Ellis v. ICC Group, Inc.

2022 IL App (1st) 211581-U
CourtAppellate Court of Illinois
DecidedDecember 13, 2022
Docket1-21-1581
StatusUnpublished

This text of 2022 IL App (1st) 211581-U (Ellis v. ICC Group, Inc.) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ellis v. ICC Group, Inc., 2022 IL App (1st) 211581-U (Ill. Ct. App. 2022).

Opinion

2022 IL App (1st) 211581-U

NOTICE: This order was filed under Supreme Court Rule 23 and is not precedent except in the limited circumstances allowed under Rule 23(e)(1).

SECOND DIVISION December 13, 2022 No. 1-21-1581 ______________________________________________________________________________

IN THE APPELLATE COURT OF ILLINOIS FIRST DISTRICT ______________________________________________________________________________

JOSEPH ELLIS, ) ) Appeal from the Plaintiff-Appellant, ) Circuit Court of ) Cook County v. ) ) No. 17 L 10936 ICC GROUP, INC. d/b/a ILLINOIS CONSTRUCTORS ) CORPORATION and WBK ENGINEERING, LLC, ) The Honorable ) Rena Van Tine, Defendants ) Judge Presiding. ) (ICC Group, Inc., Defendant-Appellee). )

PRESIDING JUSTICE FITZGERALD SMITH delivered the judgment of the court. Justices Ellis and Cobbs concurred in the judgment.

ORDER

¶1 Held: Trial court’s granting of summary judgment in favor of defendant is reversed, where defendant owed a duty of care to the plaintiff under a negligence theory of premises liability and a genuine issue of material fact existed as to proximate cause.

¶2 The plaintiff, Joseph Ellis, appeals from the trial court’s granting of summary judgment in

favor of the defendant, ICC Group, Inc. d/b/a Illinois Constructors Corporation, on all counts of

his complaint for negligence. The basis of the trial court’s ruling was that the defendant, a general

contractor, owed no duty of care to the plaintiff, an employee of a subcontractor. The trial court No. 1-21-1581

also found that the element of proximate cause was not satisfied. We reverse and remand.

¶3 I. BACKGROUND

¶4 The summary judgment record discloses the following facts, which we set forth in the light

most favorable to the plaintiff, as the party opposing summary judgment. In 2015, the defendant

served as the general contractor on a project to modify a dam at the Busse Woods Reservoir, which

was part of a flood control project undertaken by the Village of Elk Grove Village (Village). This

project involved modification of the dam to install two new dam “gates” that could be operated

hydraulically via remote control. The work was divided into two stages, with a gate for the west

half of the dam being installed first, followed by the gate for the east half of the dam. To hold back

water and create a dry area where work could be performed, the defendant first built a temporary

cofferdam around the west side of the dam. A new concrete platform was built next, which was

approximately eight feet wide, and the dam gate was then installed on top of that platform. The

plaintiff’s fall occurred in the final days of the project’s first stage, when the west side cofferdam

was in place, the west platform was built, and the west gate had been installed.

¶5 The plaintiff was a commercial electrician employed by the electrical subcontractor on the

project, Lyons & Pinner (Lyons). On October 28, 2015, Lyons had assigned the plaintiff to help

Kevin McLaughlin, the Lyons electrician primarily working on the dam project, run electrical

wires through conduit to reach the dam. This was the plaintiff’s first day working at this site, and

the plan was for it to be his only day working there. The two men spent the morning pulling the

wires through the conduit, from the shed where it was stored toward the dam itself. They reached

the dam in mid-afternoon. There, wires had to be run to reach equipment on both the north and

south sides of the gate platform.

¶6 As stated, by this time the gate was in place atop the concrete platform. It had been installed

-2- No. 1-21-1581

eight days earlier, on October 20-21. From the evidence, we would describe the gate as a curved

steel structure, approximately five feet in height. Horizontally, it extends the full length of the

concrete platform, between vertical pillars on both sides that run to the bridge above. Neither of

the gate’s sides are flat. The gate’s north side (i.e., the side facing the reservoir) curves in a convex

fashion, while its south side is concave. Also, when upright, the gate is not fully perpendicular to

the platform below, but instead it rises at a southward angle.

¶7 The platform was accessible by a ramp that ran from the road above to the platform’s north

side, and this was how the plaintiff and McLaughlin first accessed the area. Once there, the plaintiff

found no evident method of access to reach the platform’s south side. He testified that he did not

ask McLaughlin for a method to cross over the gate but that McLaughlin told him that he had

simply been jumping across the gate and sliding down. McLaughlin testified that this was the

method he had seen other tradesman use to get back and forth over the gate since it had been

installed eight days earlier, although he had also seen workers use a ladder to climb up one of the

sides. The plaintiff saw McLaughlin grab the top of the rail, swing himself up, and flip over to the

other side. The plaintiff, then age 59, said that he was “too old for that” and did not believe it was

safe to jump over the gate. He saw that an extension ladder was on the south side of the gate, and

he asked McLaughlin if they needed a second ladder to get across it. McLaughlin answered yes,

that one was by the road. The plaintiff then went to the road and retrieved a second ladder. He

positioned it against the north side of the gate, adjacent to the ladder that was already positioned

against its south side. He then tied the two ladders together with mule tape, which is a heavy nylon

cord that the electricians used on the job site. He testified that the reason he tied the two ladders

together was because he thought this would make it safer for him to cross the gate using the two

ladders. McLaughlin did not help him do this, but he said that it was fine after seeing what the

-3- No. 1-21-1581

plaintiff was doing.

¶8 After that, the plaintiff successfully used the ladders to climb across the gate to the south side

of the platform, and he and McLaughin did work there for approximately one hour. After

completing his work, the plaintiff attempted to return to the north side by climbing the ladders to

cross the gate. As he was in the process of pivoting to transfer from the south-side ladder to the

north-side ladder, he lost his balance and fell backwards onto the concrete ledge and water below.

He sustained injuries, which apparently included a lumbar spine fracture requiring surgery,

impingement syndrome in his left rotator cuff, and a concussion.

¶9 Following this incident, the plaintiff filed a three-count complaint against the defendant.

Count I was a for general negligence. It alleged that the defendant had a duty to exercise reasonable

care in ensuring that the project site was a safe workplace for the plaintiff and others, and the

defendant breached that duty, inter alia, by allowing workers to use unsecured ladders to cross the

gate. Count II pled a claim under section 414 of the Restatement (Second) of Torts, alleging that

the defendant was negligent, inter alia, by failing to exercise control over job site activities with

reasonable care so as to provide the plaintiff and others with a safe place to work. Finally, count

III plead a claim of premises liability. It alleged that the defendant was negligent, inter alia, in

allowing an unsecured ladder to exist on the project site as the presumptive method of scaling the

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cannon v. Commonwealth Edison Co.
621 N.E.2d 52 (Appellate Court of Illinois, 1993)
Preze v. Borden Chemical, Inc.
782 N.E.2d 710 (Appellate Court of Illinois, 2002)
Grillo v. Yeager Construction
900 N.E.2d 1249 (Appellate Court of Illinois, 2008)
Clifford v. Wharton Business Group, L.L.C.
817 N.E.2d 1207 (Appellate Court of Illinois, 2004)
Deibert v. Bauer Bros. Const. Co., Inc.
566 N.E.2d 239 (Illinois Supreme Court, 1990)
Young v. Bryco Arms
821 N.E.2d 1078 (Illinois Supreme Court, 2004)
Madden v. F.H. Paschen/S.N. Nielson, Inc.
916 N.E.2d 1203 (Appellate Court of Illinois, 2009)
Simmons v. Garces
763 N.E.2d 720 (Illinois Supreme Court, 2002)
LaFever v. Kemlite Co.
706 N.E.2d 441 (Illinois Supreme Court, 1998)
Ward v. K Mart Corp.
554 N.E.2d 223 (Illinois Supreme Court, 1990)
Espinoza v. Elgin, Joliet & Eastern Railway Co.
649 N.E.2d 1323 (Illinois Supreme Court, 1995)
Lee v. Chicago Transit Authority
605 N.E.2d 493 (Illinois Supreme Court, 1992)
First Springfield Bank & Trust v. Galman
720 N.E.2d 1068 (Illinois Supreme Court, 1999)
O'Connell v. Turner Construction Co.
949 N.E.2d 1105 (Appellate Court of Illinois, 2011)
Lee v. Six Flags Themes Parks, Inc.
2014 IL App (1st) 130771 (Appellate Court of Illinois, 2014)
Bruns v. City of Centralia
2014 IL 116998 (Illinois Supreme Court, 2014)
Carney v. Union Pacific R.R. Co.
2016 IL 118984 (Illinois Supreme Court, 2017)
Heider v. DJG Pizza, Inc.
2019 IL App (1st) 181173 (Appellate Court of Illinois, 2019)
Shicheng Guo v. Kamal
2020 IL App (1st) 190090 (Appellate Court of Illinois, 2020)
Johnson v. Armstrong
2022 IL 127942 (Illinois Supreme Court, 2022)

Cite This Page — Counsel Stack

Bluebook (online)
2022 IL App (1st) 211581-U, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ellis-v-icc-group-inc-illappct-2022.