Dudevoire v. CSL Behring, Inc.

2021 IL App (3d) 190373-U
CourtAppellate Court of Illinois
DecidedMarch 15, 2021
Docket3-19-0373
StatusUnpublished

This text of 2021 IL App (3d) 190373-U (Dudevoire v. CSL Behring, Inc.) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dudevoire v. CSL Behring, Inc., 2021 IL App (3d) 190373-U (Ill. Ct. App. 2021).

Opinion

NOTICE: This order was filed under Supreme Court Rule 23 and is not precedent except in the limited circumstances allowed under Rule 23(e)(1).

2021 IL App (3d) 190373-U

Order filed March 15, 2021 ____________________________________________________________________________

IN THE

APPELLATE COURT OF ILLINOIS

THIRD DISTRICT

DAVID DUDEVOIRE, ) Appeal from the Circuit Court ) of the 21st Judicial Circuit, Plaintiff-Appellant, ) Kankakee County, Illinois. ) v. ) ) CSL BEHRING, LLC, a Foreign Limited ) Liability Company and MECHANICAL, INC., ) an Illinois Corporation, ) ) Defendants-Appellees. ) _______________________________________) Appeal No. 3-19-0373 ) Circuit No. 14-L-83 CSL BEHRING, LLC, ) ) Third Party Plaintiff-Cross Appellant, ) ) v. ) ) JAMES McHUGH CONSTRUCTION ) COMPANY, ) Honorable Adrienne Albrecht, ) Judge, Presiding. Third Party Defendant-Cross Appellee. ) _______________________________________) ) MECHANICAL, INC. ) ) Third Party Plaintiff-Cross Appellant, ) ) v. ) ) JAMES McHUGH CONSTRUCTION ) COMPANY and M&M SHEET METAL, INC., ) ) Third Party Defendants-Cross Appellees.) ____________________________________________________________________________

JUSTICE SCHMIDT delivered the judgment of the court. Presiding Justice McDade and Justice Lytton concurred in the judgment.

ORDER

¶1 Held: The trial court did not err when it granted defendants’ motions for summary judgment.

¶2 Plaintiff, David Dudevoire, appeals the trial court’s grant of defendants’, CSL Behring,

Inc. (CSL), and Mechanical, Inc. (Mechanical), motions for summary judgment. We affirm.

¶3 I. BACKGROUND

¶4 Dudevoire filed a complaint against CSL and Mechanical. The complaint arose from an

injury Dudevoire sustained while stripping concrete forms in the basement area of new

construction at CSL’s human blood plasma fractionation facility. As Dudevoire carried scrap wood

from the basement to the disposal area, he stepped onto a raised concrete pad, then slipped on a

piece of blue plastic that had been left on top of the concrete pad. The slip caused him to suffer a

knee injury. At the time of the injury, Dudevoire was employed by the general contractor for the

project, James McHugh Construction Company (McHugh).

¶5 Count I of the complaint alleged construction negligence under section 414 of the

Restatement (Second) of Torts in that CSL retained control of the means and methods on the

construction site through its superintendence of the construction site and hands-on enforcement of

the construction safety measures. Count II alleged a theory of premises liability in that CSL, as the

owner of the property, knew or should have known of the dangerous condition, failed to make a

-2- reasonable inspection of the area, failed to enforce its safety policies, and failed to remove the

tripping hazard in a timely fashion from the work area. Count III alleged that CSL was directly

negligent by failing to exercise reasonable care in the performance of its work at the construction

site.

¶6 Count IV of the complaint alleged that defendant, Mechanical, acted negligently in that its

agents left the blue plastic on the floor that caused Dudevoire’s injuries.

¶7 The parties completed written discovery during which the following facts were adduced.

Defendant, CSL, began a construction project to create a new addition to one of its buildings. The

project involved three contracts. The contract between CSL and McHugh, the subcontract between

McHugh and Mechanical, and the sub-subcontract between Mechanical and M&M.

¶8 The contract between CSL and McHugh provided that McHugh, “shall supervise and direct

the Work, using [McHugh’s] best skill and attention. [McHugh] shall be solely responsible for,

and have control over, construction means, methods, techniques, sequences and procedures and

for coordinating all portions of the Work under the Contract, unless the Contract Documents give

other specific instructions concerning these matters.” The prime contract further provided that

McHugh, “shall be responsible for inspection of portions of Work already performed to determine

that such portions are in proper condition to receive subsequent Work.” As to labor and materials,

McHugh was responsible for providing and paying for “labor, materials, equipment, tools,

construction equipment and machinery, water, heat, utilities, transportation, and other facilities

and services necessary for proper execution and completion of the Work.” In addition, McHugh

was required to designate an on-site superintendent responsible to prevent accidents to serve as

McHugh’s superintendent unless otherwise designated by McHugh in writing to CSL. McHugh

-3- was also responsible for “initiating, maintaining and supervising all safety precautions and

programs in connection with the performance of the Contract.”

¶9 McHugh entered into a subcontract with Mechanical. Mechanical undertook the initial

responsibility for both the HVAC pipe fitting and all stainless-steel ductwork. Mechanical then

subcontracted out all the stainless-steel ductwork to M&M. The contract required Mechanical to

abide by the terms set forth in the contract between McHugh and CSL.

¶ 10 The sub-subcontract between Mechanical and M&M provided as follows. M&M was to

provide the “labor materials, equipment, machinery or services” necessary to complete the

stainless-steel ductwork. Under the terms of the contract, Mechanical was not “obligated to notify

[M&M] when to begin, cease or resume work, or to superintend [M&M’s] so as to relieve [M&M]

of responsibility for any consequence of neglect or carelessness by [M&M] or those for whose acts

and omissions [M&M] is responsible.” The contract further provided that M&M had a specific

duty to “take all reasonable safety precautions with respect to [M&M]’s Work, and shall comply

with such safety measures and accident reporting procedures as may be initiated by [Mechanical]

or authorized third parties.” The contract provided that M&M also had the “primary responsibility

for compliance with applicable federal and state laws and regulations pertaining to workplace

safety, including but not limited to the Occupational Safety and Health Act.” This provision was

qualified in that “[Mechanical’s] authority to initiate safety measures shall not relieve [M&M] of

such responsibility.” Finally, the contract addressed M&M’s housekeeping responsibilities by

requiring that “[M&M] will clean up and haul off the premises, or to a place on the premises

specifically designated by [Mechanical], all debris occasioned by the Work done hereunder and

will leave the Project and premises clean and free of equipment, machinery, materials, temporary

-4- facilities and debris. Any trash, debris, or liquid that poses a possible threat of fire or safety shall

be removed from the premises immediately.”

¶ 11 Dudevoire testified at his deposition that at the time of the injury, he was removing wood

forms from the concrete pads that had been laid the previous week. He was injured on a Tuesday

morning. Dudevoire did not know if anyone had worked on Saturday or Sunday but believed the

plastic may have been left on the concrete pad the Friday before the accident. While walking with

the wood in his hands, he stepped on a blue plastic bag that had been left on a concrete pad. He

twisted his knee, which caused an injury. Dudevoire assumed the plastic was left by a Mechanical

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sorce v. Naperville Jeep Eagle, Inc.
722 N.E.2d 227 (Appellate Court of Illinois, 1999)
Bokodi v. Foster Wheeler Robbins, Inc.
728 N.E.2d 726 (Appellate Court of Illinois, 2000)
Calderon v. Residential Homes of America, Inc.
885 N.E.2d 1138 (Appellate Court of Illinois, 2008)
Reed v. Wal-Mart Stores, Inc.
700 N.E.2d 212 (Appellate Court of Illinois, 1998)
Madden v. F.H. Paschen/S.N. Nielson, Inc.
916 N.E.2d 1203 (Appellate Court of Illinois, 2009)
Robidoux v. Oliphant
775 N.E.2d 987 (Illinois Supreme Court, 2002)
Wind v. Hy-Vee Food Stores, Inc.
650 N.E.2d 258 (Appellate Court of Illinois, 1995)
Donoho v. O'Connell's, Inc.
148 N.E.2d 434 (Illinois Supreme Court, 1958)
Bruns v. City of Centralia
2014 IL 116998 (Illinois Supreme Court, 2014)
Mashal v. City of Chicago
2012 IL 112341 (Illinois Supreme Court, 2012)
Oshana v. FCL Builders
2012 IL App (1st) 101628 (Appellate Court of Illinois, 2012)
Carney v. Union Pacific R.R. Co.
2016 IL 118984 (Illinois Supreme Court, 2017)
LePretre v. Lend Lease Construction, Inc.
2017 IL App (1st) 162320 (Appellate Court of Illinois, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
2021 IL App (3d) 190373-U, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dudevoire-v-csl-behring-inc-illappct-2021.