Laka Tool & Stamping Co. v. United States

650 F.2d 270, 28 Cont. Cas. Fed. 81,396, 227 Ct. Cl. 468, 1981 U.S. Ct. Cl. LEXIS 274
CourtUnited States Court of Claims
DecidedMay 20, 1981
DocketNo. 425-78
StatusPublished
Cited by9 cases

This text of 650 F.2d 270 (Laka Tool & Stamping Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Laka Tool & Stamping Co. v. United States, 650 F.2d 270, 28 Cont. Cas. Fed. 81,396, 227 Ct. Cl. 468, 1981 U.S. Ct. Cl. LEXIS 274 (cc 1981).

Opinion

BENNETT, Judge,

delivered the opinion of the court:

This case comes before the court on the parties’ motions for rehearing and to amend judgment under Ct. Cl. Rule 151.1 Plaintiffs motion raises issues previously considered and decided. Nevertheless, it has been carefully reviewed [469]*469and is denied. Defendant’s motion is more troubling and difficult, however, and we consider it here at length. Nonetheless, defendant’s motion is also denied and we uphold our earlier result.

The facts in this case are fully set forth in our earlier opinion. Laka Tool and Stamping Co. v. United States, 226 Ct. Cl. 83, 639 F.2d 738 (1980). The case involved a contract to manufacture and deliver certain rifle magazines. The original specifications proved impossible of performance and were modified. Subsequently, plaintiff was unable to comply with even the modified specifications although they were found not to be impossible. Eventually plaintiff was terminated for default. It should be emphasized that plaintiffs eventual failure to perform was unrelated to the earlier impossible specifications. The court upheld the default as proper. However, the court held plaintiff entitled to recover those excess costs, if any, which plaintiff expended in attempting to comply with the original impossible specifications before modification. Since plaintiffs unexcused default was a breach, the court also allowed the Government’s counterclaim for the amount of all progress payments it had made to plaintiff during the course of the contract, subject, of course, to any offsetting recovery by plaintiff. Plaintiffs claim was remanded to the Armed Services Board of Contract Appeals to allow plaintiff to make a showing that it had indeed made expenditures in attempting to comply with the impossible specifications and the amount of such unreimbursed expenditures. Although that showing remains yet to be made, we assume for the purposes of this opinion that there were such expenditures in some amount.

Defendant now contends that plaintiff should not be entitled to recover anything since it was properly defaulted and never delivered any acceptable goods under the contract, citing Century Hone Div. of Desert Labs., ASBCA No. 18360, 78-1 BCA ¶ 12,990 (opinion by Trial Division recommending affirmance, filed Sept. 5, 1980, in Ct. Cl. No. 44-79) and A. C. Hoyle Co., ASBCA No. 15363, 71-2 BCA ¶ 9137. This is an entirely new contention. It was not made to the court when the case was previously before us, nor were these cases cited and our opinion therefore has no discus[470]*470sion of the matter since it was never made an issue. The trial judge, in his opinion, had specifically and expressly held that plaintiff would be able to recover damages because of the impossible specifications despite plaintiffs subsequent failure to perform. Defendant never challenged that portion of the trial judge’s opinion. Defendant does not indicate why it did not make this argument before. It cannot claim to have been unaware of the trial judge’s reasoning. Normally this would be sufficient grounds for denying a motion for reconsideration. Niagara Mohawk Power Corp. v. United States, 207 Ct. Cl. 594 (1976) (order on rehearing); Mason & Hanger-Silas Mason Co. v. United States, 207 Ct. Cl. 183, 523 F.2d 1384 (1975) (order on plaintiffs motion for reconsideration); General Electric Co. v. United States, 189 Ct. Cl. 116, 416 F.2d 1320 (1969). Nevertheless, since we consider the question an important and difficult one, we have decided to consider it on its merits.

We have here a case where both parties defaulted on their contractural obligations. Defendant was the first to default by supplying impossible specifications. Plaintiff defaulted later by failing to deliver conforming goods under the modified specifications although such failure was unrelated to defendant’s default. Defendant’s default injured plaintiff by causing it an out-of-pocket loss in the form of expenditures for efforts wasted because of the impossible specifications.2 Had plaintiff completed the contract, it would have been entitled to recover the contract price plus an equitable adjustment for the wasted work. Instead, plaintiff defaulted and the Government never received the use or benefit of any of plaintiffs work. The question is whether defendant can now escape liability for that injury. That is, in cases where the contractor’s work does not benefit defendant, is a contractor’s subsequent failure to perform, for reasons unrelated to an earlier default3 of defendant’s, a complete defense to the contractor’s earlier [471]*471arising claim based on defendant’s default? We hold that it is not a complete defense in all cases.

We decline to follow Century Hone, supra. The case does not bind us as there has been no decision therein by a panel of this court. In that case the contractor was terminated for default for failing to produce a machine that conformed to the Government’s specifications. The contractor was held to be entitled to no relief for 37 unspecified constructive changes on the ground that the default termination was proper and the contractor had contributed nothing of value to the Government. If the case is read to hold that no claims survive a contractor’s failure to perform under any and all circumstances, we find it too broad and decline to follow it. We express no opinion on whether or not the case reaches the correct result since in our view that would depend on facts not specified in the opinion.

Although we hold that a contractor’s failure to perform is not a complete defense to an earlier arising claim against the Government in all cases, it is difficult to fashion a rule of universal application at this point, the issue being one of first impression. Accordingly, we are left to delineate the factors which we feel make plaintiffs recovery just and equitable in the instant case. We do so without holding that all these factprs are necessary or that any one is determinative. We keep that open to be resolved by later cases. The first factor we note is that plaintiffs default was not willful and deliberate. Rather it came only after bona fide attempts to complete the contract which plaintiff was simply unable to do. Second, plaintiffs initial efforts were wasted solely by and as a direct consequence of defendant’s default on its contractual obligation to supply specifications possible of performance.4 Third, only plaintiffs excess costs in attempting to comply with the impossible specifications are recovéred here. These are out-of-pocket reliance damages. We do hold that plaintiffs failure to perform is a good defense as to plaintiffs expectancy and any other reliance costs other than such excess costs in this case. Finally, defendant’s action in supplying impossible specifications [472]*472was something defendant had no right to do under the contract.

This last factor distinguishes the case where a contractor terminated for default would seek to recover for a mere change. The Government does have the right under the contract to issue change orders.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Nauset Construction Corporation
Armed Services Board of Contract Appeals, 2025
Roxco, Ltd. v. United States
60 Fed. Cl. 39 (Federal Claims, 2004)
Westfed Holdings, Inc. v. United States
52 Fed. Cl. 135 (Federal Claims, 2002)
Clay Bernard Systems International, Ltd. v. United States
37 Cont. Cas. Fed. 76,067 (Court of Claims, 1991)
Gould, Inc. v. United States
36 Cont. Cas. Fed. 75,781 (Court of Claims, 1990)
Laka Tool & Stamping Co. v. United States
32 Cont. Cas. Fed. 73,202 (Court of Claims, 1984)
Blum v. United States
227 Ct. Cl. 555 (Court of Claims, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
650 F.2d 270, 28 Cont. Cas. Fed. 81,396, 227 Ct. Cl. 468, 1981 U.S. Ct. Cl. LEXIS 274, Counsel Stack Legal Research, https://law.counselstack.com/opinion/laka-tool-stamping-co-v-united-states-cc-1981.