Nauset Construction Corporation

CourtArmed Services Board of Contract Appeals
DecidedOctober 7, 2025
Docket61673, 61674, 61675
StatusPublished

This text of Nauset Construction Corporation (Nauset Construction Corporation) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Nauset Construction Corporation, (asbca 2025).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeals of - ) ) Nauset Construction Corporation ) ASBCA Nos. 61673, 61674, 61675 ) Under Contract No. W912SV-13-C-0007 )

APPEARANCES FOR THE APPELLANT: John J. McNamara, Esq. Elise M. Kuehn, Esq. Lane McNamara LLP Southborough, MA

APPEARANCES FOR THE GOVERNMENT: Dana J. Chase, Esq. Army Chief Trial Attorney MAJ Danielle C. Naser, JA MAJ Joshua A. Reyes, JA Trial Attorneys

OPINION BY ADMINISTRATIVE JUDGE HAMADY ON THE GOVERNMENT’S MOTION TO DISMISS

Pending before the Board is a motion filed by the Department of the Army (government) to dismiss Nauset Construction Corporation’s (Nauset) pre-termination monetary and delay claims, specifically ASBCA Nos. 61673 and 61674. 1 On May 5, 2021, the Board dismissed ASBCA No. 61675, to the extent it challenged the default termination for lack of jurisdiction because that portion of Nauset’s claim was time-barred. Nauset Constr. Corp., ASBCA Nos. 61673, 61675, 21-1 BCA ¶ 37,852 (Nauset I). The Federal Circuit affirmed the decision. Nauset Constr. Corp. v. Sec’y of the Army, 2024 WL 911865 (Fed. Cir. Mar. 4, 2024). We presume familiarity with the facts of Nauset I. 2 For the reasons stated below, we deny the government’s motion.

1 The government’s motion to dismiss does not address the remaining monetary aspects of ASBCA No. 61675, that were not addressed by the Board’s opinion in Nauset I. Accordingly, this decision is limited to ASBCA Nos. 61673 and 61674. 2 Nauset I presents the facts in greater detail. In this decision, we only discuss the facts necessary to resolve the government’s motion. STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTION

1. Nauset submitted a certified claim (ASBCA No. 61673) to the government’s contracting officer (CO) on May 12, 2017, seeking an equitable adjustment in the amount of $2,563,622 and a time extension of 598 days in compensation for various delays it attributed to the government (R4, tabs 182-85).

2. Nauset submitted a second certified claim (ASBCA No. 61674) in the amount of $291,833.84 to the CO on behalf of its subcontractor, Griffin Electric, on August 31, 2017 (R4, tab 188).

3. The government terminated the contract for default on November 17, 2017 (R4, tab 39 at 2).

4. On February 12, 2018, Nauset submitted a third certified claim (ASBCA No. 61675), contesting the validity of the default termination and requesting an equitable adjustment in the amount of $1,076,189 in costs it incurred from November 2016 through the date of the termination (R4, tab 200).

5. On June 27, 2018—222 days after the termination for default was issued— Nauset appealed the termination to the Board and its three claims for which the contracting officer failed to issue a final decision (see Notice of Appeal dtd. June 27, 2018).

6. The government filed a motion to dismiss ASBCA Nos. 61673 and 61675 for lack of jurisdiction and to dismiss Nauset’s wrongful termination claim (included as part of ASBCA No. 61675) as untimely on December 26, 2018 (gov’t mot. to dismiss dtd. December 26, 2018).

7. On May 5, 2021, the Board determined it possessed jurisdiction over ASBCA Nos. 61673 and 61675; however, it dismissed ASBCA No. 61675 to the extent it appealed the default termination for lack of jurisdiction because that portion of the claim was time-barred. Nauset I, 21-1 BCA ¶ 37,852 at 183,820-21.

8. Nauset filed a motion for reconsideration of the dismissal of its termination claim on May 26, 2021, which the Board denied on January 26, 2022. Nauset Constr. Corp., ASBCA No. 61673 et al., 22-1 BCA ¶ 38,052 at 184,769.

9. The Federal Circuit upheld the Board’s dismissal of Nauset’s termination claim on March 4, 2024. Nauset Constr. Corp., 2024 WL 911865.

2 DECISION

The Parties’ Contentions

The government moves to dismiss ASBCA Nos. 61673 and 61674 on the grounds they are barred by a valid termination for default and the doctrines of collateral estoppel and res judicata (gov’t mot. at 1, 3, 4-6; gov’t reply at 1, 35-38). 3 Nauset opposes the government’s motion, asserting, among other things, that Nauset’s termination claim was only dismissed on jurisdictional grounds and that the surviving appeals involve claims that were submitted prior to termination that are “separate and distinct from the termination.” (App. opp’n at 1-2)

Nauset’s Remaining Claims May Proceed

The government’s motion to dismiss is premised on the assumption that the Board in Nauset I upheld the default termination and, as a result, Nauset’s remaining claims “are barred by the valid termination of the contract” (gov’t mot. at 1, 3; gov’t reply at 11-12, gov’t sur-surreply at 1). The government argues that because the default termination was valid, Nauset’s pre-termination claims are barred because they do not fall within two exceptions to the general rule that a contractor’s pre-termination claims are barred by a valid termination (gov’t mot. at 4). The government argues further that “the Board would have no way to assess the merits of the remaining claims, without analyzing whether the default termination was proper . . . [because] the Contracting Officer’s termination was specifically based on Nauset’s failure to prosecute the work, failure to comply with government directions, attempted repudiation of Phase II of the project, and failure to comply with contract provisions” (gov’t reply at 36). The government contends that permitting Nauset’s remaining pre-termination claims to proceed “would result in the Board essentially litigating Nauset’s claim regarding the termination for default despite the dismissal . . . [which] could result in an inherently contradictory predicament where Nauset is litigating the very decision, they were determined to be untimely to litigate” (id.).

3 The government’s reply in support of its motion to dismiss suggests that Nauset’s response in opposition to the government’s motion to dismiss be treated as a motion for summary judgment (gov’t reply at 1; gov’t sur-surreply at 2). The Board does not read Nauset’s response in opposition to the government’s motion as a motion for summary judgment. The government’s reply in support of its motion to dismiss also appears to attempt to convert the government’s motion to dismiss to a motion for summary judgment (gov’t reply at 11-12, 22-24; gov’t sur-surreply at 2). The government’s original motion was clearly styled as a motion to dismiss, and as such, the Board’s opinion will not address any of the government’s summary judgment-related arguments in its reply brief that were not set forth in its original motion to dismiss. 3 The Board in Nauset I dismissed that portion of ASBCA No. 61675 pertaining to Nauset’s challenge to the default termination for lack of jurisdiction because its appeal was untimely. That decision was upheld by the Federal Circuit (SOF ¶ 9). Accordingly, the default termination is final and binding, even though the Board did not reach the merits of the default termination. Cf. Combined Arms Training Sys., Inc. ASBCA Nos. 44822, 47454, 96-2 BCA ¶ 28,617 at 142,891 (stating that where a default termination has not been contested, the contracting officer’s decision must be treated as final and conclusive).

The final and binding nature of the default termination means that Nauset is foreclosed from its requested relief that the default termination be converted to a termination for convenience, meaning that the termination for default stands, irrespective of whether the government’s rationale and actions behind the termination were proper. But, contrary to the government’s arguments, allowing a contractor’s pre-termination claims to survive a dismissal of a termination for default because that appeal was untimely, does not have the potential to upset the default termination.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Phillips/May Corp. v. United States
524 F.3d 1264 (Federal Circuit, 2008)
Do-Well MacHine Shop, Inc. v. The United States
870 F.2d 637 (Federal Circuit, 1989)
Laguna Hermosa Corp. v. United States
671 F.3d 1284 (Federal Circuit, 2012)
Jet, Inc. v. Sewage Aeration Systems
223 F.3d 1360 (Federal Circuit, 2000)
Laka Tool & Stamping Co. v. United States
650 F.2d 270 (Court of Claims, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
Nauset Construction Corporation, Counsel Stack Legal Research, https://law.counselstack.com/opinion/nauset-construction-corporation-asbca-2025.