Grillo v. Yeager Construction

900 N.E.2d 1249, 387 Ill. App. 3d 577, 326 Ill. Dec. 1002, 2008 Ill. App. LEXIS 1332
CourtAppellate Court of Illinois
DecidedDecember 31, 2008
Docket1-07-2335
StatusPublished
Cited by28 cases

This text of 900 N.E.2d 1249 (Grillo v. Yeager Construction) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Grillo v. Yeager Construction, 900 N.E.2d 1249, 387 Ill. App. 3d 577, 326 Ill. Dec. 1002, 2008 Ill. App. LEXIS 1332 (Ill. Ct. App. 2008).

Opinion

JUSTICE QUINN

delivered the opinion of the court:

Plaintiff, Anthony Grillo, suffered injuries when he fell from scaffolding while performing masonry work on the construction of a new house for Sohail (a/k/a Sam) and Rubina Shakir in Northbrook, Illinois. Plaintiff filed a complaint at law against the Shakirs and defendant, Yeager Construction, alleging common-law negligence. In his complaint, plaintiff alleged that defendant was the general contractor of the construction site and that David Yeager was an employee or agent of defendant. Prior to trial, the circuit court granted summary judgment in favor of the Shakirs and also dismissed defendant’s contribution counterclaim against the Shakirs. Following a trial, the jury returned a verdict in favor of plaintiff and assessed plaintiffs damages at $1,834,496. On appeal, defendant contends that: (1) the circuit court erred in denying its motion for judgment notwithstanding the verdict (judgment n.o.v.) where plaintiff failed to establish a prima facie case of negligence; (2) defendant is entitled to a new trial due to various errors committed by the circuit court; and (3) the circuit court erred in entering summary judgment for the Shakirs on defendant’s contribution counterclaim against them. For the following reasons, we affirm.

I. Background

At trial, plaintiff testified that he had over 30 years of masonry experience. Plaintiff testified that he first learned of the Shakir residential construction project in August 2001, when he received a telephone call from David Yeager at Yeager Construction. Plaintiff testified that he met with David at the construction site in North-brook, Illinois, to negotiate a price for masonry work. Plaintiff met with David on his first and second visits to the construction site, and they orally agreed to a contract price during plaintiffs third visit to the site. Plaintiff testified that he asked David, “Who is going to pay me?” and “[W]ho is guaranteeing the money?” Plaintiff testified that David replied, “[N]ot me. Yeager Construction.” Plaintiff testified that he saw vehicles with the Yeager Construction logo at the construction site. Plaintiff testified that to get paid, he submitted his invoices to David, but he received checks from the Shakirs.

Plaintiff testified that his work at the construction site included building chimneys and all of the brick around the outside of the house. David informed plaintiff that the house was to be completed before Christmas and plaintiff testified that he was going to be able to complete his work on time if the general contractor made sure he was paid and made sure all of the backfill on the site was done before plaintiff performed his outside masonry work. Plaintiff explained that backfilling entailed placing dirt back around the foundation, nearly level with the ground, after the foundation was built. Plaintiff testified that backfilling is important for the building of scaffolding and the safety of masons and everyone else at the construction site. Plaintiff testified that he started with two employees on the construction site, which increased to seven employees in order to complete the work by winter. Plaintiff also testified that his employees built the scaffold and he supervised them.

Plaintiff testified that he spoke with David about open holes and trenches on the construction site and asked David to backfill from “day one” and every day thereafter for two months. Toward the end of October 2001, plaintiff and his employees finished all of the ground-level brick work and needed to use a scaffold to work up higher on the house. Plaintiff was laying bricks and supervised his employees as they built the scaffold. Plaintiff testified that he owned or rented the scaffolding and no one, including David, told him how to erect the scaffold. Plaintiff testified that sometimes he would be told to stop what he was doing and to start working on something else. Plaintiff testified that he observed the ground conditions at the time the scaffold was erected. Plaintiff observed that the back two legs of the scaffold were placed on cinder blocks due to the open holes at the construetion site. Plaintiff testified that he is familiar with Occupational Safety and Health Administration (OSHA) regulations and that setting up a scaffold on cinder blocks violated OSHA regulations and construction industry custom and practice. Plaintiff testified that after the scaffold was erected, the job was stopped for a week. Plaintiff testified that he would not be allowed on the site during that time and decided to address the scaffold issue when he returned.

On October 29, 2001, plaintiff returned to the construction site and told his employees that he did not like the way the scaffold was erected because the scaffold was partially on cinder blocks and the scaffold was not complete without guardrails. Plaintiff testified that David was having a meeting in front of the house, and plaintiff made a “smart remark” to him by “thanking” him for the backfilling that had not been done. Plaintiff testified that he made the sarcastic comment because he had been asking David to backfill the house since the start of the job, but had been “ignored over and over and over and over.” Plaintiff testified that David responded by calling him a “whiner” and walked away to his meeting. Plaintiff testified that he intended to speak with David again about the backfilling after David’s meeting.

Plaintiff testified that he was under pressure to complete his work, so he decided to climb the scaffold to take window measurements in order to proceed with his next phase of work. Plaintiff testified that he climbed the scaffold, about 12 feet off the ground, with just a tape measure on his belt. Plaintiff testified that the scaffold suddenly tipped upside down and he fell into an open hole, landing next to an exposed pipe inside of the hole. Plaintiff testified that after his fall, he saw that the scaffold was at an angle and no longer supported by the cinder blocks.

Plaintiff testified that he was taken by ambulance to the hospital, where he had back surgery and stayed for approximately three weeks. Plaintiff testified that after a year of rehabilitation, he was able to walk on his own. Plaintiff also testified that he continues to have tremendous pain and suffers from personality changes and nausea from the narcotic pain relievers he must take.

Dr. Jerry Bauer testified that he is a board-certified physician specializing in neurosurgery. Dr. Bauer treated plaintiff in the emergency room on October 31, 2001, and shortly thereafter performed surgery to relieve pressure on plaintiffs spinal cord. Dr. Bauer testified that plaintiffs surgery left him with permanent metal screws and plates in his lower spine, and permanent disability. Dr. Bauer testified that over time, plaintiff will likely develop additional degenerative changes above and below the fused area in his spine. Dr. Bauer testifled that he observed that plaintiff had recovered from his initial spinal cord injury. Dr. Bauer also testified that plaintiff was being treated with narcotics, which would preclude him from working.

Dr. Victoria Santucci testified via an evidence deposition, over defendant’s objection that the subjects of her testimony had not been disclosed before her evidence deposition was taken. Dr. Santucci testified that she is employed by Advanced Pain Centers, which focuses on pain management. Dr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

McNamara v. ICO Polymers North America
2023 IL App (1st) 220634-U (Appellate Court of Illinois, 2023)
Ellis v. ICC Group, Inc.
2022 IL App (1st) 211581-U (Appellate Court of Illinois, 2022)
Frieden v. Bott
2020 IL App (4th) 190232 (Appellate Court of Illinois, 2020)
Foley v. Builtech Construction, Inc.
2019 IL App (1st) 180941 (Appellate Court of Illinois, 2019)
Russo v. Corey Steel Co.
2018 IL App (1st) 180467 (Appellate Court of Illinois, 2018)
Jefferson v. Mercy Hospital & Medical Center
2018 IL App (1st) 162219 (Appellate Court of Illinois, 2018)
Gapinski v. Gujrati
2017 IL App (3d) 150502 (Appellate Court of Illinois, 2017)
People v. Donley
2015 IL App (4th) 130223 (Appellate Court of Illinois, 2015)
Lucasey v. Plattner
2015 IL App (4th) 140512 (Appellate Court of Illinois, 2015)
Graham v. Northwestern Memorial Hosp.
965 N.E.2d 611 (Appellate Court of Illinois, 2012)
Graham v. Northwestern Memorial Hospital
2012 IL App (1st) 102609 (Appellate Court of Illinois, 2012)
O'Connell v. Turner Construction Co.
949 N.E.2d 1105 (Appellate Court of Illinois, 2011)
O' Connell v. Turner Construction Company
Appellate Court of Illinois, 2011
Aguirre v. Turner Construction Co.
582 F.3d 808 (Seventh Circuit, 2009)
Pekin Insurance v. Hallmark Homes, L.L.C.
912 N.E.2d 250 (Appellate Court of Illinois, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
900 N.E.2d 1249, 387 Ill. App. 3d 577, 326 Ill. Dec. 1002, 2008 Ill. App. LEXIS 1332, Counsel Stack Legal Research, https://law.counselstack.com/opinion/grillo-v-yeager-construction-illappct-2008.