the work under the contract.

“The term ‘Work’ means the construction and services required by

the Contract Documents, whether completed or partially

completed, and included all other labor, materials, equipment and

services provided or to be provided by the Contractor to fulfill the

Contractor’s obligations. The Work may constitute the whole or a

part of the Project. The Work shall also consist of labor, materials,

equipment and services provided or to be provided by

Subcontractors, Sub-subcontractors, material suppliers or any other

entity for whom the Contractor is responsible under or pursuant to

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bardhan v. Northwestern Memorial Hospital
2026 IL App (1st) 240371-U (Appellate Court of Illinois, 2026)
Fowler v. Ill. Sports Facilities Auth. & Chi. White Sox, Ltd.
338 F. Supp. 3d 822 (E.D. Illinois, 2018)
Snow v. Power Construction Co.
2017 IL App (1st) 151226 (Appellate Court of Illinois, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
2017 IL App (1st) 151226, 78 N.E.3d 587, Counsel Stack Legal Research, https://law.counselstack.com/opinion/snow-v-power-construction-co-llc-illappct-2017.