Ellis v. ICC Group, Inc.

2022 IL App (1st) 211581-U
Appellate Court of Illinois·Decided December 13, 2022·No. 1-21-1581·Unpublished

Opinion

2022 IL App (1st) 211581-U

NOTICE: This order was filed under Supreme Court Rule 23 and is not precedent except in the limited circumstances allowed under Rule 23(e)(1).

SECOND DIVISION

December 13, 2022

No. 1-21-1581

IN THE

APPELLATE COURT OF ILLINOIS FIRST DISTRICT

JOSEPH ELLIS, )

) Appeal from the

Plaintiff-Appellant, ) Circuit Court of ) Cook County

v. )

) No. 17 L 10936

ICC GROUP, INC. d/b/a ILLINOIS CONSTRUCTORS ) CORPORATION and WBK ENGINEERING, LLC, ) The Honorable ) Rena Van Tine,

Defendants ) Judge Presiding.

)

(ICC Group, Inc., Defendant-Appellee). )

PRESIDING JUSTICE FITZGERALD SMITH delivered the judgment of the court.

Justices Ellis and Cobbs concurred in the judgment.

ORDER

¶1 Held: Trial court’s granting of summary judgment in favor of defendant is reversed, where defendant owed a duty of care to the plaintiff under a negligence theory of premises liability and a genuine issue of material fact existed as to proximate cause.

¶2 The plaintiff, Joseph Ellis, appeals from the trial court’s granting of summary judgment in favor of the defendant, ICC Group, Inc. d/b/a Illinois Constructors Corporation, on all counts of his complaint for negligence. The basis of the trial court’s ruling was that the defendant, a general contractor, owed no duty of care to the plaintiff, an employee of a subcontractor. The trial court

also found that the element of proximate cause was not satisfied. We reverse and remand.

¶3 I. BACKGROUND

¶4 The summary judgment record discloses the following facts, which we set forth in the light most favorable to the plaintiff, as the party opposing summary judgment. In 2015, the defendant served as the general contractor on a project to modify a dam at the Busse Woods Reservoir, which was part of a flood control project undertaken by the Village of Elk Grove Village (Village). This project involved modification of the dam to install two new dam “gates” that could be operated hydraulically via remote control. The work was divided into two stages, with a gate for the west half of the dam being installed first, followed by the gate for the east half of the dam. To hold back water and create a dry area where work could be performed, the defendant first built a temporary cofferdam around the west side of the dam. A new concrete platform was built next, which was approximately eight feet wide, and the dam gate was then installed on top of that platform. The plaintiff’s fall occurred in the final days of the project’s first stage, when the west side cofferdam was in place, the west platform was built, and the west gate had been installed.

¶5 The plaintiff was a commercial electrician employed by the electrical subcontractor on the project, Lyons & Pinner (Lyons). On October 28, 2015, Lyons had assigned the plaintiff to help Kevin McLaughlin, the Lyons electrician primarily working on the dam project, run electrical wires through conduit to reach the dam. This was the plaintiff’s first day working at this site, and the plan was for it to be his only day working there. The two men spent the morning pulling the wires through the conduit, from the shed where it was stored toward the dam itself. They reached the dam in mid-afternoon. There, wires had to be run to reach equipment on both the north and south sides of the gate platform.

¶6 As stated, by this time the gate was in place atop the concrete platform. It had been installed

eight days earlier, on October 20-21. From the evidence, we would describe the gate as a curved steel structure, approximately five feet in height. Horizontally, it extends the full length of the concrete platform, between vertical pillars on both sides that run to the bridge above. Neither of the gate’s sides are flat. The gate’s north side (i.e., the side facing the reservoir) curves in a convex fashion, while its south side is concave. Also, when upright, the gate is not fully perpendicular to the platform below, but instead it rises at a southward angle.

¶7 The platform was accessible by a ramp that ran from the road above to the platform’s north side, and this was how the plaintiff and McLaughlin first accessed the area. Once there, the plaintiff found no evident method of access to reach the platform’s south side. He testified that he did not ask McLaughlin for a method to cross over the gate but that McLaughlin told him that he had simply been jumping across the gate and sliding down. McLaughlin testified that this was the method he had seen other tradesman use to get back and forth over the gate since it had been installed eight days earlier, although he had also seen workers use a ladder to climb up one of the sides. The plaintiff saw McLaughlin grab the top of the rail, swing himself up, and flip over to the other side. The plaintiff, then age 59, said that he was “too old for that” and did not believe it was safe to jump over the gate. He saw that an extension ladder was on the south side of the gate, and he asked McLaughlin if they needed a second ladder to get across it. McLaughlin answered yes, that one was by the road. The plaintiff then went to the road and retrieved a second ladder. He positioned it against the north side of the gate, adjacent to the ladder that was already positioned against its south side. He then tied the two ladders together with mule tape, which is a heavy nylon cord that the electricians used on the job site. He testified that the reason he tied the two ladders together was because he thought this would make it safer for him to cross the gate using the two ladders. McLaughlin did not help him do this, but he said that it was fine after seeing what the

plaintiff was doing.

¶8 After that, the plaintiff successfully used the ladders to climb across the gate to the south side of the platform, and he and McLaughin did work there for approximately one hour. After completing his work, the plaintiff attempted to return to the north side by climbing the ladders to cross the gate. As he was in the process of pivoting to transfer from the south-side ladder to the north-side ladder, he lost his balance and fell backwards onto the concrete ledge and water below. He sustained injuries, which apparently included a lumbar spine fracture requiring surgery, impingement syndrome in his left rotator cuff, and a concussion.

¶9 Following this incident, the plaintiff filed a three-count complaint against the defendant. Count I was a for general negligence. It alleged that the defendant had a duty to exercise reasonable care in ensuring that the project site was a safe workplace for the plaintiff and others, and the defendant breached that duty, inter alia, by allowing workers to use unsecured ladders to cross the gate. Count II pled a claim under section 414 of the Restatement (Second) of Torts, alleging that the defendant was negligent, inter alia, by failing to exercise control over job site activities with reasonable care so as to provide the plaintiff and others with a safe place to work. Finally, count III plead a claim of premises liability. It alleged that the defendant was negligent, inter alia, in allowing an unsecured ladder to exist on the project site as the presumptive method of scaling the dam gate while working on it, failing to ensure that the ladder was secure, allowing workers including the plaintiff to work on an unsecured ladder, failing to warn, and failing to discover and remedy the dangerous condition.

¶ 10 Following discovery, the defendant filed a motion for summary judgment. It argued that the evidence was insufficient to show that it had “retained control” over the work done by the Lyons electricians on the job site sufficient to impose on it a duty under section 414 of the Restatement

Free access — add to your briefcase to read the full text and ask questions with AI

Ellis v. ICC Group, Inc., 2022 IL App (1st) 211581-U (Ill. Ct. App. 2022).

2022 IL App (1st) 211581-U (Ellis v. ICC Group, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Stout v. Costco Wholesale Corp.
Appellate Court of Illinois, 2026