Phillips/May Corp. v. United States

524 F.3d 1264, 2008 U.S. App. LEXIS 8726, 2008 WL 1808548
CourtCourt of Appeals for the Federal Circuit
DecidedApril 23, 2008
Docket2007-5139
StatusPublished
Cited by55 cases

This text of 524 F.3d 1264 (Phillips/May Corp. v. United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Phillips/May Corp. v. United States, 524 F.3d 1264, 2008 U.S. App. LEXIS 8726, 2008 WL 1808548 (Fed. Cir. 2008).

Opinion

DYK, Circuit Judge.

Plaintiff-appellant Phillips/May Corporation (“Phillips”) appeals from a decision of the United States Court of Federal Claims granting summary judgment in favor of the government. Because the Court of Federal Claims correctly determined that Phillips’s complaint was barred by res ju-dicata, we affirm.

BACKGROUND

On April 11, 2001, Phillips was awarded Contract No. N62467-01-D-0257 (“the contract”), for the design, labor, materials, and equipment necessary to construct the Religious Ministry Facility at the Naval Air Station-Joint Reserve Base (“NAS-JRB”) in Fort Worth, Texas. Under the contract, Phillips was responsible for the rehabilitation of an existing chapel and the construction of a new building next to that chapel. Notice to proceed on the contract was issued on May 23, 2001, and the project was to be completed in 265 calendar days. Phillips ultimately completed the work on June 24, 2003—more than 800 days after beginning work. The NAS-JRB accepted the completed Religious Ministry Facility. Phillips was paid $1,229,385.30 for its work; the original contract price was increased by $32,052.30 due to contract modifications.

Between July 10, 2003, and November 12, 2003, Phillips submitted to the Contracting Officer (“CO”) at ÑAS-JRB ten claims related to its work under the contract. One of these claims, submitted on November 7, 2003 (“Inspection Claim”), was for “Delay, Mal-Administration of the Contract, Overzealous Inspection and Impossibility.” J.A. at 86. The CO failed to act on any of the claims within the sixty days; this failure constituted a denial of Phillips’s claims under 41 U.S.C. § 605(c)(5), and gave Phillips the right to appeal. The claims became appealable between September 8, 2003, and January 11, 2004.

Between October 5, 2003, and January 29, 2004, Phillips appealed all but the Inspection Claim to the Armed Services Board of Contract Appeals (“Board”). Because each of the appealed claims involved less than $100,000, Phillips elected to have these claims tried pursuant to the Small *1267 Claims Accelerated Procedure, authorized under 41 U.S.C. § 607(f), which requires the Board to render a decision within 180 days whenever possible. In those appeals, Phillips sought compensation for costs incurred while performing the contract, which allegedly resulted from delay caused by the government’s conduct and from design changes demanded by the government. One of the nine appealed claims was settled while pending before the Board. The administrative judge (“AJ”) heard the other eight appeals between March 29 and April 2, 2004, and issued decisions on them from the bench. Five of the appeals were denied, and three were sustained in part and denied in part. Ultimately, the parties entered into a global settlement agreement with respect to the nine Board appeals, and the Board entered judgment in accordance with the agreement on June 30, 2005.

As of January 2006, the CO still had not issued a final decision with respect to the Inspection Claim. On January 19, 2006, Phillips filed an appeal of that claim in the Court of Federal Claims. On June 9, 2006, the CO denied the claim in its entirety. The CO’s decision determined that “pursuant to the legal principles of res judicata and collateral estoppel,” Phillips was precluded from litigating the issues raised by the Inspection Claim because they were included in its other, finally adjudicated claims. Defendant-Appel lee’s Supplemental App. at 185.

Following the CO’s decision, on October 26, 2006, the government moved for summary judgment in the Court of Federal Claims, which granted the motion. The court found that Phillips’s claim involved the same parties as the claims decided in the Board appeals, that there had been a final judgment on the merits of those appeals, and that the Inspection Claim was based on the same transactional facts as the Board appeals and should have been litigated along with those appeals. The court further determined that Phillips could have appealed the Inspection Claim along with its other claims, and that Phillips could have elected to forgo the Small Claims Accelerated Procedure on those other claims in order to litigate all its appeals together. Accordingly, the Court of Federal Claims held that Phillips was barred from litigating its claim by the doctrine of claim preclusion.

Phillips timely appealed the decision of the Court of Federal Claims. We have jurisdiction pursuant to 28 U.S.C. § 1295(a)(3).

DISCUSSION

We review the Court of Federal Claims’s decision to grant summary judgment without deference. Old Stone Corp. v. United States, 450 F.3d 1360, 1367 (Fed.Cir.2006). Whether a particular claim is barred by res judicata is a question of law, which we also review without deference. Sharp Kabushiki Kaisha v. Thinksharp, Inc., 448 F.3d 1368, 1370 (Fed.Cir.2006).

The doctrine of res judicata involves the related concepts of claim preclusion and issue preclusion. The Court of Federal Claims here relied on claim preclusion, which refers to “the effect of foreclosing any litigation of matters that never have been litigated, because of a determination that they should have been advanced in an earlier suit.” 18 Charles Alan Wright, Arthur R. Miller & Edward H. Cooper, Federal Practice and Procedure § 4402 (2d ed.2002). As the Supreme Court has explained, “when a final judgment has been entered on the merits of a case, ‘[i]t is a finality as to the claim or demand in controversy ... not only as to every matter which was offered and received to sustain or defeat the claim or demand, but as to any other admissible matter which might have been offered for *1268 that purpose.’ ” Nevada v. United States, 463 U.S. 110, 129-30, 103 S.Ct. 2906, 77 L.Ed.2d 509 (1983) (quoting Cromwell v. County of Sac, 94 U.S. 351, 352, 24 L.Ed. 195 (1876)). Claim preclusion applies when “(1) the parties are identical or in privity; (2) the first suit proceeded to a final judgment on the merits; and (3) the second claim is based on the same set of transactional facts as the first.” Ammex, Inc. v. United States, 334 F.3d 1052, 1055 (Fed.Cir.2003). The doctrine is properly applied to the final judgment of an administrative agency, such as a board of contract appeals, that “is acting in a judicial capacity and resolved disputed issues of fact properly before it which the parties have had an adequate opportunity to litigate.” United States v. Utah Constr. & Mining Co., 384 U.S. 394, 422, 86 S.Ct. 1545, 16 L.Ed.2d 642 (1966);

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Avery v. United States
Federal Claims, 2026
JORDAN v. United States
Federal Claims, 2025
Nauset Construction Corporation
Armed Services Board of Contract Appeals, 2025
Tindall v. United States
Federal Claims, 2025
Emiabata v. United States
Federal Claims, 2024
Castillejos v. Opm
Federal Circuit, 2022
Brown v. Air Force
Federal Circuit, 2022
Podlucky v. United States
Federal Claims, 2021
Crumley v. United States
Federal Claims, 2021
Barajas v. United States
Federal Claims, 2021
Bondyopadhyay v. United States
Federal Claims, 2020
First Mortgage Corporation v. United States
961 F.3d 1331 (Federal Circuit, 2020)
Fuller v. United States
Federal Claims, 2020
Stewart v. United States
Federal Claims, 2020
Scarselli v. United States
Federal Claims, 2020
Sang Kash Company
Armed Services Board of Contract Appeals, 2020

Cite This Page — Counsel Stack

Bluebook (online)
524 F.3d 1264, 2008 U.S. App. LEXIS 8726, 2008 WL 1808548, Counsel Stack Legal Research, https://law.counselstack.com/opinion/phillipsmay-corp-v-united-states-cafc-2008.