O' Connell v. Turner Construction Company

CourtAppellate Court of Illinois
DecidedMarch 25, 2011
Docket1-09-3442 Rel
StatusPublished

This text of O' Connell v. Turner Construction Company (O' Connell v. Turner Construction Company) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
O' Connell v. Turner Construction Company, (Ill. Ct. App. 2011).

Opinion

FIFTH DIVISION Opinion filed March 25, 2011 Modified upon denial of rehearing May 20, 2011

No. 1-09-3442

LAWRENCE O’CONNELL, ) Appeal from the ) Circuit Court of Plaintiff-Appellant, ) Cook County ) v. ) 05 L 6746 ) TURNER CONSTRUCTION COMPANY, a Corporation, ) Honorable ) Marcia Maras, Defendant-Appellee. ) Judge Presiding.

JUDGE EPSTEIN delivered the judgment of the court, with opinion.

Justices Joseph Gordon and Howse concurred in the judgment and opinion.

OPINION

Plaintiff, Lawrence O’Connell, was injured while working on a construction site. He appeals

the trial court’s grant of summary judgment in favor of Turner Construction Company, the

construction manager, claiming triable issues of fact on all of his claims, which are premised on

sections 414 and 343 of the Restatement. Restatement (Second) of Torts §§414, 343 (1965). For the

reasons below, we affirm.

BACKGROUND

In 2002 Grayslake Community High School District 127 (School District) hired Turner

Construction Company (Turner) as the construction manager for building a new high school campus.

Turner’s contract with the School District provided, inter alia:

“2.2.19 The Construction Manager shall receive bids, prepare bid analyses 1-09-3442

and make recommendations to the Owner for Owner’s award of Contracts or

rejections of bids.

2.2.20 The Construction Manager shall assist the Owner in preparing

Construction Contracts and advise the Owner in the acceptability of Subcontractors

and material suppliers proposed by Contractors.

***

2.3.12 The Construction Manager shall review the safety programs developed

by each of the Contractors for purposes of coordinating the safety programs with

those of the other Contractors. The Construction Manager’s responsibilities for

coordination of safety programs shall not extend to direct control over or charge of

the acts or omission of Contractors, Subcontractors, agents or employees of

Contractors or Subcontractors, or any other persons performing portions of the Work

and not directly employed the Construction Manager.

2.3.15 With respect to each Contractor’s own Work, the Construction

Manager shall not have control over or charge of and shall not be responsible for

construction means, methods, techniques, sequences or procedures, or for safety

precautions and programs in connection with the Work of each of the Contractors,

since these are solely the Contractor’s responsibility under the Contract of

Construction. The Construction Manager shall not be responsible for a Contractor’s

failure to carry out the Work in accordance with the respective Contract Documents.

2 1-09-3442

The Construction Manager shall not have control over or charge of acts or omissions

of the Contractors, Subcontractors, or their agents or employees, or any other persons

performing portions of the Work not directly employed by the Construction Manager.

2.3.28 Duties, responsibilities and limitations on authority of the Construction

Manager as set forth in the Contract Documents shall not be restricted, modified or

extended without written consent of the Owner, Construction Manager, Architects

and Contractors. Consent shall not be unreasonably withheld.”

A supplement to Turner’s contract modifies section 2.3.15 by adding “unless such failure could have

reasonably been discovered by the Construction Manager” to the second sentence in that paragraph,

inserting “and” between Owner and Construction Manager in paragraph 2.3.28, and deleting the last

sentence of that paragraph.

Waukegan Steel, a trade contractor hired by the School District for the project, subcontracted

its work to Linden Erectors (Linden), plaintiff’s employer. On July 17, 2003, plaintiff was injured

on the construction site while working with another Linden employee to unravel a large steel

perimeter cable using a motorized lift. Plaintiff was injured when the cable he was guiding went

slack and then taut, jerking him forward. Plaintiff’s “right foot fell in a little hole -- a rut,” his neck

snapped back, his hardhat fell off, and plaintiff fell to the ground, landing on his knees and hands.

He then stood up and continued to work. He did not seek immediate medical attention and

maintained his regular work schedule for two months thereafter.

On June 20, 2005, plaintiff filed the instant lawsuit against Turner, Linden, and others,

3 1-09-3442

seeking to recover damages for a cervical spine injury he allegedly sustained by being jerked to the

ground by the cable. Plaintiff’s claims against all but Turner were settled and dismissed. In January

2009 plaintiff filed a third amended complaint against Turner only, claiming negligence under

section 414 (count I) and premises liability under section 343 (count II). Plaintiff maintained Turner

was liable for his injuries because it “exercised significant operational and/or supervisor control over

the trade contractors, particularly with respect to safety, but also as to details of construction means

and methods.” The trial court disagreed and granted Turner summary judgment on plaintiff’s

complaint. Plaintiff appeals, claiming summary judgment was inappropriate because there are

genuine and material issues of fact with respect to each of his claims.

ANALYSIS

Summary judgment is intended to determine whether triable issues of fact exist and “is

appropriate where the pleadings, affidavits, depositions, admissions, and exhibits on file, when

viewed in the light most favorable to the nonmovant, reveal that there is no genuine issue as to any

material fact and that the movant is entitled to judgment as a matter of law.” Busch v. Graphic Color

Corp., 169 Ill. 2d 325, 333 (1996).

“A triable issue of fact exists where there is a dispute as to a material fact or where,

although the facts are not in dispute, reasonable minds might differ in drawing

inferences from those facts. Although summary judgment is an expeditious method

of disposing of a lawsuit, it is a drastic remedy and should be allowed only when the

right of the moving party is free and clear from doubt.” Petrovich v. Share Health

Plan of Illinois, Inc., 188 Ill. 2d 17, 31 (1999).

4 1-09-3442

Our review is de novo. Busch, 169 Ill. 2d at 333.

A. Turner Is Not Liable Under Section 414

Plaintiff maintains summary judgment on count I was inappropriate because the scope of

Turner’s control at the construction site is allegedly a material issue of fact and the determining

factor for liability under section 414. Control alone does not, however, trigger liability under section

414, which has “been recognized as expressing the law of Illinois.” Haberer v. Village of Sauget,

158 Ill. App. 3d 313, 319 (1987). Titled “Negligence in Exercising Control Retained by Employer,”

section 414 “is an exception to the general rule that an employer of an independent contractor is not

liable for the independent contractor’s acts or omissions.” Doe v. Big Brothers Big Sisters of

America, 359 Ill. App. 3d 684, 695 (2005). It provides:

“One who entrusts work to an independent contractor, but who retains the

control of any part of the work, is subject to liability for physical harm to others for

whose safety the employer owes a duty to exercise reasonable care, which is caused

by his failure to exercise his control with reasonable care.” (Emphasis added.)

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Martens v. MCL Construction Corp.
807 N.E.2d 480 (Appellate Court of Illinois, 2004)
Kravis v. Smith Marine, Inc.
324 N.E.2d 417 (Illinois Supreme Court, 1975)
Busch v. Graphic Color Corp.
662 N.E.2d 397 (Illinois Supreme Court, 1996)
Grillo v. Yeager Construction
900 N.E.2d 1249 (Appellate Court of Illinois, 2008)
Haberer v. Village of Sauget
511 N.E.2d 805 (Appellate Court of Illinois, 1987)
Petrovich v. Share Health Plan of Illinois, Inc.
719 N.E.2d 756 (Illinois Supreme Court, 1999)
Esser v. McIntyre
661 N.E.2d 1138 (Illinois Supreme Court, 1996)
Ivanov v. Process Design Associates
642 N.E.2d 711 (Appellate Court of Illinois, 1994)
Madden v. F.H. Paschen/S.N. Nielson, Inc.
916 N.E.2d 1203 (Appellate Court of Illinois, 2009)
Doe v. Big Brothers Big Sisters of America
834 N.E.2d 913 (Appellate Court of Illinois, 2005)
Collins v. Mid-America Bag Co.
535 N.E.2d 48 (Appellate Court of Illinois, 1989)
Wilkerson v. Paul H. Schwendener, Inc.
884 N.E.2d 208 (Appellate Court of Illinois, 2008)
Keating v. 68th & Paxton, L.L.C.
936 N.E.2d 1050 (Appellate Court of Illinois, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
O' Connell v. Turner Construction Company, Counsel Stack Legal Research, https://law.counselstack.com/opinion/o-connell-v-turner-construction-company-illappct-2011.